Bid Tabulation.pdf
PDF 704 KB Posted
- Attached to
- CO FLAP MES 18(1) 18 Road Federal contract opportunity
- Solicitation number
- 6982AF24B000013
About this file
This document is a Bid Tabulation for a Federal contract opportunity. The project is to reconstruct approximately six miles of 18 Road in Mesa County, Colorado, including earthwork, drainage improvements, fencing, signage, and paving. The contract opportunity has a solicitation number of 6982AF24B000013, a project ID of CO FLAP MES18(1), and an estimated cost range between $10,000,000 and $20,000,000. The Federal Highway Administration is the agency overseeing the contract. The apparent low bidder after the HUBZone price preference is Mountain Valley Contracting, Inc. at $11,108,061.65. The solicitation was opened on 08/22/24 in Lakewood, Colorado. The bid tabulation provides detailed pricing line items for various construction activities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Opening Summary.pdf | ||
| QnA 8.19.24.pdf | ||
| A003.pdf | ||
| A002.pdf | ||
| QnA 8.15.24.pdf | ||
| QnA 8.8.24.pdf | ||
| A001.pdf | ||
| QnA 8.1.24.pdf | ||
| Pavement Report CO FLAP MES 18(1) 18 Road 20240613.pdf | ||
| CO FLAP MES18(1) Plans Final - 06_20_2024.pdf | ||
| 6982AF24B000013.pdf | ||
| CO FLAP MES18(1) Cross Sections Final - 06_20_2024.pdf | ||
| CO FLAP MES 18(1) 18 Road Final Hydraulics Report with Addendum.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HUBZone Price Evaluation
CO FLAP MES 18(1) 18 ROAD Schedule A Total Bid Amount 10% factor Adjusted Bid Amount
Contractor
*Mountain Valley Contracting Inc. (SBC, SDBC) $11,108,061.65 $11,108,061.65 $0.00 $11,108,061.65 SEMA Construction Inc. (LB) $13,095,991.00 $13,095,991.00 $1,309,599.10 $14,405,590.10 Siete, Inc. (SBC, SDBC) $12,822,963.00 $12,822,963.00 $1,282,296.30 $14,105,259.30 Central Southern Construction (SBC, SDBC, HUBZONE) $11,985,532.00 $11,985,532.00 $0.00 $11,985,532.00 Steve Manning Construction Inc. (SBC, SDBC, HUBZONE) $13,696,832.00 $13,696,832.00 $0.00 $13,696,832.00
*Apparent low bidder after HUBZone Price Preference
Tabulation of Bids Report Date: 09/03/24
1 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF24B000013
Division: Central Federal Lands
State: CO County: Mesa
Federal Land: North Fruita Desert Special Recreation Management Area Opened at: Lakewood, CO
Opened by: Ryan Phillips
Date: 08/22/24
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Mountain Valley Contracting, Inc. $11,108,061.65 2756 Winters Ave.
Grand Junction, CO 81501
Central Southern Construction Corp. $11,985,532.00 119 Sewald Street Jacksonville, FL 32204
Siete. Inc. $12,822,963.00
SEMA CONSTRUCTION, INC. $13,095,991.00
7353 S. EAGLE STREET
CENTENNIAL, CO 80112
Steve Manning Construction, Inc $13,696,832.00 5211 Churn Creek Road Redding, CA 96002
Engineer's Estimate $12,929,664.00
09/03/2021
Contract Specialist
2 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0010 15101-0000 MOBILIZATION
Mountain Valley Contracting, Inc. Lump Sum $365,245.19 Central Southern Construction Corp. Lump Sum $1,400,000.00 Siete. Inc. Lump Sum $1,250,000.00 SEMA CONSTRUCTION, INC. Lump Sum $1,180,000.00 Steve Manning Construction, Inc Lump Sum $1,300,000.00 Engineer's Estimate ALL LPSM Lump Sum $1,471,332.00
A0030 15215-1000 SURVEY AND STAKING, APPROACH ROAD
Mountain Valley Contracting, Inc. $780.66 $17,955.18 Central Southern Construction Corp. $2,500.00 $57,500.00 Siete. Inc. $2,000.00 $46,000.00
SEMA CONSTRUCTION, INC. $1,000.00 $23,000.00
Steve Manning Construction, Inc $1,200.00 $27,600.00 Engineer's Estimate 23 EACH $1,400.00 $32,200.00
A0050 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE
Mountain Valley Contracting, Inc. $557.61 $5,018.49 Central Southern Construction Corp. $2,000.00 $18,000.00 Siete. Inc. $5,000.00 $45,000.00
