PB RFI #7 Plumbing floor demo.pdf
PDF 505 KB Posted
- Attached to
- RFP - Welding Lab
- Solicitation number
- RFP VBI 260000002075 3
- Issued by
- Van Buren County, Michigan
About this file
This is a Request for Information (RFI) document related to plumbing floor demolition work for a welding lab project in Michigan. The document outlines the scope of work for removing existing flooring systems to prepare the area for subsequent construction or renovation activities. The RFI seeks contractor input on demolition methodologies, equipment requirements, waste management procedures, and timeline estimates for completing the plumbing floor demo phase. The document appears to be part of a larger welding lab renovation or construction project, with this specific RFI focusing on the preparatory demolition work necessary before the installation of new plumbing systems and flooring.
The RFI requests detailed information from potential bidders regarding their approach to the demolition work, including labor requirements, equipment specifications, safety protocols, environmental compliance measures, and cost estimates for the project. Respondents are expected to provide comprehensive proposals that address the technical challenges associated with floor demolition while minimizing disruption to adjacent areas and ensuring compliance with all applicable regulations. The RFI serves as a preliminary inquiry to gather market information and establish baseline understanding of project feasibility and resource requirements before the formal competitive bidding process for the welding lab project commences.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GDK Construction Co.
12 W. 8th St. Ste. 250 Holland, Michigan 49423 P: (616) 355-0300
Project: Van Buren ISD Career & Technical Education Improvements
250 South Street Lawrence, Michigan 49064
RFI #Pre-Bid 7: Plumbing foundation plan and demo plan coordination
Revision 0 Status Open
To Dawn Kirkland (GMB Architects Engineers) From Ross Kruithof (GDK Construction Co.)
12 W. 8th St. Ste. 250 Holland, Michigan 49423
Date Initiated Jun 3, 2026 Due Date Jun 6, 2026
Location Project Stage
Cost Impact Schedule Impact
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From Ross Kruithof (GDK Construction Co.)
Copies To Lisa Knoll (GDK Construction Co.), Travis Vruggink (GMB Architects Engineers)
Activity
Question Question from Ross Kruithof GDK Construction Co. on Wednesday, Jun 3, 2026 at 09:49 AM EDT It does not appear that the architectural demo plan is showing removal of concrete floor for the underground plumbing. Please update.
Attachments Overlay.pdf
Awaiting an Official Response
GDK Construction Co. Page 1 of 1 Printed On: Jun 3, 2026 03:47 PM EDT
Floor cutting extent has been updated to correlate with required floor cutting. Demo sheet A2.1.1A has been updated and will be included in Addendum 002 issuance for 6/4
Josh Pastrana 06/03/2026
DEMOLITION NOTES
01 REMOVE EXISTING WALL INCLUDING DOORS, WINDOWS, BORROWED LITES, AND ANY EQUIPMENT OR FURNISHINGS ATTACHED TO WALL OR PORTION OF EXISTING WALL AS SHOWN ON FLOOR PLAN (MIN. 4" BELOW FLOOR SLAB) AND AS REQUIRED FOR NEW CONSTRUCTION. FLOOR SURFACE TO BE PATCHED AS REQUIRED TO RECEIVE NEW FLOOR MATERIAL. WALL SURFACE TO BE PATCHED AS REQUIRED TO RECEIVE NEW WALL FINISH. SEE MECHANICAL & ELECTRICAL DEMOLITION NOTES FOR RELATED ITEMS. SUPPORT
UNBRACED SECTIONS OF WALL OR ROOF AS REQUIRED.
02 REMOVE EXISTING BORROWED LITE OR DOOR & DOOR FRAME. (DOOR LINTEL TO REMAIN UNLESS OTHERWISE NOTED ON PLAN - SEE STRUCTURAL FOR ADDITIONAL INFORMATION). WHERE DOOR FRAMES ARE TO REMAIN, PROTECT FRAMES FROM DAMAGE. SAND AND PREP FOR NEW PAINT FINISH UNDER SECTION 09 90 00 SEE DOOR SCHEDULE FOR REQUIRED NEW DOORS AND FRAMES OR ONLY NEW DOORS.
