Pavement Report CO FLAP MES 18(1) 18 Road 20240613.pdf
PDF 5 MB Posted
- Attached to
- CO FLAP MES 18(1) 18 Road Federal contract opportunity
- Solicitation number
- 6982AF24B000013
About this file
This document is a pavement and materials report for the CO FLAP MES 18(1) 18 Road project in Mesa County, Colorado. The report provides pavement recommendations and design inputs based on a field investigation and laboratory testing. The existing roadway consists of old, deteriorated asphalt pavement with extensive cracking and patching. A full reconstruction is recommended, with a pavement section of 3 inches of hot-mix asphalt concrete over 8 inches of aggregate base course. The report includes traffic data, soil properties, corrosion potential, and recommended bid items. The related federal contract opportunity is for the reconstruction of approximately 6 miles of 18 Road, including earthwork, drainage, fencing, signing, and other related work, with an estimated cost range between $10-20 million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Tabulation.pdf | ||
| Bid Opening Summary.pdf | ||
| QnA 8.19.24.pdf | ||
| A003.pdf | ||
| A002.pdf | ||
| QnA 8.15.24.pdf | ||
| QnA 8.8.24.pdf | ||
| A001.pdf | ||
| QnA 8.1.24.pdf | ||
| CO FLAP MES 18(1) 18 Road Final Hydraulics Report with Addendum.pdf | ||
| CO FLAP MES18(1) Plans Final - 06_20_2024.pdf | ||
| 6982AF24B000013.pdf | ||
| CO FLAP MES18(1) Cross Sections Final - 06_20_2024.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CO FLAP MES 18(1) 18 Road
PAVEMENT AND MATERIALS REPORT
Revised June 12, 2024
Report Prepared By
U.S. Department of Transportation Federal Highway Administration
Central Federal Lands Highway Division Lakewood, Colorado ii
Written by: Marty Fey, Pavements & Materials Engineer
Revised by:
Darin Lockhart, Pavements & Materials Engineer
Reviewed and approved for distribution by:
Mike Voth, Pavements and Materials Team Lead
Distribution:
Project Development Project Management Construction Materials Pavements Geotech iii
TABLE OF CONTENTS
I. INTRODUCTION
II. CLIMATE
III. EXPLORATION
IV. EXISTING PAVEMENT & SOILS
V. PAVEMENT DESIGN CALCULATION INPUTS
VI. PAVEMENT RECOMMENDATIONS & DISCUSSION
VII. MATERIALS RECOMMENDATIONS
APPENDICES
A – Location Map B – Laboratory Reports and Boring Log C – Photographs D – AASHTO ’93 Flexible Pavement Design E – PG LTPPBIND Software F – Preliminary Pavement Recommendation Memo
I. INTRODUCTION
This report is written to provide pavement and materials recommendations for CO FLAP MES 18(1) 18 Road. The project is located north of Fruita, Colorado in Mesa County. 18 Road runs from the Government Canal on the south end of the project to the BLM North Fruita Campground on the north end. The project will include realignments, widening, grade changes, and a new roadway surface. See Appendix A for location map.
The Preliminary Pavement Recommendations Memo was issued in March 2021. The memo provided the pavement recommendations as well as the proposed pay items. This memo is found in Appendix F. The pavement recommendations have been finalized and are discussed in Part VI of this report.
Revision to the final document include updating the report date, updating the results on corrosivity ratings based on soil resistivity, pH and sulfate and chloride exposure and Appendix B Laboratory Reports to include AASHTO T 290 Sulfate Content and AASHTO T 291 Chloride Content test results revised on 02/18/2021.
II. CLIMATE
Climate data was obtained from noaa.gov. This data is summarized in Table 1 below.
The average annual precipitation for this area is approximately 9.66 inches. The project is in a high desert area and at an elevation that receives both snow and rain, dependent upon the time of year.