SEMA CONSTRUCTION, INC. $1,500.00 $13,500.00
Steve Manning Construction, Inc $1,300.00 $11,700.00 Engineer's Estimate 9 EACH $1,200.00 $10,800.00
A0070 15215-5000 SURVEY AND STAKING, BOX CULVERT
Mountain Valley Contracting, Inc. $3,234.16 $6,468.32 Central Southern Construction Corp. $7,500.00 $15,000.00 Siete. Inc. $5,000.00 $10,000.00
SEMA CONSTRUCTION, INC. $3,000.00 $6,000.00
Steve Manning Construction, Inc $4,000.00 $8,000.00 Engineer's Estimate 2 EACH $2,000.00 $4,000.00
A0090 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL
Mountain Valley Contracting, Inc. $2,457.56 $14,853.49 Central Southern Construction Corp. $12,000.00 $72,528.00 Siete. Inc. $3,500.00 $21,154.00
SEMA CONSTRUCTION, INC. $10,000.00 $60,440.00
Steve Manning Construction, Inc $3,000.00 $18,132.00 Engineer's Estimate 6.044 MILE $24,000.00 $145,056.00
3 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0110 15236-2000 SURVEY CONTROL, GRADE FINISHING
Mountain Valley Contracting, Inc. $3,125.22 $37,777.66 Central Southern Construction Corp. $5,500.00 $66,484.00 Siete. Inc. $3,000.00 $36,264.00
SEMA CONSTRUCTION, INC. $6,000.00 $72,528.00
Steve Manning Construction, Inc $5,000.00 $60,440.00 Engineer's Estimate 12.088 MILE $9,500.00 $114,836.00
A0130 15301-0000 CONTRACTOR QUALITY CONTROL
Mountain Valley Contracting, Inc. Lump Sum $342,598.17 Central Southern Construction Corp. Lump Sum $950,000.00 Siete. Inc. Lump Sum $550,000.00 SEMA CONSTRUCTION, INC. Lump Sum $800,000.00 Steve Manning Construction, Inc Lump Sum $295,000.00 Engineer's Estimate ALL LPSM Lump Sum $320,000.00
A0150 15401-0000 CONTRACTOR TESTING
Mountain Valley Contracting, Inc. Lump Sum $171,944.28 Central Southern Construction Corp. Lump Sum $125,000.00 Siete. Inc. Lump Sum $550,000.00 SEMA CONSTRUCTION, INC. Lump Sum $65,000.00 Steve Manning Construction, Inc Lump Sum $300,000.00 Engineer's Estimate ALL LPSM Lump Sum $320,000.00
A0170 15501-0000 CONSTRUCTION SCHEDULE
Mountain Valley Contracting, Inc. Lump Sum $14,955.19 Central Southern Construction Corp. Lump Sum $75,000.00 Siete. Inc. Lump Sum $25,000.00 SEMA CONSTRUCTION, INC. Lump Sum $100,000.00 Steve Manning Construction, Inc Lump Sum $30,000.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00
A0190 15701-0000 SOIL EROSION CONTROL
Mountain Valley Contracting, Inc. Lump Sum $287,842.19 Central Southern Construction Corp. Lump Sum $375,000.00 Siete. Inc. Lump Sum $150,000.00 SEMA CONSTRUCTION, INC. Lump Sum $500,000.00 Steve Manning Construction, Inc Lump Sum $120,000.00 Engineer's Estimate ALL LPSM Lump Sum $200,000.00
4 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0210 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Mountain Valley Contracting, Inc. Lump Sum $8,895.04 Central Southern Construction Corp. Lump Sum $50,000.00 Siete. Inc. Lump Sum $10,000.00 SEMA CONSTRUCTION, INC. Lump Sum $50,000.00 Steve Manning Construction, Inc Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $60,000.00
A0230 15802-0000 WATERING FOR DUST CONTROL
Mountain Valley Contracting, Inc. Lump Sum $138,792.70 Central Southern Construction Corp. Lump Sum $325,000.00 Siete. Inc. Lump Sum $50,000.00 SEMA CONSTRUCTION, INC. Lump Sum $500,000.00 Steve Manning Construction, Inc Lump Sum $182,000.00 Engineer's Estimate ALL LPSM Lump Sum $45,000.00
A0250 20101-0000 CLEARING AND GRUBBING
Mountain Valley Contracting, Inc. $2,101.99 $46,243.78 Central Southern Construction Corp. $2,000.00 $44,000.00 Siete. Inc. $15,000.00 $330,000.00
SEMA CONSTRUCTION, INC. $5,000.00 $110,000.00
Steve Manning Construction, Inc $9,800.00 $215,600.00 Engineer's Estimate 22.0 ACRE $5,500.00 $121,000.00
A0270 20301-1900 REMOVAL OF PIPE CULVERT
