This document is a set of Questions and Answers regarding a federal contract opportunity for the CO FLAP MES 18(1) 18 Road project. The key details are:

The project will reconstruct approximately 6 miles of 18 Road in Mesa County, Colorado, including roadway excavation, aggregate base and asphalt concrete pavement, drainage improvements, fence replacement, signing, striping, and revegetation. The estimated cost range is between $10-20 million. The contractor is responsible for obtaining the appropriate NPDES permit and sourcing water for the project. Contractor-furnished and government-furnished field laboratories are required. The anticipated start date is Fall 2024, and the contractor must maintain vehicular, cyclist, and pedestrian access during construction. The questions address various technical aspects of the project, such as fence quantities, post lengths, and earthwork calculations.

View the file

Other files for this federal contract opportunity

Other files attached to CO FLAP MES 18(1) 18 Road, newest first.
File Type Posted
Bid Tabulation.pdf PDF
Bid Opening Summary.pdf PDF
QnA 8.19.24.pdf PDF
A003.pdf PDF
A002.pdf PDF
QnA 8.8.24.pdf PDF
A001.pdf PDF
QnA 8.1.24.pdf PDF
CO FLAP MES 18(1) 18 Road Final Hydraulics Report with Addendum.pdf PDF
Pavement Report CO FLAP MES 18(1) 18 Road 20240613.pdf PDF
CO FLAP MES18(1) Plans Final - 06_20_2024.pdf PDF
6982AF24B000013.pdf PDF
CO FLAP MES18(1) Cross Sections Final - 06_20_2024.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

CO FLAP MES 18(1) 18 Road

August 5, 2024

Questions Answers

1 After adding up all the fence they have I am coming up with

11,045' Almost twice as much as the bid quantity. Do we know why?

Addendum 001 updates notes and quantities to correct and clarify.

2 They want 76'' T-posts according to the detail. 72'' posts would give them 30'' in the ground. 2' in ground is the CDOT Standard.

Is 30'' adequate?

Addendum 001 updates to allow 72” post length with 30” embedment.

3 They show gates on the detail but I don't see gates on the plans or

Bid Tab. Am I missing them?

No gates are being replaced as part of the project.

4 They don't have quantities for End and Corner Braces. This leaves a lot to interpretation as far as the overall price of the estimate.

Would they be willing to give a estimate on brace quantities?

Design and locations of brace and corner posts are not quantified or identified in the plans.

August 8, 2024

5 Can a rainfall erosivity waiver be utilized for a portion of this project?

The contractor is responsible for researching and obtaining the appropriate

NDPES permit which will cover the activity outlined in the contract.

6 What is the anticipated start date for this project? Fall 2024. Reference special contract requirements and solicitation for calendar and seasonal restrictions.

7 Does the contractor need to provide a lab trailer for QA and a second one for QC?

Refer to Amendment A0001, and the Notice to Bidders, Pay Item 15401-

0000, Contractor testing on Page A-4 of the solicitation for more information on Contractor-furnished and Government-furnished field laboratories.

8 Will the contractor need to supply a separate field office for the

CO?

No

August 15, 2024

9 Do you know if we are able to pull water out of the Government

Highline Canal for this project?

Contractor is responsible for sourcing water for project. Contact responsible authorities for water access.

10 On the Grading Summary Sheet B4, Do the Prismoidal volumes include the new structural section? Meaning were the surfaces compared existing to subgrade or existing to finish.

Prismoidal volumes are calculated to the same standard that earthwork is measured in the FP-14, section 204.