Table 1: Weather Data
Month Average
HIGH (°F)
Average
LOW (°F)
Average
MEAN (°F)
Average PRECIP. (in)
January 38.2 13.4 25.8 0.63 February 45.8 20.9 33.3 0.65
March 57.5 28.6 43.0 0.93 April 66.1 35.1 50.6 0.85 May 76.3 44.0 60.2 0.75 June 86.9 51.9 69.4 0.58 July 92.7 59.0 75.8 0.69
August 89.6 57.4 73.5 0.89 September 80.9 47.0 63.9 1.03
October 67.7 35.1 51.4 1.23 November 52.4 24.9 38.6 0.74 December 39.8 16.6 28.2 0.69
III. EXPLORATION
On June 9th, 2020 CFLHD pavement & material engineer Marty Fey completed a field investigation which included boring and subgrade sampling. DA Smith Drilling was hired through the CFLHD BPA to assist with the field investigation. A CME 55 track-mounted drill rig with a 6” O.D. solid stem auger was used to complete the borings. Pavement borings were logged at 16 locations, subgrade samples were collected and tested in the laboratory. CFL personnel logged the borings; this included depth of boring, visual soil classification, and pavement thickness when applicable. Boring locations, test results, and other information is shown in Appendix B.
IV. EXISTING PAVEMENT & SOILS
The existing roadway was observed to consist of old, oxidized asphalt pavement with high severity fatigue cracking, large areas of patching, chip seals, and poorly performing gravel surfaces extending throughout the length of the project. Due to highly variable existing sections and large amount of embankment work, a full reconstruction is recommended for this project. Because this project is located in a high desert area, boulders and cobbles may be encountered during construction.
Pavement thickness was found to be 0 to 6.5 inches in depth at the locations drilled, supported by 0 to 6 inches of aggregate road base.
Drilling efforts were relatively easy. The subgrade materials encountered are of moderate quality. The subgrade soils encountered consisted primarily of silty and clayey sands to sandy clays and were classified primarily as A-2-4(0) and A-4. Subgrade soils exhibited low plasticity and had R-values of 14 to 48.
3 samples were used for estimating the corrosion potential through the following tests Soil Resitivity, pH, Water Soluble Sulfate Content and Water Soluble Chloride Content.
Soil Resistivity for 3 samples were measured at 730, 800 and 660 ohm-cm indicating corrosive to extremely corrosive soils, where less than 1000 ohm-cm is considered extremely corrosive based on Roberge (2012).
pH values were measured at 7.9 for all 3 samples which indicates a normal range for corrosion potential.
Sulfate Content for the 3 samples were measured at 3,620, 1240 and 2,440 ppm which is within the range of 1,500 – 10,000 which is considered Severe (S2).
Chloride Content for the 3 samples were measured at 47, 53 and 128 ppm chloride contents greater than 500 ppm are corrosive to ferrous materials. The measured values are less than what is considered corrosive.
See the laboratory reports and boring logs in Appendix B for more information. Ratings and classifications are based on standard industry criteria.
V. PAVEMENT DESIGN CALCULATION INPUTS
Design Parameters
Traffic counts were provided with the FLAP application and were used to develop ESAL estimates. An average daily traffic (ADT) of 259 and a truck factor of 7% class 5, resulted in a calculated cumulative equivalent single axel load (ESALs) of 50,000 for a 20-year period. The assumptions made in the ESAL calculations as well as related design factors are included in Appendix D. Design factors used in the ESALs calculations as well as the structural coefficients were taken from the CFLHD Project Development Design Manual (PDDM), Chapter 11.
Roadbed Soil Resilient Modulus
The soil resilient modulus was converted from R-Values, AASHTO T 190, using the following equation:
Resilient Modulus (psi) = 10[ ( S
+ 18.72 ) / 6.24 ] where S1 = [(R-Value – 5) / 11.29] + 3
The average R-value was found to be 31. However, due to high variability in in the subgrade, an R-value of 15 was selected to generate a design resilient modulus of 5,000 psi.