Mountain Valley Contracting, Inc. $2,231.07 $26,772.84 Central Southern Construction Corp. $4,000.00 $48,000.00 Siete. Inc. $12,500.00 $150,000.00
SEMA CONSTRUCTION, INC. $7,500.00 $90,000.00
Steve Manning Construction, Inc $4,000.00 $48,000.00 Engineer's Estimate 12 EACH $1,000.00 $12,000.00
A0290 20301-2400 REMOVAL OF SIGN
Mountain Valley Contracting, Inc. $111.52 $557.60 Central Southern Construction Corp. $400.00 $2,000.00 Siete. Inc. $500.00 $2,500.00
SEMA CONSTRUCTION, INC. $110.00 $550.00
Steve Manning Construction, Inc $400.00 $2,000.00 Engineer's Estimate 5 EACH $175.00 $875.00
5 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0310 20302-0700 REMOVAL OF FENCE
Mountain Valley Contracting, Inc. $0.67 $4,482.30 Central Southern Construction Corp. $3.00 $20,070.00 Siete. Inc. $4.00 $26,760.00
SEMA CONSTRUCTION, INC. $2.20 $14,718.00
Steve Manning Construction, Inc $3.00 $20,070.00 Engineer's Estimate 6,690 LNFT $3.00 $20,070.00
A0330 20401-0000 ROADWAY EXCAVATION (CHANNEL GRADING)
Mountain Valley Contracting, Inc. $32.53 $26,024.00 Central Southern Construction Corp. $50.00 $40,000.00 Siete. Inc. $50.00 $40,000.00
SEMA CONSTRUCTION, INC. $32.00 $25,600.00
Steve Manning Construction, Inc $87.00 $69,600.00 Engineer's Estimate 800 CUYD $35.00 $28,000.00
A0350 20401-0000 ROADWAY EXCAVATION
Mountain Valley Contracting, Inc. $48.70 $1,972,350.00 Central Southern Construction Corp. $30.00 $1,215,000.00 Siete. Inc. $45.00 $1,822,500.00
SEMA CONSTRUCTION, INC. $20.00 $810,000.00
Steve Manning Construction, Inc $48.00 $1,944,000.00 Engineer's Estimate 40,500 CUYD $35.00 $1,417,500.00
A0370 20402-0000 SUBEXCAVATION
Mountain Valley Contracting, Inc. $71.41 $35,705.00 Central Southern Construction Corp. $50.00 $25,000.00 Siete. Inc. $450.00 $225,000.00
SEMA CONSTRUCTION, INC. $120.00 $60,000.00
Steve Manning Construction, Inc $450.00 $225,000.00 Engineer's Estimate 500 CUYD $240.00 $120,000.00
A0390 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2
Mountain Valley Contracting, Inc. $343.01 $89,182.60 Central Southern Construction Corp. $275.00 $71,500.00 Siete. Inc. $300.00 $78,000.00
SEMA CONSTRUCTION, INC. $300.00 $78,000.00
Steve Manning Construction, Inc $300.00 $78,000.00 Engineer's Estimate 260 CUYD $250.00 $65,000.00
6 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0410 25101-0400 PLACED RIPRAP, METHOD A, CLASS 4
Mountain Valley Contracting, Inc. $341.27 $27,301.60 Central Southern Construction Corp. $300.00 $24,000.00 Siete. Inc. $350.00 $28,000.00
SEMA CONSTRUCTION, INC. $300.00 $24,000.00
Steve Manning Construction, Inc $300.00 $24,000.00 Engineer's Estimate 80 CUYD $250.00 $20,000.00
A0430 25101-0600 PLACED RIPRAP, METHOD A, CLASS 6
Mountain Valley Contracting, Inc. $341.84 $58,112.80 Central Southern Construction Corp. $350.00 $59,500.00 Siete. Inc. $400.00 $68,000.00
SEMA CONSTRUCTION, INC. $300.00 $51,000.00
Steve Manning Construction, Inc $300.00 $51,000.00 Engineer's Estimate 170 CUYD $305.00 $51,850.00
A0470 30101-0000 AGGREGATE BASE
Mountain Valley Contracting, Inc. $36.95 $2,032,250.00 Central Southern Construction Corp. $32.00 $1,760,000.00 Siete. Inc. $35.00 $1,925,000.00
SEMA CONSTRUCTION, INC. $45.00 $2,475,000.00
Steve Manning Construction, Inc $39.00 $2,145,000.00 Engineer's Estimate 55,000 TON $54.00 $2,970,000.00
A0510 40101-0600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3
MILLION ESAL
Mountain Valley Contracting, Inc. $147.21 $2,738,106.00 Central Southern Construction Corp. $132.00 $2,455,200.00 Siete. Inc. $132.00 $2,455,200.00
SEMA CONSTRUCTION, INC. $175.00 $3,255,000.00
Steve Manning Construction, Inc $157.00 $2,920,200.00 Engineer's Estimate 18,600 TON $151.00 $2,808,600.00
A0530 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