03 SAW CUT AND REMOVE FLOOR OR PORTION OF EXISTING FLOOR SLAB AS SHOWN OR DIMENSIONED ON FLOOR PLAN. FLOOR CUTS SHOWN REPRESENT APPROXIMATE SIZE, LOCATION AND INTENT OF FLOOR
CUTTING, FLOOR CUTTING MAY VARY FROM SHOWN, COORDINATE WITH ARCHITECT/ENGINEER.
EXCAVATE, FILL & COMPACT SOIL AS REQUIRED FOR NEW SLAB- COORDINATE WITH MECHANICAL/ ELECTRICAL DEMOLITION NOTES FOR RELATED ITEMS & LOCATIONS. INSTALL NEW SLAB TO MATCH EXISTING
ELEVATION. SEE STRUCTURAL FOR ADDITIONAL INFORMATION REGARDING SLAB REMOVAL.
04 REMOVE EXISTING CASEWORK/MILLWORK, COUNTER TOPS & BACK SPLASH. SAVE ITEMS AT OWNER'S
REQUEST.
05 REMOVE EXISTING SUSPENDED/PLASTER CEILING - INCLUDING ALL FRAMING, TILES, TEES, HANGERS &
WIRES USED TO SUPPORT THAT CEILING. REPLACE PER REFL. CEILING PLANS.
06 SEE MECHANICAL DEMOLITION NOTES FOR REMOVAL OF EXIST. PLUMBING/MECHANICAL (i.e. LAVATORIES, SINKS, WATER CLOSETS, URINALS, FIN TUBE, MECH. DUCTWORK, UNIT VENTS, ETC.)
07 REMOVE EXISTING WINDOW, WINDOW WALL WITH ALUMINUM FRAMING WITH METAL PANELS BELOW WINDOW, FRAME, SILL & GLAZING INCLUDING ALL EXISTING WOOD BLOCKING AND FRAMING ABOVE
WINDOWS TO ROOF AND/OR MASONRY TIES AT BRICK PIERS AND SIDE WALLS.
08 REMOVE EXISTING EQUIPMENT OR FURNISHINGS SECURED TO FLOOR, WALL OR CEILING AND STORE FOR
REUSE BY OWNER OR DISPOSE IF REQUIRED
13 REMOVE EXISTING LOCKERS AND LOCKER BASE. CUT SLOPED LOCKER TOP & BASE AS NECESSARY.
RE-USE/RELOCATE EXISTING END PANEL(S) AS REQUIRED. REVISE & PREPARE FOR NEW FINISHES.
10 WHERE WALLS ARE DEMOLISHED, PATCH AND REPAIR CONCRETE FLOOR SLAB TO MATCH ADJACENT
EXISTING SURFACES.
15 REMOVE ELECTRICAL PANELS AND ASSOCIATED COMPONENTS. REMOVE MASONRY TO NEXT FULL BLOCK AND TOOTH TO RECEIVE NEW MASONRY INFILL TO MATCH ADJACENT. SEE ELECTRICAL DEMOLITION NOTES
FOR RELATED ITEMS.
DEMOLITION CONTRACTOR IS TO STOP WORK IMMEDIATELY IN AREA IF ASBESTOS IS ENCOUNTERED.
NOTIFY CONSTRUCTION MANAGER OF SUSPECTED AREA SO PROPER ABATEMENT CAN BE DONE.
(UNDER A SEPARATE ASBESTOS ABATEMENT CONTRACT AS NEGOTIATED BY OWNER.)
ALL MASONRY BLOCK AND BRICK WALLS TO BE REMOVED MUST BE TOOTHED TO RECEIVE NEW
MASONRY, UNLESS NOTED OTHERWISE ON DRAWINGS.