VI. PAVEMENT RECOMMENDATIONS & DISCUSSION
Utilizing AASHTO 93 Flexible Pavement Design (Appendix D), a 20-year pavement design required a Calculated Design Structural Number (SN) of 2.21. After evaluating alternatives and performing various iterations, the following is the recommended pavement structural section:
Table 2: Recommended Pavement Section Layer Thickness
HACP 3 inches (two lifts) Aggregate Base Course 8 inches
SN = 2.28
VII. MATERIALS RECOMMENDATIONS
Selection of Asphalt Binder
LTPPBind software was utilized to assist in the selection of asphalt binder. The information presented in LTPPBind is shown in Appendix E. LTPPBind indicated that a PG 64-22 binder should be used. Consideration was given to the location of the project as well as performance of past projects in similar conditions.
Prime and Tack Coats, Blotter and Fog Seal
Prime Coat and Blotter are recommended for this project. A tack coat applied between pavement lifts is recommended. It is also recommended that a fog seal be applied to the final surfacing.
Drainage and Subexcavation
During the field investigation, areas of pavement distress were present. However, they appeared to be caused due to fatigue and age. No major water damage or drainage problems pertaining to the existing traveled way were observed. If any drainage issues are encountered, the scope of the project allows for partial reconstruction. A quantity of 100 cubic yards of subexcavation should be included in the contract. This quantity should remain in the Contract in the event that areas in need of repair are encountered.
Bid Items
Suggested FP-14 pay items for the proposed structural section are shown in Table 3 below.
Table 3: Recommended Pay Items Item Number Item Description Unit
20402-0000 Subexcavation CUYD
30101-0000 Aggregate Base TON
40101-0600 Asphalt Concrete Pavement, Gyratory Mix, ½” Nominal Max Size Aggregate, 0.3 to < 3 Million ESAL
TON
40105-3000 Antistrip Additive Type 3 TON
40601-0000 Fog Seal TON
41101-1000 Prime Coat, Method 1 TON
41105-0000 Blotter TON
41201-0000 Tack Coat TON
APPENDICES
A – Location Map
B – Laboratory Reports and Boring Log
C – Photographs
D – AASHTO ’93 Flexible Pavement Design
E – PG LTPPBind Software
F – Preliminary Pavement Recommendation Memo
Appendix A: Location Map
Appendix B: Laboratory Reports and Boring Logs
Project:
Sample Number
Station or Location
Offset from CL
Date Sampled
Depth of Bore
Container Type
Pavement/ABC Thickness R‐Value Class Liquid
Limit/PI Resistivity, ohm.cm pH Sulfate % Chloride %
0 to 2"
2" to 5" CL / A‐4 (2) 5" to 5'
0 to 5"