Mountain Valley Contracting, Inc. $508.54 $96,622.60 Central Southern Construction Corp. $456.00 $86,640.00 Siete. Inc. $463.00 $87,970.00
SEMA CONSTRUCTION, INC. $500.00 $95,000.00
Steve Manning Construction, Inc $595.00 $113,050.00 Engineer's Estimate 190 TON $360.00 $68,400.00
7 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0570 40601-0000 FOG SEAL
Mountain Valley Contracting, Inc. $624.53 $31,226.50 Central Southern Construction Corp. $560.00 $28,000.00 Siete. Inc. $570.00 $28,500.00
SEMA CONSTRUCTION, INC. $1,000.00 $50,000.00
Steve Manning Construction, Inc $728.00 $36,400.00 Engineer's Estimate 50 TON $950.00 $47,500.00
A0590 40605-0000 BLOTTER
Mountain Valley Contracting, Inc. $162.82 $27,679.40 Central Southern Construction Corp. $170.00 $28,900.00 Siete. Inc. $150.00 $25,500.00
SEMA CONSTRUCTION, INC. $75.00 $12,750.00
Steve Manning Construction, Inc $150.00 $25,500.00 Engineer's Estimate 170 TON $33.00 $5,610.00
A0610 41102-1000 PRIME COAT, METHOD 1
Mountain Valley Contracting, Inc. $1.52 $170,240.00 Central Southern Construction Corp. $1.40 $156,800.00 Siete. Inc. $0.60 $67,200.00
SEMA CONSTRUCTION, INC. $2.25 $252,000.00
Steve Manning Construction, Inc $1.70 $190,400.00 Engineer's Estimate 112,000 SQYD $1.50 $168,000.00
A0630 41201-0000 TACK COAT
Mountain Valley Contracting, Inc. $1,287.93 $64,396.50 Central Southern Construction Corp. $1,155.00 $57,750.00 Siete. Inc. $2,000.00 $100,000.00
SEMA CONSTRUCTION, INC. $1,000.00 $50,000.00
Steve Manning Construction, Inc $1,500.00 $75,000.00 Engineer's Estimate 50 TON $1,000.00 $50,000.00
A0650 60103-0000 CONCRETE, HEADWALL (HEADWALL AND WINGWALLS FOR 12 FEET SPAN X 10 FEET RISE BOX CULVERT)
Mountain Valley Contracting, Inc. $46,274.51 $92,549.02 Central Southern Construction Corp. $50,000.00 $100,000.00 Siete. Inc. $85,000.00 $170,000.00
SEMA CONSTRUCTION, INC. $100,000.00 $200,000.00
Steve Manning Construction, Inc $110,000.00 $220,000.00 Engineer's Estimate 2 EACH $45,000.00 $90,000.00
8 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0670 60103-0000 CONCRETE, HEADWALL (HEADWALL AND WINGWALLS FOR 9 FEET SPAN X 6 FEET RISE BOX CULVERT)
Mountain Valley Contracting, Inc. $29,302.10 $58,604.20 Central Southern Construction Corp. $15,000.00 $30,000.00 Siete. Inc. $75,000.00 $150,000.00
SEMA CONSTRUCTION, INC. $75,000.00 $150,000.00
Steve Manning Construction, Inc $90,000.00 $180,000.00 Engineer's Estimate 2 EACH $25,000.00 $50,000.00
A0690 60103-0260 CONCRETE, HEADWALL FOR 60-INCH PIPE CULVERT
Mountain Valley Contracting, Inc. $9,973.49 $19,946.98 Central Southern Construction Corp. $15,000.00 $30,000.00 Siete. Inc. $65,000.00 $130,000.00
SEMA CONSTRUCTION, INC. $35,000.00 $70,000.00
Steve Manning Construction, Inc $80,000.00 $160,000.00 Engineer's Estimate 2 EACH $18,000.00 $36,000.00
A0710 60201-0600 18-INCH PIPE CULVERT (CONCRETE PIPE)
Mountain Valley Contracting, Inc. $134.09 $9,386.30 Central Southern Construction Corp. $225.00 $15,750.00 Siete. Inc. $300.00 $21,000.00
SEMA CONSTRUCTION, INC. $200.00 $14,000.00
Steve Manning Construction, Inc $380.00 $26,600.00 Engineer's Estimate 70 LNFT $175.00 $12,250.00
A0730 60201-0800 24-INCH PIPE CULVERT (CONCRETE PIPE)
Mountain Valley Contracting, Inc. $175.92 $11,434.80 Central Southern Construction Corp. $260.00 $16,900.00 Siete. Inc. $400.00 $26,000.00
SEMA CONSTRUCTION, INC. $250.00 $16,250.00
Steve Manning Construction, Inc $400.00 $26,000.00 Engineer's Estimate 65 LNFT $240.00 $15,600.00
A0750 60201-1100 42-INCH PIPE CULVERT (CONCRETE PIPE)
Mountain Valley Contracting, Inc. $398.81 $27,916.70 Central Southern Construction Corp. $400.00 $28,000.00 Siete. Inc. $500.00 $35,000.00
SEMA CONSTRUCTION, INC. $400.00 $28,000.00
Steve Manning Construction, Inc $620.00 $43,400.00 Engineer's Estimate 70 LNFT $460.00 $32,200.00