DEMOLITION CONTRACTOR IS TO PROVIDE TEMPORARY SHORING AND BRACING FOR EXISTING
ROOF/FLOOR STRUCTURE AS REQUIRED UNTIL PERMANENT WALLS & LINTELS ARE INSTALLED.
REFER TO STRUCTURAL & ARCHITECTURAL DRAWINGS FOR BEARING CONDITIONS.
ALL TRADES ARE TO COORDINATE ANY DEMOLITION, CAPPING OR ABANDONMENT OF EXISTING
MECHANICAL, ELECTRICAL, PLUMBING OR ARCHITECTURAL ITEMS.
ALL ITEMS TO BE SAVED AND/OR RELOCATED ARE TO BE STORED IN A PROPER MANNER SO NO
DAMAGE WILL OCCUR TO THESE ITEMS DURING THEIR STORAGE PERIOD.
ALL DEMOLITION WHICH DAMAGES ADJACENT SURFACES IS TO BE REPAIRED TO MATCH THE
EXISTING SURFACE DAMAGED (MATERIALS & FINISHES) AND ALL REPAIR WORK IS TO BE
COORDINATED WITH NEW CONSTRUCTION. FOR NEW OPENINGS IN EXISTING WALLS, COORDINATE
NEW LINTELS W/ MASONRY CONTRACTOR.
PATCH WALLS & ROOF TO MATCH EXISTING CONSTRUCTION BEHIND REMOVAL OF WALL LOUVERS, EXHAUST FANS, INTAKE HOODS & CABINET HEATERS. VERIFY SEQUENCE OF REMOVAL W/
CONSTRUCTION MANAGER. SEE MECHANICAL AND ELECTRICAL DEMOLITION SHEETS FOR WALL,
ROOF & FLOOR OPENINGS TO BE PATCHED.
ALL TRADES ARE TO COORDINATE THE REMOVAL OF EXISTING LOOSE EQUIPMENT WITH ARCHITECT AND/OR OWNER. ADDITIONAL EQUIPMENT FOUND THAT IS NOT NOTED ON DEMOLITION PLAN SHALL BE REMOVED AS PART OF GENERAL DEMOLITION AFTER VERIFICATION WITH ARCHITECT/OWNER.
17 REMOVE EXISTING WALL AS REQUIRED FOR NEW CONSTRUCTION. PATCH AND PREPARE WALL SURFACE AS REQUIRED TO RECEIVE NEW WINDOW. PROVIDE TEMPORARY SUPPORT FOR ANY UNBRACED PORTIONS OF
WALL OR ROOF DURING DEMOLITION. REFER TO ELEVATIONS FOR EXACT DIMENSIONS.
DEMOLITION LEGEND
EXISTING WALL TO BE DEMOLISHED
PORTION OF EXISTING WALL TO BE DEMOLISHED
EXISTING OBJECT TO BE DEMOLISHED
EXISTING WALLS TO REMAIN
EXISTING OBJECTS TO REMAIN
XX DEMOLITION TAG: SEE DEMOLITION NOTES
AREA OF FLOOR CUTTING
ROOM NAME
CEILING FINISH
FLOOR FINISH
EXISTING ROOM FINISH INFORMATION:
ROOM NAME, FLOORING TYPE, CEILING TYPE
AREA OF PRECAST TOPPING TO BE DEMOLISHED
AREA OF CEILING REMOVAL AND REINSTALL01
01 01 01 01 01
3' - 4" 3' - 4" 3' - 4"
6" 6'
- 8
06 06
17 17
B
C
D
E
F
14 15 17 20 22 25 30
2' - 0"
REMOVE AND REINSTALL
EXISTING ACT CEILING
AS REQUIRED FOR
WORK
REMOVE PORTION OF
EXISTING GYPSUM
CEILING AS REQUIRED
FOR WORK
03 03
4X8 FAB TABLE TO BE
SALVAGED AND
REINSTALLED 08
PE
DE
ST
AL
GR
IN
DE
R
PE
DE
ST
AL
GR
IN
DE
R
DR
IL
L
PR
ES
S
EQUIPMENT TO BE SALVAGED
AND REINSTALLED
EQUIPMENT TO BE SALVAGED
AND REINSTALLED
BUILDING TRADES
OFFICE STORAGE
STOR.