5" to 8"
8" to 5'
0 to 3"
3" to 5"
8" to 5'
0 to 6"
6" to 5' 58 SM / A‐1‐b (0)
0 to 5'
22 CL‐ML / A‐4 (4)
0 to 4"
4" to 4.5' SC‐SM / A‐4 (0) 4.5' to 5'
0 to 5"
5" to 5'
0 to 4"
4" to 6" 24 CL / A‐4 (3) 6" to 5'
0 to 6.5"
6.5" to 12.5" CL / A‐4 (3) 12.5" to 5'
0 to 1"
1" to 4" 50 SM / A‐4 (0) 4" to 5'
0 to 0.5"
0.5" to 1' 55 1' to 5'
0 to 0.5"
0.5" to 3"
3" to 1.5'
1.5' to 5'
0 to 1"
1" to 3" 22 3" to 5'
0 to 1"
1" to 2' 23 CL / A‐4 (2) 2' to 5'
0 to 6"
6" to 1.5' SC / A‐4(0) 1.5' to 5'
0 to 5"
5" to 2'
2' to 3.5'
3.5' to 5'
Clay Sandy, Brown
Aggregate Base Course, Brown Sand Silty, Brown
4" / 2"
34 SM / A‐4 (0)
P‐8 2.5 Mi N of Gvmt Canal
6' Rt 6/9/2020 5' 5‐gal bucket
Asphalt Classification, R‐ValueAggregate Base Course, Brown
Clay Sandy, Brown
CME 55 track mounted (6"O.D. SSA)
DA Smith Pavement Investigation ‐ Shallow Borings and Cores ‐ Log & Sampling Summary
7.9
7.9
7.9
4" / 0"
5" / 0"
6.5" / 6"
1" / 3"
0.5" / 0"
0.5" / 2.5"
0" / 5"
1" / 2"
ML / A‐4 (0)
SC / A‐6 (2)
SC / A‐4 (1)
1" / 0"
23 / 8
6.0 Mi N of
Gvmt Canal
2' Lt Sand Silty, Brown
Sand, Brown
P‐13 4.5 Mi N of Gvmt Canal
4' Lt 6/9/2020 5' 5‐gal bucket
Chip Seal Classification, R‐Value
P‐14 5.0 Mi N of Gvmt Canal
Classification, R‐Value
Gravel Sandy, Brown P‐16
P‐11 3.5 Mi N of Gvmt Canal
P‐9 3.0 Mi N of Gvmt Canal
1' Lt 6/9/2020 5' 5‐gal bucket
Asphalt
Sand Clayey, Brown Silt Sandy, Brown
5' 5‐gal bucket
Asphalt Classification, R‐ValueSilt Sandy, Brown
5‐gal bucket
Chip Seal Classification, R‐Value
5‐gal bucket
Classification, R‐Value, Resistivity and pH
P‐2
0.15 Mi N
of Gvmt Canal
4' Rt 6/9/2020 5' 5‐gal bucket
Asphalt Classification Patched AreaAggregate Base Course, Brown
Sand Silty, Brown
P‐4 1.1 Mi N of Gvmt Canal
1' Rt 6/9/2020
Sand Silty, Brown Classification, R‐Value, Resistivity and pH
Culvert
5'
P‐6
P‐5
1.5 Mi N of
Gvmt Canal
5‐gal bucket
30' Lt
0.6 Mi N of
Gvmt Canal
Asphalt
Clay Sandy, Brown ClassificationAggregate Base Course, Brown
Sand Silty, Brown
P‐7 2.0 Mi N of Gvmt Canal
2' Lt 6/9/2020
Comments
30' Lt of Ceterline
Testing Requested
CO FLAP MES 18(1) 18 Road Contractor:
Logged By: Equipment:Sampled By:Marty Fey Marty Fey
6/9/20202' Rt
0.1 Mi N of
Gvmt Canal
Boring Observations (grey = sample depth )
Asphalt Aggregate Base Course, Brown Sand Silty, Brown
Asphalt P‐3 0.5 Mi N of
Gvmt Canal 1' Lt 6/9/2020
2" / 3"
5" / 3"
Classification, R‐Value
Classification, R‐Value, Resistivity and pH
Culvert
5‐gal bucket
6/9/2020
Gravel, Brown 5' 0" / 6"
N/A
5' 5‐gal bucket
Classification, R‐Value
Sand Silty, Brown
3" / 2"
5‐gal bucket
6/9/2020 5' 5‐gal bucket
Gravel w/ RAP, Gray