9 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0770 60201-1400 60-INCH PIPE CULVERT (CONCRETE PIPE)
Mountain Valley Contracting, Inc. $647.71 $48,578.25 Central Southern Construction Corp. $550.00 $41,250.00 Siete. Inc. $700.00 $52,500.00
SEMA CONSTRUCTION, INC. $500.00 $37,500.00
Steve Manning Construction, Inc $820.00 $61,500.00 Engineer's Estimate 75 LNFT $600.00 $45,000.00
A0790 60202-0200 18-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT (ELLIPTICAL CONCRETE)
Mountain Valley Contracting, Inc. $288.23 $43,234.50 Central Southern Construction Corp. $350.00 $52,500.00 Siete. Inc. $400.00 $60,000.00
SEMA CONSTRUCTION, INC. $300.00 $45,000.00
Steve Manning Construction, Inc $410.00 $61,500.00 Engineer's Estimate 150 LNFT $250.00 $37,500.00
A0810 60202-0400 24-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT (ELLIPTICAL CONCRETE)
Mountain Valley Contracting, Inc. $332.85 $69,898.50 Central Southern Construction Corp. $395.00 $82,950.00 Siete. Inc. $500.00 $105,000.00
SEMA CONSTRUCTION, INC. $350.00 $73,500.00
Steve Manning Construction, Inc $430.00 $90,300.00 Engineer's Estimate 210 LNFT $260.00 $54,600.00
A0830 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT (CONCRETE)
Mountain Valley Contracting, Inc. $1,516.23 $3,032.46 Central Southern Construction Corp. $3,000.00 $6,000.00 Siete. Inc. $5,000.00 $10,000.00
SEMA CONSTRUCTION, INC. $2,500.00 $5,000.00
Steve Manning Construction, Inc $1,800.00 $3,600.00 Engineer's Estimate 2 EACH $675.00 $1,350.00
A0850 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT (CONCRETE)
Mountain Valley Contracting, Inc. $1,875.45 $3,750.90 Central Southern Construction Corp. $3,500.00 $7,000.00 Siete. Inc. $6,000.00 $12,000.00
SEMA CONSTRUCTION, INC. $3,000.00 $6,000.00
Steve Manning Construction, Inc $2,200.00 $4,400.00 Engineer's Estimate 2 EACH $1,050.00 $2,100.00
10 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0870 60210-1100 END SECTION FOR 42-INCH PIPE CULVERT (CONCRETE)
Mountain Valley Contracting, Inc. $4,099.05 $8,198.10 Central Southern Construction Corp. $7,500.00 $15,000.00 Siete. Inc. $7,000.00 $14,000.00
SEMA CONSTRUCTION, INC. $5,000.00 $10,000.00
Steve Manning Construction, Inc $3,900.00 $7,800.00 Engineer's Estimate 2 EACH $2,000.00 $4,000.00
A0890 60211-0600 END SECTION FOR 18-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT (ELLIPTICAL
CONCRETE)
Mountain Valley Contracting, Inc. $1,681.10 $6,724.40 Central Southern Construction Corp. $4,000.00 $16,000.00 Siete. Inc. $5,000.00 $20,000.00
SEMA CONSTRUCTION, INC. $3,500.00 $14,000.00
Steve Manning Construction, Inc $2,300.00 $9,200.00 Engineer's Estimate 4 EACH $2,500.00 $10,000.00
A0910 60211-0800 END SECTION FOR 24-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT (ELLIPTICAL
CONCRETE)
Mountain Valley Contracting, Inc. $1,825.34 $10,952.04 Central Southern Construction Corp. $4,500.00 $27,000.00 Siete. Inc. $6,000.00 $36,000.00
SEMA CONSTRUCTION, INC. $4,000.00 $24,000.00
Steve Manning Construction, Inc $2,800.00 $16,800.00 Engineer's Estimate 6 EACH $2,000.00 $12,000.00
A0930 60220-2450 9 FEET SPAN, 6 FEET RISE PRECAST REINFORCED CONCRETE BOX CULVERT
Mountain Valley Contracting, Inc. $3,150.98 $239,474.48 Central Southern Construction Corp. $4,000.00 $304,000.00 Siete. Inc. $5,500.00 $418,000.00
SEMA CONSTRUCTION, INC. $3,000.00 $228,000.00
Steve Manning Construction, Inc $2,780.00 $211,280.00 Engineer's Estimate 76 LNFT $3,400.00 $258,400.00
A0950 60220-4150 12 FEET SPAN, 10 FEET RISE PRECAST REINFORCED CONCRETE BOX CULVERT
Mountain Valley Contracting, Inc. $5,018.02 $306,099.22 Central Southern Construction Corp. $6,500.00 $396,500.00 Siete. Inc. $6,500.00 $396,500.00
SEMA CONSTRUCTION, INC. $4,500.00 $274,500.00
