Part 4A - Drawings 657-20-109JB Building 23 and 25 HVAC.pdf
PDF 10 MB Posted
- Solicitation number
- 36C25522R0021
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
H101H103
109 110 111 112
114 115 116
113A
H103A
112A
112B
H201
H203
212A
210 209
209A
209B
209C 209D
207 205
208A
208B
303A
304 305 306
308A
308B 308C
309 310
312304A 307A
309A
AREA OF WORK
FIRST FLOOR HAZARDOUS REMOVAL PLAN BUILDING 25
SCALE: 1/8" = 1'-0"
SECOND FLOOR HAZARDOUS REMOVAL PLAN BUILDING 25
SCALE: 1/8" = 1'-0"
THIRD FLOOR HAZARDOUS REMOVAL PLAN BUILDING 25
SCALE: 1/8" = 1'-0"
AREA OF WORK
AREA OF WORK
PLAN NOTES:
1. ALL WORK TO BE DONE WEEKNIGHT HOURS AND OVER WEEKEND HOURS.
2. STEAM, CONDENSATE RETURN, CHILLED WATER SUPPLY AND/OR RETURN
PIPING THAT REQUIRES ABATEMENT; SEE SPECIFICATIONS.
3. DOOR WITH WALK OFF MAT.
4. WITHIN SCOPE OF WORK, ANY PEELING OR DAMAGED PAINT SHOULD BE
STABILIZED AND CLEANED UP PER EPA GUIDELINES.
5. PORTION OF WALL WITH DUCT PENETRATION TO HAVE LEAD PAINT
STABILIZATION.
6. STOP ASBESTOS REMOVAL AT WALL, FLOOR, AND CEILING PENETRATIONS.
SPECIALTY NOTES:
A. SECURITY
1. CONTRACTOR SHALL NOT LEAVE DOORS PROPPED OPEN.
2. CONTRACTOR SHALL NOT LEAVE TOOLS OR LADDERS UNATTENDED.
3. CONTRACTOR SHALL NOT LEAVE ELECTRICAL OR DATA PANELS EXPOSED.
B. PHOTOGRAPHY
1. NO PHOTOGRAPHY OF VA PREMISES IS ALLOWED WITHOUT WRITTEN PERMISSION OF THE
COR. IF PERMISSION IS GRANTED BY THE COR, NO PHOTOGRAPHY IS PERMITTED OF
PERSONNEL, PATIENTS, COMPUTER SCREENS, LICENSE PLATES, OR ANY OTHER SENSITIVE
MATERIAL AS DETERMINED BY THE COR.
C. BADGING
1. ALL CONTRACTOR PERSONNEL ARE REQUIRED TO DISPLAY VA BADGE WHEN WORKING ON
STATION.
2. TWO-WEEK NOTICE IS REQUIRED FOR BADGING OF CONTRACTOR PERSONNEL REQUIRING A
FLASH PASS/BADGE ABOVE WAIST.
D. KEYS
1. COORDINATE WITH VA COR FOR ACCESS AND ISSUING OF KEYS.
E. JOBSITE PLAN
1. JOBSITE PLAN MUST BE SUBMITTED PRIOR TO COMMENCEMENT OF WORK
a. INCLUDES
1. ENTRANCES USED
2. MATERIAL MOVEMENT PLAN
3. RESTROOMS TO BE USED
4. LIST OF SUBCONTRACTORS
5. SITE PLAN (LAYDOWN AREA, JOBSITE TRAILER LOCATION, DUMPSTER LOCATION)
6. PERSONNEL ON SITE
F. TRAILER STORAGE
1. CONTRACTORS ARE REQUIRED TO COORDINATE TRAILER STORAGE LOCATION WITH COR.
G. CONTRACTOR SHALL NOTIFY COR OF ANY MATERIAL REMOVED CONTAINING EE# OR
MAXIMO NUMBER.