Classification, R‐Value
6/9/2020 Clay Sandy, Brown
Aggregate Base Course, Brown
Classification, R‐Value
5' Lt 6/9/2020 5' 5‐gal bucket
Chip Seal
P‐10 3.2 Mi N of Gvmt Canal
6/9/20204' Rt 5'
P‐12 4.0 Mi N of Gvmt Canal
3' Lt 6/9/2020 5'
5'
4' Rt
Chip Seal
Sand Clayey, Brown
Aggregate Base Course, Brown Silt Sandy, Brown
Chip Seal Aggregate Base Course, Brown
Clay Sandy, Brown
2' Rt
P‐1 5' 5‐gal bucket
6/9/2020 5' 5‐gal bucket
Classification
Clay Sandy, Brown Silt Sandy, Brown
P‐15 5.5 Mi N of Gvmt Canal
2' Rt 6/9/2020 5' 5‐gal bucket
Gravel w/ RAP, Gray Classification 0" / 6"Gravel w/ Cobbles, Gray Brown
Silt Sandy, Brown
17 23 / 9
33 / 17
NV / NP
NV / NP
23 / 7
21 / 6
23 / 9
24 / 10
CL / A‐6 (9)
14 CL / A ‐4 (0)
18 / 3
NV / NP
19 27 / 13
25 / 10
24 / 9
32 23 / 8SC / A‐2‐4 (0)
23 / 8
Appendix C: Photographs
Photo 1: 18 Road, Typical Pavement
Photo 2: Start of project
Photo 3: Asphalt Pavement
Photo 4: Aggregate Surfacing
Photo 5: Aggregate Surfacing
Photo 6: Typical Roadway Prism
Photo 7: Large Culvert
Photo 8: Washboarding
Photo 9: End of Project
Appendix D: AASHTO ’93 Flexible Pavement Design
AASHTO FLEXIBLE PAVEMENT DESIGN
Layer Thickness Determination Using Trial and Error
Layer Drainage Layer Layer No. Description Coefficient, ai Coefficient, mi Thickness, in SN
(topmost) Layer 1 AC Layer 0.44 1.00 3.00 1.32 Layer 2 FDR or ABC 0.12 1.00 8.00 0.96 Layer 3 FDR w/ Cement 0.22 1.00 0.00 0.00 Layer 4 Gran. Subbase 0.12 1.00 0.00 0.00 Layer 5 Select Borrow 0.08 0.90 0.00 0.00 Layer 6 0.00 Layer 7 0.00
(bottommost) Layer 8 0.00 Subgrade Subgrade N/A N/A N/A N/A
AC Layer 401 = 0.44 Trial SN 2.28 403 = 0.40
CAB 301 = 0.14 Design SN to Match 2.21 Subbase/Minor agg 302 = 0.12 FDR w/ Cement 305 = 0.22 FDR 304 = 0.12 Design is sufficient Select borrow 204 = 0.06 to 0.08 (Refer to Exhibit 11.2-C in Chapter 11 of PDDM for additional guidance on coefficients)
AASHTO FLEXIBLE PAVEMENT DESIGN
SN Determination
Design Inputs W18 = 50,000 ESALs Applications Over Design Period Typ. Range 50k to 10 million
R = 75 % Reliability Typ. Range 75 to 95%
So = 0.49 Standard Deviation AASHTO Standard
MR = 5,000 psi Subgrade Resilient Modulus Typ. Range 3000 to 15000 psi
Pi = 4.2 Initial Serviceability Typ. Range 4.2 to 4.4
Pt = 2 Terminal Serviceability Typ. Range 2.0 to 3.0
DESIGN SN = 2.21
R-Value = 14 S1 = 3.797 MR = 4060 R-Value = 48 S1 = 6.809 MR = 12335
R‐Value Correlation to Resilient Modulus*
Only change the R-values in C4 or C5. The rest is automatically calculated.
*CDOT method. Similar to results from Figure FF.6 in Volume 2 of AGDPS and used by CFLHD.