Steve Manning Construction, Inc $5,230.00 $319,030.00 Engineer's Estimate 61 LNFT $4,400.00 $268,400.00
11 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0970 61901-0900 FENCE, BARBED WIRE, 4 STRAND
Mountain Valley Contracting, Inc. $5.58 $37,330.20 Central Southern Construction Corp. $10.00 $66,900.00 Siete. Inc. $8.00 $53,520.00
SEMA CONSTRUCTION, INC. $5.50 $36,795.00
Steve Manning Construction, Inc $26.00 $173,940.00 Engineer's Estimate 6,690 LNFT $15.00 $100,350.00
A0990 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
Mountain Valley Contracting, Inc. $162.06 $12,964.80 Central Southern Construction Corp. $200.00 $16,000.00 Siete. Inc. $135.00 $10,800.00
SEMA CONSTRUCTION, INC. $150.00 $12,000.00
Steve Manning Construction, Inc $200.00 $16,000.00 Engineer's Estimate 80 HOUR $130.00 $10,400.00
A1010 62201-0350 BACKHOE
Mountain Valley Contracting, Inc. $135.16 $10,812.80 Central Southern Construction Corp. $200.00 $16,000.00 Siete. Inc. $130.00 $10,400.00
SEMA CONSTRUCTION, INC. $250.00 $20,000.00
Steve Manning Construction, Inc $220.00 $17,600.00 Engineer's Estimate 80 HOUR $160.00 $12,800.00
A1030 62201-0850 WHEEL LOADER, 1 CUBIC YARD MINIMUM RATED CAPACITY
Mountain Valley Contracting, Inc. $176.90 $7,076.00 Central Southern Construction Corp. $200.00 $8,000.00 Siete. Inc. $180.00 $7,200.00
SEMA CONSTRUCTION, INC. $250.00 $10,000.00
Steve Manning Construction, Inc $220.00 $8,800.00 Engineer's Estimate 40 HOUR $270.00 $10,800.00
A1050 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
Mountain Valley Contracting, Inc. $294.33 $23,546.40 Central Southern Construction Corp. $250.00 $20,000.00 Siete. Inc. $196.00 $15,680.00
SEMA CONSTRUCTION, INC. $250.00 $20,000.00
Steve Manning Construction, Inc $280.00 $22,400.00 Engineer's Estimate 80 HOUR $205.00 $16,400.00
12 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1070 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
Mountain Valley Contracting, Inc. $206.41 $8,256.40 Central Southern Construction Corp. $250.00 $10,000.00 Siete. Inc. $228.00 $9,120.00
SEMA CONSTRUCTION, INC. $400.00 $16,000.00
Steve Manning Construction, Inc $250.00 $10,000.00 Engineer's Estimate 40 HOUR $240.00 $9,600.00
A1090 62301-0000 GENERAL LABOR
Mountain Valley Contracting, Inc. $51.70 $4,136.00 Central Southern Construction Corp. $50.00 $4,000.00 Siete. Inc. $60.00 $4,800.00
SEMA CONSTRUCTION, INC. $60.00 $4,800.00
Steve Manning Construction, Inc $110.00 $8,800.00 Engineer's Estimate 80 HOUR $80.00 $6,400.00
A1110 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Mountain Valley Contracting, Inc. $178.44 $7,137.60 Central Southern Construction Corp. $250.00 $10,000.00 Siete. Inc. $165.00 $6,600.00
SEMA CONSTRUCTION, INC. $160.00 $6,400.00
Steve Manning Construction, Inc $300.00 $12,000.00 Engineer's Estimate 40 HOUR $210.00 $8,400.00
A1130 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
Mountain Valley Contracting, Inc. $178.44 $7,137.60 Central Southern Construction Corp. $350.00 $14,000.00 Siete. Inc. $165.00 $6,600.00
SEMA CONSTRUCTION, INC. $250.00 $10,000.00
Steve Manning Construction, Inc $410.00 $16,400.00 Engineer's Estimate 40 HOUR $190.00 $7,600.00
A1150 62406-0200 PLACING CONSERVED TOPSOIL, 3-INCH DEPTH
Mountain Valley Contracting, Inc. $2,359.27 $49,544.67 Central Southern Construction Corp. $10,000.00 $210,000.00 Siete. Inc. $1,000.00 $21,000.00
SEMA CONSTRUCTION, INC. $3,500.00 $73,500.00
Steve Manning Construction, Inc $16,110.00 $338,310.00 Engineer's Estimate 21.0 ACRE $6,300.00 $132,300.00
13 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1170 62510-2000 SEEDING, HYDRAULIC METHOD
Mountain Valley Contracting, Inc. $2,043.64 $42,916.44 Central Southern Construction Corp. $4,000.00 $84,000.00 Siete. Inc. $1,500.00 $31,500.00