1. CONTRACTOR SHALL NOTIFY COR OF ANY NEW EQUIPMENT AND/OR SPECIFIC
REQUIREMENTS FOR EQUIPMENT (I.E. SPECIAL OUTLETS, ADEQUATE BREAKER SIZE, ETC.).
(MAKE, MODEL, SERIAL NUMBER)
H. UTILITY SHUTDOWNS
1. MUST BE COORDINATED WITH COR 21 DAYS IN ADVANCE.
I. FIRESTOPPING
1. INSTALL TEMPORARY FIRESTOPPING IN ALL NEW CORE DRILLED PENETRATIONS IN FLOOR
AND WALLS. ENSURE FIRESTOPPING IS MAINTAINED THROUGHOUT CONSTRUCTION UNTIL
PENETRATIONS ARE PERMANENTLY FIRE STOPPED.
K. FIRE ALARM/SPRINKLER
1. IF FIRE ALARM AND/OR SPRINKLER SYSTEM IS DISABLED DURING CONSTRUCTION,
HEAT DETECTION MUST BE PROVIDED. SIEMENS MUST MAKE FINAL TERMINATIONS AND
PROGRAM INTO EXISTING FIRE ALARM SYSTEM.
J. ILSM
1. TEMPORARY FIRE EXTINGUISHERS SHALL BE APPROPRIATELY MOUNTED AND SPACED
DURING CONSTRUCTION FOR HOUSEKEEPING AND SAFETY REQUIREMENTS.
a. TRAVEL DISTANCE FROM ANY POINT OF THE PROTECTED AREA TO THE NEAREST FIRE
EXTINGUISHER SHALL NOT EXCEED 100 FEET.
L. EXIT PATHS MUST BE LITTER/DEBRIS FREE.
M. THE CONTRACTOR IS RESPONSIBLE FOR MOVING, STORING AND PROTECTING ALL EXISTING
FURNITURE AND EQUIPMENT IN EACH AREA FOR THE DURATION OF THE PROJECT.
FURNITURE AND EQUIPMENT DAMAGED BY THE CONTRACTOR WILL BE REPLACED OR
RESTORED TO COMPLETE FUNCTIONALITY AND APPEARANCE BY THE CONTRACTOR AT NO
COST TO THE VA.
LEAD ABATEMENT NOTES:
1. ALL LEAD-BASED PAINT SHALL BE REMOVED FROM THE DOOR
ATTACHED TO ROOM 108.
MOLD REMEDIATION NOTES:
1. REMOVE AND DISPOSE OF ALL FIBERGLASS PIPE INSULATION AND DISPOSE AS
GENERAL CONSTRUCTION DEBRIS IN ROOMS 108, 210, AND 305.
2. CLEAN ALL SURFACES (FLOORS, WALLS, AND CEILINGS) IN ROOMS 108, 210, AND 305.
ASBESTOS ABATEMENT NOTES:
1. ABATEMENT CONTRACTOR SHALL REMOVE ALL ASBESTOS-CONTAINING
MATERIALS IN THE MARKED AREAS IDENTIFIED.
SCOPE OF WORK
The contractor shall follow all applicable MDNR, EPA, and OSHA rules and regulations. The Contractor shall install plywood barriers and/or lock doors with sufficient signage to isolate the work area in order to prevent access by unauthorizes personnel. Barriers shall be constructed in accordance with MDNR rules and regulations.
Contractor shall provide all worker paperwork to Geo-Enviro Consultants, Inc.'s on-site project manager at the beginning of the shift on the first day of the project. If additional workers arrive during the duration of the project, their paperwork shall also be provided to the Geo-Enviro Consultants, Inc.'s project manager. For asbestos workers and supervisors, this includes copies of their current MDNR license, training certificate, physical, and fit test for each person. All persons involved shall have his/her MDNR “hard card” license on-site each and every day said person is on-site. Any and all workers who do not provide the required documentation shall not be admitted to the project site by the Geo-Enviro Consultants, Inc. project manager.