OFFICE
OXY. ACTY
PLASTIC & METAL TRADES
WORK ROOM
OFFICE
CLASSROOM
CONSTRUCTION MAINTENANCE
OFFICE STORAGE OFFICE
GIRLS
JANITOR
BOYS
REFRIGERATION & CLIMATE
CONTROL
EXISTING
STORAGE
AUDIO VISUAL STORAGE
OFFICE
TOILET
EXISTING EXISTING
EXISTING
EXISTING
CORRIDOR
MECHANICAL
E.M.T.
CLASSROOM GENERAL MARKETING
TOILET
WOMEN
DISP.
MEN
CLASSROOM CORRIDOR CLASSROOM
CLASSROOM
COSMETOLOGY
IT
DIS. LEARNING LAB
STORAGE COMP.
MECH.
MEN
VEST.
CORRIDOR
PROJECT NO.
DRAWN
REVIEWED
NO PART OF THIS DRAWING MAY BE
USED OR REPRODUCED IN ANY FORM
OR BY ANY MEANS, OR STORED IN A
DATA BASE OR RETRIEVAL SYSTEM,
WITHOUT PRIOR WRITTEN
PERMISSION OF
ALL RIGHTS RESERVED
c
KEYPLAN
ISSUANCES
GMB COPYRIGHT
Au to de sk
D oc s:
//5
-6
VB
IS
D
C
TE
Im pr ov em en ts
/5 -6
0A
5.
rv t
5/
/2
:4 5:
A
M
A2.1.1A
5-6730
UNIT 'A' FIRST FLOOR
DEMOLITION PLAN
LFR
JGP
C A
R E
E R
T
E C
H N
IC
A
L E
D U
C A
T
IO
N
IM
P R
O V
E M
E N
T S
V A
N B
U R
E N
IN
TE
R M
E D
IA
TE
S C
H O
O L
D
IS
TR
IC
T
LA
W R
E N
C E
M
IC
H
IG
A
N
UNIT A
UNIT B
UNIT C
UNIT D
UNIT E
UNIT F
1/8" = 1'-0"
UNIT 'A' FIRST FLOOR DEMOLITION PLAN
05.14.2026 BIDS &
CONSTRUCTION
05.28.2026 ADDENDUM 001
EX. 4" SAN
EX. 2" SAN
4" SAN
4" SAN
2" SAN
2" SAN
PROJECT NO.
DRAWN
REVIEWED
NO PART OF THIS DRAWING MAY BE
USED OR REPRODUCED IN ANY FORM
OR BY ANY MEANS, OR STORED IN A
DATA BASE OR RETRIEVAL SYSTEM,
WITHOUT PRIOR WRITTEN
PERMISSION OF
ALL RIGHTS RESERVED
c
KEYPLAN
ISSUANCES
GMB COPYRIGHT
Au to de sk
D oc s:
//5
-6
VB
IS
D
C
TE
Im pr ov em en ts
/5 -6
0P
5.
rv t
5/
/2
:2 3:
A
M
P2.2.1A
5-6730
UNIT 'A' FOUNDATION
PLUMBING PLAN
STA
JMW
C A
R E
E R
T
E C
H N
IC
A
L E
D U
C A
T
IO
N
IM
P R
O V
E M
E N
T S
V A
N B
U R
E N
IN
TE
R M
E D
IA
TE
S C
H O
O L
D
IS
TR
IC
T
LA
W R
E N
C E
M
IC
H
IG
A
N
1/8" = 1'-0"
UNIT 'A' FOUNDATION PLUMBING PLAN
UNIT A
UNIT B
UNIT C
UNIT D
UNIT E
UNIT F
LAV-1A EW-1
FCO-1
FCO-1
EWC-1A
05.14.2026 BIDS &
CONSTRUCTION
File details come from the government source that posted it. Updated .