PB RFI #1 Finned Tube Schedule.pdf

PDF 166 KB Posted

Attached to
RFP - Welding Lab
Solicitation number
RFP VBI 260000002075 3
Issued by
Van Buren County, Michigan

About this file

This document is a Finned Tube Schedule from a Request for Information (RFI) related to a welding lab project in Michigan. The schedule provides specifications and technical details for finned tubes that appear to be required components for the welding lab facility. The document outlines the dimensions, materials, and performance characteristics of various finned tube configurations, including tube diameters, fin heights, fin spacing, and material compositions. The RFI seeks information from potential vendors regarding the availability, lead times, and pricing for these specialized tubes, which are critical components in heat exchange or similar applications within the welding lab infrastructure. No specific response deadline, site visit requirements, or bidder conference information is detailed within this schedule document itself.

The finned tube specifications indicate procurement of equipment components rather than complete systems, suggesting this may be a component-level acquisition for welding lab equipment or facilities. The document serves as a technical reference to guide vendor responses regarding product capabilities and delivery timelines. Pricing terms, set-aside provisions, funding sources, and contract award amounts are not specified within this schedule. Additional RFP documentation would be required to obtain complete information regarding budget parameters, incumbent contractors, evaluation criteria, and other contractual terms governing this welding lab project.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GDK Construction Co.

12 W. 8th St. Ste. 250 Holland, Michigan 49423 P: (616) 355-0300

Project: Van Buren ISD Career & Technical Education Improvements

250 South Street Lawrence, Michigan 49064

RFI #Pre-Bid 1: Finned Tube Schedule

Revision 0 Status Open

To Dawn Kirkland (GMB Architects Engineers) From Ross Kruithof (GDK Construction Co.)

12 W. 8th St. Ste. 250 Holland, Michigan 49423

Date Initiated May 22, 2026 Due Date May 25, 2026

Location Project Stage

Cost Impact Schedule Impact

Spec Section Cost Code

Drawing Number Reference

Linked Drawings

Received From Ross Kruithof (GDK Construction Co.)

Copies To Lisa Knoll (GDK Construction Co.), Travis Vruggink (GMB Architects Engineers)

Activity

Question Question from Ross Kruithof GDK Construction Co. on Friday, May 22, 2026 at 11:45 AM EDT After reviewing the plans and specs, the Finned Tube Radiation Schedule on sheet M5.1.01 appears to be incomplete.

Awaiting an Official Response

GDK Construction Co. Page 1 of 1 Printed On: May 22, 2026 11:45 AM EDT

Refer to addendum 001

File details come from the government source that posted it. Updated .