ADT 259 Annual Growth R0.02 Design Years 20
Directional Distribution
0.6
Lane Distribution
Classification Percent Truck Factor
Growth Factor ADT Yr 1 Design Lane ESALs ADT at N
Autos 53.0% 0.0006 137 0 204 Values Pickups, Vans 40.0% 0.004 24.29737 104 2205 154
385 (calculated) Class 4 buses 0.0% 1.5 24.29737 0 0 0 259 Class 5 trucks/RVs 7.0% 0.5 24.29737 18 48236 27 2020 Class 6 0.0% 1 24.29737 0 0 0 2040 Class 8 0.0% 1.5 24.29737 0 0 0
2 Class 9 0.0% 2 24.29737 0 0 0 100.00% 50441 385
(118 ADT * 9 mo + 681 ADT * 3 mo) / 12 month = 259 AADT (refer to Exhibit 11.2‐A in the PDDM for additional guidance on truck factors)
GR = Growth Rate (%)
Future ADT Calculation ADTf = ADTi (1 + GR)(F‐I)
ADTf = Average daily traffic for future year ADTi = Average daily traffic for initial year
I = Initial year for ADT F = Future year for ADT
Appendix E: PG LTPPBind Software
BindReport‐5Closest.txt
Five Closest Weather Stations For Latitude/Longitude= 39.126/108.736 Report Date: 3/19/2021 (LTPPBind V3.0 Alpha)
18 Road
General A=3 km B=5 km C=16 km D=26 km E=32 km Station ID CO1772 CO3146 CO3488 CO3489 CO6266 County/District mesa mesa mesa mesa mesa Weather Station colorado natl m fruita 1 w grand junction grand junction palisade Elevation, m 1637 1269 1371 1348 1362 Latitude, Longitude 39.1 ,108.73 39.17 ,108.75 39.1 ,108.55 39.05 ,108.45 39.12 ,108.35 Last Year Data Available 1997 1997 1997 1997 1997
Air Temperature Mean ( Std, N ) Mean ( Std, N ) Mean ( Std, N ) Mean ( Std, N ) Mean ( Std, N ) High Temperature 35.9 (13,34) 36.4 (10,33) 36.9 (13,35) 36.2 (13,34) 37.6 (15,32) Low Temperature ‐17.7 (39,35) ‐23 (60,34) ‐19.7 (49,35) ‐18.6 (46,34) ‐17.1 (47,32) Low Temperature Drop 22.5 (27,35) 28 (23,34) 22.4 (22,35) 24.8 (23,34) 24.7 (24,32) Degree‐Days > 10C 3210 (230,34) 3379 (190,33) 3372 (168,35) 3284 (192,34) 3483 (248,32)
PG High Low Rel. High Low Rel. High Low Rel. High Low Rel. High Low Rel.
Pavement Temperature, C 58.2 ‐11.7 59.5 ‐15.5 59.5 ‐13.1 58.8 ‐12.3 60.3 ‐11.2 50% Reliability PG 64‐16 (98,89) 64‐16 (98,54) 64‐16 (98,76) 64‐16 (98,83) 64‐16 (98,88) >50% Reliability PG 64‐22 (98,98) 64‐22 (98,91) 64‐22 (98,98) 64‐22 (98,98) 64‐22 (98,98) = 64‐28 (98,98)
Appendix F: Preliminary Pavement Recommendation Memo
Subject: Preliminary Pavement & Materials Recommendations (V1)
From: Marty Fey Pavement & Materials Engineer, CFLHD
Through: Mike Voth Pavement & Materials Team Lead, CFLHD
To: Thomas Sohn, Project Manager, CFLHD Darin Lockhart, Design Engineer, CFLHD
INTRODUCTION
This memorandum provides preliminary pavement and material recommendations for the 18 Road project located in Mesa County, north of Fruita, Colorado.
18 Road, runs from the Government Canal on the south end of the project to the BLM North Fruita Campground on the north. The project will include reconstruction of the roadway surface along with minor realignments and widening.
CFLHD standards and guidelines were used to complete the pavement and materials recommendations.
FIELD INVESTIGATION
On June 9th, 2020 CFLHD pavement & material engineer Marty Fey completed a field investigation which included boring and subgrade sampling. DA Smith Drilling was hired through the CFLHD BPA to assist with the field investigation. A CME 55 track-mounted drill rig with a 6” O.D. solid stem auger was used to complete the borings. Pavement boring were logged at 16 locations, subgrade samples were collected and tested in the laboratory. See the attached boring and testing logs for more detailed information.
Technical Memorandum
Date: March 19, 2021
The primary objectives of this field investigation were as follows:
Measure and record existing pavement and subgrade layer depths;
Gather subgrade soil samples for follow-up testing to determine engineering properties;
Evaluate and record pavement distress conditions;
Evaluate roadway and project area for constructability concerns.