SEMA CONSTRUCTION, INC. $2,000.00 $42,000.00
Steve Manning Construction, Inc $1,380.00 $28,980.00 Engineer's Estimate 21.0 ACRE $1,500.00 $31,500.00
A1190 62515-2000 MULCHING, HYDRAULIC METHOD
Mountain Valley Contracting, Inc. $2,582.26 $54,227.46 Central Southern Construction Corp. $2,500.00 $52,500.00 Siete. Inc. $2,000.00 $42,000.00
SEMA CONSTRUCTION, INC. $2,500.00 $52,500.00
Steve Manning Construction, Inc $2,780.00 $58,380.00 Engineer's Estimate 21.0 ACRE $2,200.00 $46,200.00
A1210 63301-0000 SIGN SYSTEM
Mountain Valley Contracting, Inc. $585.49 $29,274.50 Central Southern Construction Corp. $600.00 $30,000.00 Siete. Inc. $525.00 $26,250.00
SEMA CONSTRUCTION, INC. $600.00 $30,000.00
Steve Manning Construction, Inc $1,750.00 $87,500.00 Engineer's Estimate 50 EACH $1,000.00 $50,000.00
A1230 63308-2000 OBJECT MARKER, TYPE 2
Mountain Valley Contracting, Inc. $273.23 $6,830.75 Central Southern Construction Corp. $300.00 $7,500.00 Siete. Inc. $245.00 $6,125.00
SEMA CONSTRUCTION, INC. $300.00 $7,500.00
Steve Manning Construction, Inc $150.00 $3,750.00 Engineer's Estimate 25 EACH $65.00 $1,625.00
A1250 63309-0000 DELINEATOR
Mountain Valley Contracting, Inc. $46.84 $27,167.20 Central Southern Construction Corp. $60.00 $34,800.00 Siete. Inc. $42.00 $24,360.00
SEMA CONSTRUCTION, INC. $45.00 $26,100.00
Steve Manning Construction, Inc $120.00 $69,600.00 Engineer's Estimate 580 EACH $60.00 $34,800.00
14 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1270 63316-1000 REMOVE AND RESET SIGN
Mountain Valley Contracting, Inc. $446.09 $2,230.45 Central Southern Construction Corp. $500.00 $2,500.00 Siete. Inc. $400.00 $2,000.00
SEMA CONSTRUCTION, INC. $500.00 $2,500.00
Steve Manning Construction, Inc $900.00 $4,500.00 Engineer's Estimate 5 EACH $1,000.00 $5,000.00
A1290 63402-0300 PAVEMENT MARKINGS, TYPE B, SOLID
Mountain Valley Contracting, Inc. $3,238.62 $208,890.99 Central Southern Construction Corp. $1,300.00 $83,850.00 Siete. Inc. $3,500.00 $225,750.00
SEMA CONSTRUCTION, INC. $3,200.00 $206,400.00
Steve Manning Construction, Inc $1,900.00 $122,550.00 Engineer's Estimate 64.5 MILE $3,000.00 $193,500.00
A1310 63402-0400 PAVEMENT MARKINGS, TYPE B, BROKEN
Mountain Valley Contracting, Inc. $1,889.20 $9,446.00 Central Southern Construction Corp. $500.00 $2,500.00 Siete. Inc. $3,600.00 $18,000.00
SEMA CONSTRUCTION, INC. $2,000.00 $10,000.00
Steve Manning Construction, Inc $1,900.00 $9,500.00 Engineer's Estimate 5.0 MILE $1,000.00 $5,000.00
A1330 63501-2000 TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM
Mountain Valley Contracting, Inc. Lump Sum $50,185.28 Central Southern Construction Corp. Lump Sum $50,000.00 Siete. Inc. Lump Sum $50,000.00 SEMA CONSTRUCTION, INC. Lump Sum $50,000.00 Steve Manning Construction, Inc Lump Sum $40,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00
A1350 63501-3500 TEMPORARY TRAFFIC CONTROL, PUBLIC INFORMATION PROGRAM
Mountain Valley Contracting, Inc. Lump Sum $355,445.60 Central Southern Construction Corp. Lump Sum $50,000.00 Siete. Inc. Lump Sum $10,000.00 SEMA CONSTRUCTION, INC. Lump Sum $10,000.00 Steve Manning Construction, Inc Lump Sum $12,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00
15 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1370 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
Mountain Valley Contracting, Inc. $557.61 $2,230.44 Central Southern Construction Corp. $1,000.00 $4,000.00 Siete. Inc. $550.00 $2,200.00
SEMA CONSTRUCTION, INC. $600.00 $2,400.00
Steve Manning Construction, Inc $200.00 $800.00 Engineer's Estimate 4 EACH $340.00 $1,360.00
A1390 63502-1050 TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER
Mountain Valley Contracting, Inc. $55.76 $11,152.00 Central Southern Construction Corp. $60.00 $12,000.00 Siete. Inc. $10.00 $2,000.00