The asbestos abatement materials include the removal of pipe system insulation and fittings, and fan coil units.
Lead-Based paint to be abated includes white paint on plaster ceilings and walls, blue paint on concrete walls and yellow ceramic tile.
Mold remediation to include the cleaning of all surfaces and the removal and disposal of all ceiling tiles in Room G05 ONLY.
All asbestos abatement work shall utilize wet methods.
Tented mini-containment areas shall consist of critical seals and one layer of 6-mil poly on the floors, walls, and ceiling of the tent.
Each tented mini-containment work area shall include critical seals over all doorways, windows, and ventilation system openings. Negative air pressure may be provided by HEPA vacuum cleaning equipment (remaining ibn operation for the duration of the project) and negative air may be discharged to the interior or exterior of the building. Contractor shall install a 1-chamber airlock to each tented containment work area for the worker entry/exit. A remote 5-chamber decon with negative air machine attached to the dirty room and exhausting outside the building shall be constructed.
For tented mini-containment work areas, the contractor shall employ a double disposable suiting procedure. The outer “dirty” suit shall be removed immediately prior to exiting a mini-containment, and a new “clean” outer suit shall be donned immediately prior to entering another mini-containment.
Full containment work areas shall consist of critical seals, two layers of 4-mil poly on the walls, and one layer of 6-mil poly on the ceiling. An attached 5-chamber decon and 2-chamber waste out shall be constructed at the entry to the full containment work area.
The contractor shall provide a manometer for the full containment work area to ensure that a negative pressure of 0.02” w.c. is maintained throughout the duration of the project. All negative air exhaust tubing shall be vented outside the work area.
All waste shall be adequately wet and double-bagged. Waste containers shall be labeled and leak-proof. All waste with sharp-edged components (e.g. nails, screws, metal lath, floor tile, etc.)
shall be placed into drums for disposal. All equipment and double-bagged/labeled waste shall be transported from the work area directly to an enclosed, lockable, signed, and poly-lined dumpster. All double-bagged and labeled waste shall be transported from the work area in a covered gondola. No waste shall be left within the building overnight.
All electrical systems shall be shut down and locked out. All electrical power within the work areas shall be “ground-fault protected” utilizing Ground Fault Circuit Interrupters. The contractor is required to handle all electrical shutdowns. Temporary lighting contractor's responsibility and shall be provided as necessary.
The owner will assist the contractor with electrical shutdowns and HVAC isolation within the work area. The building owner shall be responsible for maintaining appropriate life safety code requirements, including fire protection, for the building for the duration of the project.
After all abatement and cleaning activities are complete in any particular work area, the contractor shall apply a lock-down encapsulant on all materials in which asbestos or asbestos-contaminated materials were removed. This shall be conducted prior to clearance air sampling. Clearance air samples shall be collected when the cleanliness of the work area is to the satisfaction of the on-site project manager, and the required amount of hangtime has elapsed.
In all areas of abatement, contractor shall be responsible for investigating all rooms adjacent to all work areas during teardown activities. If any debris of any kind is identified in any room adjacent to an abatement work area, the contractor shall be responsible for the cleanup of that debris utilizing HEPA-vacuuming and wet methods.
Clearance is to be performed by aggressive TEM sampling methods and will be provided by Geo-Enviro Consultants, Inc's on-site project manager.
NOTES - GENERAL
1. Work will be completed following all applicable requirements.
2. The owner will not accept any change orders based on the contractor's failure to recognize unique conditions.
3. All permits and fees that need to be filled are the responsibility of the contractor. A copy of these permits and receipts shall be supplied to the owner's representative prior to start of work.
4. The owner will assist in the coordination for hooking up electrical equipment, if needed. The contractor will be responsible for supplying a licensed electrician.