The existing roadway was observed to consist of old, oxidized asphalt pavement with high severity fatigue cracking, large areas of pathing, chip seals, and poorly performing gravel surfaces extending throughout the length of the project. This roadway would be a good candidate for full depth reclamation. Additional roadbase will need to be added in areas where existing asphalt is thin or nonexistent.
The information gathered as described above was used to support pavement rehabilitation, structural design, and material recommendations.
Below are summary tables of data gathered and test results. For more complete and detailed results, see the attached logs and lab test reports.
Summary of Sampling & Test Results
Pavement Depth
Roadbase Depth
R‐value, subbase
R‐value, subgrade Comments
0 to 6.5 inches
0 to 6 inches
N/A 14 ‐ 48
Subgrade material consists primarily of Silty and Clayey Sands to Sandy Clays, A‐2‐4(0) and A‐4.
Resistivity values are moderate and indicate a lower risk of sulfate and chloride attack.
TRAFFIC:
Traffic counts were provided with the FLAP application and used to developed estimates for ESALs. The road is primarily used for recreational access with very little to no commercial use.
Truck counts were based on engineering judgement and are assumed to be very low. The counts appear generally consistent with other historical traffic data and they align with what was experienced during the field investigation. The following is a summary of traffic data as well as the estimated ESALs used for design:
2020 AADT = 259
2040 AADT = 385 (2% growth rate) 2020 % trucks = 7% Class 5 (trucks/RVs) Directional factor = 60% Design Lane ESAL’s = 50,000
DESIGN RECOMMENDATIONS
The pavement design, rehabilitation method, and other recommendations are included below.
In developing the pavement structural and rehabilitation recommendations the following criteria was used:
Design Criteria Initial Serviceability 4.2 Terminal Serviceability 2.0 Design Reliability Level 75% Overall Standard Deviation 0.49 Soil Resilient Modulus 5,000 psi Performance Period (3R) 20 years 20-year ESAL 50,000 Existing Borrow Material R-Value 20 Calculated Structural Number (SN) 2.21
The following is the recommended pavement structural section:
Pulverize and Overlay Layer Thickness
HACP 3 inches (two lifts) Full Depth Reclamation (FDR) or Aggregate Base Course 8 inches
SN = 2.28
Portions of the roadway with asphalt patches thicker than 6” were observed. The contractor should be made aware that the FDR depth of 6” is a minimum and that isolated areas of thicker pavement are present and will need to be addressed.
ADDITIONAL RECOMMENDATIONS:
The asphalt binder grade should be PG 64-22. This aligns with recommendations from LTPPBind.
Include a nominal amount of subexcavation (~100 cu yd) to be used at discretion of the
CO.
Recommend the following bid items.
Item Number Item Description Unit 20402-0000 Subexcavation CUYD 30202-2000 Roadway Aggregate, Method 2 TON 30401-5300 Full Depth Reclamation, Method 2, 6-inch SQYD
40101-0600 Asphalt Concrete Pavement, Gyratory Mix, ½” Nominal Max Size Aggregate,
0.3 to < 3 Million ESAL
TON
40105-3000 Antistrip Additive, Type 3 TON 40601-0000 Fog Seal TON 40605-0000 Blotter TON 41101-0000 Prime Coat TON 41105-0000 Blotter TON 41201-0000 Tack Coat TON
CONSTRUCTION CONSIDERATIONS & SPECIAL CONTRACT PROVISIONS
CFLHD standard SCR’s related to pavements & materials will be used.
Attachments:
Boring Logs & Charts Lab Test Reports LTPPBind Report Pavement Design
VI. PAVEMENT RECOMMENDATIONS & DISCUSSION
| 2024-06-13T14:18:39-0600 | |
| DARIN L LOCKHART |
| 2024-06-17T10:02:41-0600 | |
| MICHAEL D VOTH |