PLA_Resolution.pdf
PDF 568 KB Posted
- Solicitation number
- 2027-RFP-00201
- Issued by
- San Mateo County, California
About this file
This file is Resolution No. 081396, adopted by the San Mateo County Board of Supervisors on September 9, 2025, approving a five-year Project Labor Agreement (PLA) between San Mateo County and the San Mateo County Building and Construction Trades Council and affiliated unions. The PLA will apply to all County public works projects awarded between July 1, 2026, and June 30, 2031, that meet specified monetary thresholds: $3 million or more for projects awarded on or after July 1, 2026; $2.5 million or more for projects awarded on or after July 1, 2027; $2 million or more for projects awarded on or after July 1, 2028; and $1 million or more for projects awarded on or after July 1, 2029, with annual adjustments thereafter based on the California Construction Cost Index. The agreement includes exceptions for construction work performed by County staff, maintenance and repair work, emergency work as defined by Public Contract Code, and situations where PLA requirements are preempted by law or grant conditions.
The PLA establishes provisions for regulating work stoppages, strikes, and lockouts; guaranteeing fair wages, benefits, and employment conditions; and including apprenticeship, pre-apprenticeship, and military veteran hiring programs. Notably, the agreement does not require non-union contractor employees to join a union or pay union dues or fees as a condition of employment on covered projects. The County Executive or designee is authorized to execute the PLA and take all necessary steps to implement its terms. The resolution was unanimously approved by all five supervisors present (Jackie Speier, Noelia Corzo, Ray Mueller, Lisa Gauthier, and David J. Canepa) with no dissenting votes.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RESOLUTION NO. 081396
BOARD OF SUPERVISORS, COUNTY OF SAN MATEO, STATE OF CALIFORNIA
RESOLUTION APPROVING A PROJECT LABOR AGREEMENT
BETWEEN THE COUNTY OF SAN MATEO AND THE SAN MATEO COUNTY
BUILDING AND CONSTRUCTION TRADES COUNCIL, ALONG WITH AFFILIATED
UNIONS, WHICH SHALL APPLY TO ALL COUNTY PUBLIC WORKS PROJECTS
AWARDED OVER A FIVE-YEAR TERM, BEGINNING JULY 1, 2026, WITH AN
ENGINEER’S ESTIMATE OR CUMULATIVE BID AMOUNT ABOVE THE MONETARY
THRESHOLDS ESTABLISHED IN THE AGREEMENT, AND AUTHORIZING AND
DIRECTING THE COUNTY EXECUTIVE, OR DESIGNEE(S), TO EXECUTE THE
PROJECT LABOR AGREEMENT ON BEHALF OF THE COUNTY AND TAKE ALL
STEPS NECESSARY AND APPROPRIATE TO EFFECTUATE AND CARRY-OUT ITS
TERMS
RESOLVED, by the Board of Supervisors of the County of San Mateo, State of
California, that:
WHEREAS, a Project Labor Agreement (“PLA”) is a pre-hire collective bargaining agreement that applies to a specific construction project or series of construction projects for the duration of the project(s) and is between the owner of the project(s) and a group of unions; and
WHEREAS, the owner and unions enter a PLA before the owner solicits bids for construction of the project(s) and the PLA is included in the bid documents, and the winning bidder is required to abide by the terms of the PLA; and
WHEREAS, PLAs seek to promote the efficiency of construction operations through use of skilled labor and the peaceful settlement of labor disputes and grievances without strikes or lockouts, outcomes which can result in the timely and economical completion of public works projects and improvement of labor relations; and
WHEREAS, PLAs also seek to establish and stabilize wages, hours, and working conditions for workers employed public works projects, thereby helping to improve the quality of work and safety on such projects and increasing potential economic opportunities for residents throughout San Mateo County; and
WHEREAS, PLAs have been implemented by local government across the State and the County has utilized project-specific PLAs on specific major capital projects, including the Maple Street Correctional Center, County Office Building 3, Parking
Structure 2, the San Mateo County Health Campus, South San Francisco Wellness
Center, and the Cordilleras Mental Health Facility; and
WHEREAS, the proposed PLA with the San Mateo County Building and
Construction Trades Council and affiliated unions would apply more broadly to County public works projects awarded over a five-year term, beginning July 1, 2026, with an engineer’s estimate or cumulative bid amount above the following monetary thresholds:
$3 million or more for projects awarded on or after July 1, 2026
$2.5 million or more for projects awarded on or after July 1, 2027
$2 million or more for projects awarded on or after July 1, 2028
$1 million or more for projects awarded on or after July 1, 2029, with this threshold adjusted annually thereafter based on the California Construction Cost
Index; and
WHEREAS, the PLA provides for certain exceptions, including, without limitation, construction work performed by County staff as permitted by the Public Contract Code;
maintenance and repair work; emergency work as defined by the Public Contract Code;
and where the requirements of the PLA are preempted by law or prohibited by either a lead agency or grant condition; and
WHEREAS, the PLA, among other things, regulates work stoppages, strikes, and lock outs; helps to guarantee fair wages, benefits, and conditions of employment on projects; and includes provisions for apprenticeship and pre-apprenticeship programs and the hiring of military veterans; and
WHEREAS, the PLA does not require any employee of a non-union contractor to join a union or to pay dues or fees to a union as a condition of working on a covered project; and
WHEREAS, this Board has been presented with the PLA, a copy of which is included as Attachment A and incorporated herein by this reference and has examined and approved it as to both form and content and desires to enter the PLA.
NOW THEREFORE, IT IS HEREBY DETERMINED AND ORDERED that the
Board approves the PLA and authorizes and directs the County Executive, or designee(s), to execute the PLA on behalf of the County and take all steps necessary and appropriate to effectuate and carry-out its terms.
RESOLUTION NUMBER: 081396
Regularly passed and adopted this 9th day of September, 2025
AYES and in favor of said resolution:
Supervisors: JACKIE SPEIER
NOELIA CORZO
RAY MUELLER
LISA GAUTHIER
DAVID J. CANEPA
NOES and against said resolution:
Supervisors: NONE
President, Board of Supervisors County of San Mateo State of California
Certificate of Delivery
I certify that a copy of the original resolution filed in the Office of the Clerk of the Board of Supervisors of San Mateo County has been delivered to the President of the Board of Supervisors.
Assistant Clerk of the Board of Supervisors
| Resolution Signature Page-SUKHI.pdf |
| Certificate of Delivery |
File details come from the government source that posted it. Updated .