SEMA CONSTRUCTION, INC. $45.00 $9,000.00
Steve Manning Construction, Inc $60.00 $12,000.00 Engineer's Estimate 200 EACH $35.00 $7,000.00
A1410 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
Mountain Valley Contracting, Inc. $55.76 $5,910.56 Central Southern Construction Corp. $60.00 $6,360.00 Siete. Inc. $45.00 $4,770.00
SEMA CONSTRUCTION, INC. $50.00 $5,300.00
Steve Manning Construction, Inc $120.00 $12,720.00 Engineer's Estimate 106 EACH $100.00 $10,600.00
A1430 63502-1500 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE A
Mountain Valley Contracting, Inc. $55.76 $223.04 Central Southern Construction Corp. $100.00 $400.00 Siete. Inc. $60.00 $240.00
SEMA CONSTRUCTION, INC. $65.00 $260.00
Steve Manning Construction, Inc $800.00 $3,200.00 Engineer's Estimate 4 EACH $250.00 $1,000.00
A1450 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
Mountain Valley Contracting, Inc. $223.05 $446.10 Central Southern Construction Corp. $1,000.00 $2,000.00 Siete. Inc. $800.00 $1,600.00
SEMA CONSTRUCTION, INC. $850.00 $1,700.00
Steve Manning Construction, Inc $100.00 $200.00 Engineer's Estimate 2 EACH $250.00 $500.00
16 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1470 63502-1700 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C
Mountain Valley Contracting, Inc. $55.76 $5,576.00 Central Southern Construction Corp. $100.00 $10,000.00 Siete. Inc. $60.00 $6,000.00
SEMA CONSTRUCTION, INC. $65.00 $6,500.00
Steve Manning Construction, Inc $100.00 $10,000.00 Engineer's Estimate 100 EACH $50.00 $5,000.00
A1490 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
Mountain Valley Contracting, Inc. $16,728.43 $33,456.86 Central Southern Construction Corp. $20,000.00 $40,000.00 Siete. Inc. $20,000.00 $40,000.00
SEMA CONSTRUCTION, INC. $20,000.00 $40,000.00
Steve Manning Construction, Inc $8,200.00 $16,400.00 Engineer's Estimate 2 EACH $24,000.00 $48,000.00
A1510 63502-3900 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN (Bipartisan Infrastructure Law Sign)
Mountain Valley Contracting, Inc. $1,672.84 $1,672.84 Central Southern Construction Corp. $2,000.00 $2,000.00 Siete. Inc. $10,000.00 $10,000.00
SEMA CONSTRUCTION, INC. $2,000.00 $2,000.00
Steve Manning Construction, Inc $2,200.00 $2,200.00 Engineer's Estimate 1 EACH $1,000.00 $1,000.00
A1530 63502-3900 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Mountain Valley Contracting, Inc. $178.44 $10,706.40 Central Southern Construction Corp. $100.00 $6,000.00 Siete. Inc. $90.00 $5,400.00
SEMA CONSTRUCTION, INC. $100.00 $6,000.00
Steve Manning Construction, Inc $420.00 $25,200.00 Engineer's Estimate 60 EACH $75.00 $4,500.00
A1550 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
Mountain Valley Contracting, Inc. $42.38 $156,806.00 Central Southern Construction Corp. $40.00 $148,000.00 Siete. Inc. $40.00 $148,000.00
SEMA CONSTRUCTION, INC. $45.00 $166,500.00
Steve Manning Construction, Inc $90.00 $333,000.00 Engineer's Estimate 3,700 HOUR $65.00 $240,500.00
17 out of 17
Project No: CO FLAP MES18(1)
Project Name: 18 Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1570 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
Mountain Valley Contracting, Inc. $55.76 $105,944.00 Central Southern Construction Corp. $85.00 $161,500.00 Siete. Inc. $85.00 $161,500.00
SEMA CONSTRUCTION, INC. $100.00 $190,000.00
Steve Manning Construction, Inc $120.00 $228,000.00 Engineer's Estimate 1,900 HOUR $95.00 $180,500.00
Total Schedule - All Items
Mountain Valley Contracting, Inc. $11,108,061.65 Central Southern Construction Corp. $11,985,532.00 Siete. Inc. $12,822,963.00
SEMA CONSTRUCTION, INC. $13,095,991.00
Steve Manning Construction, Inc $13,696,832.00 Engineer's Estimate $12,929,664.00