5. The contractor is to use only MDNR-licensed workers.
6. The contractor's MDNR-licensed supervisor must be on-site at all times.
7. The contractor is responsible for supplying electrical power to the work area from the existing electrical panel as shown on the plans.
8. The contractor shall be responsible for supplying adequate protection for workers.
9. The contractors shall comply with applicable building and safety requirements.
10.Walk-off mats shall be required at all entrances to work areas.
11.The contractors may be responsible for additional project management and air sampling, and any additional associated costs (including sampling) incurred due to contractor delays and/or contractor failure to perform.
1. ASBESTOS-CONTAINING PIPE INSULATION - APPROXIMATELY 390 LINEAR FEET.
2. ASBESTOS-CONTAINING PIPE FITTINGS - APPROXIMATELY 95 TOTAL.
ASBESTOS ABATEMENT ESTIMATE:
INFORMATION CONCERNING THE LOCATION(S) AND SIZES OF EXISTING MECHANICAL EQUIPMENT, ELECTRICAL EQUIPMENT, PIPING, PLUMBING AND DUCTWORK WAS OBTAINED FROM ORIGINAL
DESIGN DRAWINGS AND/OR CURSORY FIELD OBSERVATION, HOWEVER, ACTUAL "ASBUILT"
DRAWINGS WERE NOT AVAILABLE, CERTAIN INFORMATION CONCERNING THE LOCATION OF THE
EXISTING MECHANICAL EQUIPMENT, ELECTRICAL EQUIPMENT, PIPING, PLUMBING AND DUCTWORK HAS BEEN ASSUMED IN THIS DRAWING. THE EXACT LOCATION(S) AND DIRECTION OF FLOW OF ALL EXISTING WORK IS UNKNOWN. REASONABLE EFFORT HAS BEEN MADE TO ACCURATELY DEPICT THE
EXISTING CONDITIONS, HOWEVER, ALL EXISTING WORK MUST BE VERIFIED IN THE FIELD TO
DETERMINE THE EXACT LOCATIONS, DIRECTIONS OF FLOW, DEPTH, SIZE, ETC.. PRIOR TO STARTING CONSTRUCTION. ANY CONFLICT BETWEEN THESE PLANS AND ACTUAL FIELD CONDITIONS SHALL BE
REPORTED IMMEDIATELY TO THE ENGINEER FOR VERIFICATION AND/OR CORRECTION.
FIELD VERIFY:
EX-AHU-2
EX-AHU-3
GJ201
CONSULTANTS: ARCHITECT/ENGINEERS:
Revisions: Date:
Drawing Title
VA Health Care System Approval:
Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
Drawing # of
Veterans Health
Administration
FCA - REPLACE MECHANICAL
EQUIPMENT IN BUILDINGS 23 & 25
657-20-109JB
www.daengineering.com www.daengineering.com voice (317) 464-9090 2707 Rand Road Indianapolis, Indiana 46241 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC. JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
07-09-2021 DEH MV
ARCHITURA CORPORATION
9880 Westpoint Drive, Suite #400 Indianapolis, IN 46256-3384
PH: (317) 348-1000
POC: Michael Conly, AIA, NCARB, President
P R O F E S S I O N A L E N G I N E E R
PE-2021014461
HANNAH
ROSE
KIGER
S
TA
TE
OF MI SSOUR
I
25-HA-11231
BID DOCUMENTS
FIRST, SECOND, AND THIRD FLOOR
OVERALL HAZARDOUS MATERIAL
REMOVAL PLAN BUILDING 25
8 36
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
ALL ICRA WALLS ARE TO BE TYPE 'FA' U.N.O.
PROVIDE LATERAL BRACING FOR PARTITIONS WHICH EXTEND ABOVE CEILINGS.
PROVIDE FIRE RESISTIVE RATED GYPSUM WALL BOARD AT ALL RATED ASSEMBLIES TO
MEET ASSEMBLY REQUIREMENTS.
