QnA 8.8.24.pdf
PDF 137 KB Posted
- Attached to
- CO FLAP MES 18(1) 18 Road Federal contract opportunity
- Solicitation number
- 6982AF24B000013
About this file
This document contains Questions and Answers (Q&A) related to a federal contract opportunity for the CO FLAP MES 18(1) 18 Road project.
The key details are:
- The project involves reconstructing approximately 6 miles of 18 Road in Mesa County, Colorado, including earthwork, grading, aggregate base, asphalt paving, drainage improvements, fencing, signing, striping, and revegetation.
- The anticipated start date for the project is Fall 2024.
- The contract does not require the contractor to provide a separate field office for the Contracting Officer, but does require the contractor to provide field laboratories for quality assurance and quality control testing.
- Questions were asked about the fence quantities, post lengths, gate details, and bracing quantities, which were addressed through an addendum.
- The contractor is responsible for obtaining the appropriate NPDES permit to cover the project activities.
- The estimated cost range for the project is between $10,000,000 and $20,000,000.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Tabulation.pdf | ||
| Bid Opening Summary.pdf | ||
| QnA 8.19.24.pdf | ||
| A003.pdf | ||
| A002.pdf | ||
| QnA 8.15.24.pdf | ||
| A001.pdf | ||
| QnA 8.1.24.pdf | ||
| CO FLAP MES 18(1) 18 Road Final Hydraulics Report with Addendum.pdf | ||
| Pavement Report CO FLAP MES 18(1) 18 Road 20240613.pdf | ||
| CO FLAP MES18(1) Plans Final - 06_20_2024.pdf | ||
| 6982AF24B000013.pdf | ||
| CO FLAP MES18(1) Cross Sections Final - 06_20_2024.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for CO FLAP MES 18(1) 18 Road
August 5, 2024
Questions Answers 1 After adding up all the fence they have I am coming up with
11,045' Almost twice as much as the bid quantity. Do we know why?
Addendum 001 updates notes and quantities to correct and clarify.
2 They want 76'' T-posts according to the detail. 72'' posts would give them 30'' in the ground. 2' in ground is the CDOT Standard.
Is 30'' adequate?
Addendum 001 updates to allow 72” post length with 30” embedment.
3 They show gates on the detail but I don't see gates on the plans or Bid Tab. Am I missing them?
No gates are being replaced as part of the project.
4 They don't have quantities for End and Corner Braces. This leaves a lot to interpretation as far as the overall price of the estimate.
Would they be willing to give a estimate on brace quantities?
Design and locations of brace and corner posts are not quantified or identified in the plans.
5 Can a rainfall erosivity waiver be utilized for a portion of this project?
The contractor is responsible for researching and obtaining the appropriate NDPES permit which will cover the activity outlined in the contract.
6 What is the anticipated start date for this project? Fall 2024. Reference special contract requirements and solicitation for calendar and seasonal restrictions.
7 Does the contractor need to provide a lab trailer for QA and a second one for QC?
Refer to Amendment A0001, and the Notice to Bidders, Pay Item 15401- 0000, Contractor testing on Page A-4 of the solicitation for more information on Contractor-furnished and Government-furnished field laboratories.
8 Will the contractor need to supply a separate field office for the
CO?
No
August 8, 2024
File details come from the government source that posted it. Updated .