This document contains questions and answers related to a federal contract opportunity for the CO FLAP MES 18(1) 18 Road project. The project will reconstruct approximately six miles of 18 Road in Mesa County, Colorado, including roadway excavation, aggregate base, asphalt concrete pavement, concrete culverts, fencing, revegetation, pavement markings, and traffic control. The estimated cost range is between $10,000,000 and $20,000,000. The project is being procured through full and open competition by the Department of Transportation Federal Highway Administration. Key details include:
- Addendums were issued to update notes, quantities, and post length requirements
- No gates are being replaced as part of the project
- Brace and corner post quantities are not explicitly provided
- The contractor is responsible for obtaining the appropriate NPDES permit and water access
- The government will not provide a biological monitor for prairie dog and burrowing owl surveys
- Excess excavation must be disposed of offsite
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Tabulation.pdf | ||
| Bid Opening Summary.pdf | ||
| A003.pdf | ||
| A002.pdf | ||
| QnA 8.15.24.pdf | ||
| QnA 8.8.24.pdf | ||
| A001.pdf | ||
| QnA 8.1.24.pdf | ||
| CO FLAP MES 18(1) 18 Road Final Hydraulics Report with Addendum.pdf | ||
| Pavement Report CO FLAP MES 18(1) 18 Road 20240613.pdf | ||
| CO FLAP MES18(1) Plans Final - 06_20_2024.pdf | ||
| 6982AF24B000013.pdf | ||
| CO FLAP MES18(1) Cross Sections Final - 06_20_2024.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for CO FLAP MES 18(1) 18 Road
August 5, 2024
Questions Answers 1 After adding up all the fence they have I am coming up with
11,045' Almost twice as much as the bid quantity. Do we know why?
Addendum 001 updates notes and quantities to correct and clarify.
2 They want 76'' T-posts according to the detail. 72'' posts would give them 30'' in the ground. 2' in ground is the CDOT Standard.
Is 30'' adequate?
Addendum 001 updates to allow 72” post length with 30” embedment.
3 They show gates on the detail but I don't see gates on the plans or Bid Tab. Am I missing them?
No gates are being replaced as part of the project.
4 They don't have quantities for End and Corner Braces. This leaves a lot to interpretation as far as the overall price of the estimate.
Would they be willing to give a estimate on brace quantities?
Design and locations of brace and corner posts are not quantified or identified in the plans.
August 8, 2024
5 Can a rainfall erosivity waiver be utilized for a portion of this project?
The contractor is responsible for researching and obtaining the appropriate NDPES permit which will cover the activity outlined in the contract.
6 What is the anticipated start date for this project? Fall 2024. Reference special contract requirements and solicitation for calendar and seasonal restrictions.
7 Does the contractor need to provide a lab trailer for QA and a second one for QC?
Refer to Amendment A0001, and the Notice to Bidders, Pay Item 15401- 0000, Contractor testing on Page A-4 of the solicitation for more information on Contractor-furnished and Government-furnished field laboratories.
8 Will the contractor need to supply a separate field office for the
CO?
No
August 15, 2024
9 Do you know if we are able to pull water out of the Government
Highline Canal for this project?
Contractor is responsible for sourcing water for project. Contact responsible authorities for water access.
10 On the Grading Summary Sheet B4, Do the Prismoidal volumes include the new structural section? Meaning were the surfaces compared existing to subgrade or existing to finish.
Prismoidal volumes are calculated to the same standard that earthwork is measured in the FP-14, section 204.
August 19, 2024
Questions Answers 11 Do the upstream ends of the box culverts have concrete approach slabs?
See special 601-A Box Culvert Headwall and Wingwalls, for box culvert outlet headwall details. There are not approach slabs for the concrete box culverts.
12 Can Bids be sent via fed-ex or is it hand delivered only?
13 SCR 156.07 (o): Does this requirement pertain to maintenance of existing fencing or is the contractor expected to provide temporary fencing around the construction limits?
The requirement pertains to maintaining the existing fence.
14 Standard Spec Section 203: The roadway profile and provided cross sections would indicate that removal of the existing asphalt pavement section will be required. Please indicate how payment will be provided for removed pavement surfacing materials?
See FP-14 subsection 204.02.
15 SCR 107.10(e )(1): The presence of prairie dogs and burrowing owls has a significant impact on how the contractor could progress construction operations. The bidding documents do not disclose the locations or occurrence of sensitive wildlife. Without the government providing this information, can the contractors schedule under the assumption none are currently present, until determined at time of construction surveys? Will the government provide the necessary biological monitor as not pay item is provided?
The government performed a survey in fall of 2024 and no burrowing owls were found. Prairie dogs were encountered but will not require relocation.
Addendum 002 in section 107.10 provides additional clarification. The Government will not provide a biological monitor.
Either method is acceptable.
16 SCR 204.14: Please clearly indicate if the contractor would be allowed to dispose of excess excavation within the project limits or should the contractor assume offsite disposal. Because the tabulation on plan sheet number 84 classifies this material as waste the assumption is to export off the project limits?
Contractor to determine disposal location offsite.