PROVIDE FIRE RESISTIVE JOINT SYSTEMS EQUAL TO WALL RATING AT ALL PENETRATIONS
AND AT HEAD/FLOOR INTERSECTIONS WITH RATED ASSEMBLIES.
PROVIDE ACOUSTICAL SEALANT AT WALL SILL, HEAD, PENETRATIONS, AND ADDITIONAL
SPECIFIED SOUND ATTENUATION COMPONENTS AT SOUND RATED WALLS.
FRAME DOOR OPENINGS 4" FROM FACE OF PERPENDICULAR WALL ON HINGE SIDE AND 1'-
6" MIN. FROM FACE OF PERP. WALL ON LATCH SIDE, UNLESS NOTED OTHERWISE.
PROVIDE GYPSUM BOARD CONTROL JOINTS AND MASONRY CONTROL JOINTS AT WALLS
OVER 30'-0" LENGTH. LOCATE ABOVE EDGE OF OPENING WHEN POSSIBLE.
AT FIRE RATED WALLS WHERE OPENINGS ARE GREATER THAN 16 SQUARE INCHES OR
WHERE TOTAL AREA OF OPENINGS EXCEEDS 100 SQUARE INCHES IN 100 SQUARE FEET,
WRAP 5/8 TYPE 'X' GYPSUM BOARD BEHIND OPENINGS PER U.L. DESIGN #U510.
ISOLATE NON-LOAD-BEARING STUD FRAMING FROM BUILDING STRUCTURE TO PREVENT
TRANSFER OF VERTICAL LOADS INTO PARTITION WHILE PROVIDING LATERAL SUPPORT
REQUIRED VIA USE OF DOUBLE TRACK TYPE (SECONDARY TRACK SET INSIDE DEEP-LEG
TRACK) OR SLOTTED TRACK TYPE, EACH ALLOWING VERTICAL MOVEMENT OF THE
STRUCTURE, PREVENTING ROTATION OF STUDS BUT MAINTAINING STRUCTURAL
PERFORMANCE OF PARTITION.
LINE OF STRUCTURE INDICATED FOR EACH PARTITION IS DIAGRAMMATIC ONLY AND DOES
NOT INDICATE EXACT CONSTRUCTION CONDITIONS OR GEOMETRY.
FIRE RESISTANCE RATED PARTITIONS SHALL USE RATED FIRE RESISTANT FILL MATERIAL
IN CONJUNCTION WITH AN APPROPRIATE RATED FIRESTOPPING SYTEM.
NON-RATED PARTITIONS SHALL USE ACOUSTICAL SEALANT.
PROVIDE SHEET METAL OR FIRE RETARDANT WOOD BLOCKING IN WALL CAVITIES FOR
ITEMS THAT ARE REQUIRED TO BE SECURED TO THE WALLS, INCLUDING ALL CABINETRY,
SHELVING, WALL STOPS, WALL MOUNTED EQUIPMENT, AND ALL OTHER WALL MOUNTED
ITEMS. REFERENCE MECHANICAL, PLUMBING, ELECTRICAL AND TECHNOLOGY
DRAWINGS. COORDINATE WITH FURNITURE SUPPLIER WHERE APPROPRIATE.
TAPE AND SPACKLE ALL PENETRATIONS IN GYPSUM BOARD PARTITIONS, INCLUDING, BUT
NOT LIMITED TO WATER LINES, DRAINS, CONDUIT, THERMOSTATS, ETC. INSTALL FIRE
RETARDANT SEALANT AT PENETRATIONS IN RATED PARTITIONS AS REQUIRED.
FOR PARTITIONS INDICATED TO RECEIVE SOUND ATTENUATION (S), EXTEND ATTENUATION
TO FULL HEIGHT OF PARTITION U.N.O. FLOOR TRACK TO BE SET IN A CONTINUOUS BED
OF SEALANT.
IN AREAS DESIGNATED TO HAVE A RATED CEILING, BUILD WALLS THAT ARE NOT
INDICATED TO GO TO DECK TO UNDERSIDE OF RATED CEILING.
ALTHOUGH WALL STUD SIZE / SPACING ARE LISTED, CONTRACTOR WILL VERIFY AND
PROVIDE APPROPRIATE SIZE / GAGE / SPACING OF STUDS REQUIRED FOR CONDITIONS
INDICATED AND NOTIFY ARCHITECT OF ANY DISCREPANCY PRIOR TO FABRICATION /
INSTALLATION.
ENLARGED DRAWING REFERENCE
ELEVATION DATUM REFERENCE
NORTH ARROW
DRAWING NUMBER
SHEET NUMBER
BUILDING SECTION CUT REFERENCE
SF27
A101
SIM
W3
KEYED NOTE
REVISION REFERENCE
WINDOW TAG
DOOR TAG
ROOM NAME AND NUMBER
COLUMN GRID NEW
A
DRAWING NUMBER
SHEET NUMBER
WALL SECTION CUT REFERENCE
DRAWING NUMBER
SHEET NUMBER
EXTERIOR ELEVATION REFERENCE
WALL TYPE REFERENCE (REFERENCE
INTERIOR PARTITION LEGEND)
COLUMN GRID EXISTING
1 EQUIPMENT TAG
X
XX
X
XX
1 Ref
XX
Room
A.
B.
C.
D.
E.
F.
G.
COORDINATE WORK OF ALL TRADES PRIOR TO STARTING CONSTRUCTION.
ALL DIMENSIONS ARE TO GRID LINES, FACE OF STUD FRAMING, FINISHED FACE OF
EXISTING WALL SURFACE, OR FACE OF CONCRETE / MASONRY UNITS UNLESS NOTED
OTHERWISE.
THE CONTRACTOR AND SUBCONTRACTORS INVOLVED IN THIS PROJECT SHALL BE
RESPONSIBLE FOR DESIGNING AND INSTALLING THEIR RESPECTIVE WORK AND
SYSTEMS TO MEET ALL APPLICABLE FEDERAL, STATE, AND LOCAL CODES, LAWS,
SAFETY REGULATIONS, HAZARDOUS WASTE LAWS, ETC. THE CONTRACTOR SHALL
FURNISH ALL NECESSARY PERMITS.
THE CONTRACTOR SHALL REVIEW THE DRAWINGS AND UNDERSTAND THE SCOPE OF
THE DRAWINGS TO BE THE FOLLOWING: THESE CONSTRUCTION DOCUMENTS
(DRAWINGS, SPECIFICATIONS, ADDENDA, ETC.) INDICATE THE GENERAL SCOPE OF THE
PROJECT IN TERMS OF ARCHITECTURAL DESIGN CONCEPTS, THE DIMENSIONS OF THE
BUILDING, THE MAJOR ARCHITECTURAL ELEMENTS, AND THE MAJOR STRUCTURAL,
MECHANICAL, AND ELECTRICAL SYSTEMS. THE DOCUMENTS DO NOT AND ARE NOT
INTENDED TO INDICATE OR DESCRIBE IN DETAIL ALL THE NECESSARY WORK REQUIRED
FOR FULL PERFORMANCE OF, AND COMPLETION OF THE REQUIREMENTS OF THE
CONTRACT. ON THE BASIS OF THE GENERAL SCOPE INDICATED IN THESE DOCUMENTS,
THE TRADE CONTRACTORS SHALL FURNISH ALL ITEMS REQUIRED FOR THE PROPER
EXECUTION AND COMPLETION OF THEIR WORK. ALL WORK SHALL BE COMPLETE IN
EVERY DETAIL AND THE CONTRACTORS SHALL PROVIDE A ONE YEAR WARRANTY FOR
THEIR WORK.
CONTRACTORS SHALL FOLLOW AND OBEY ALL FEDERAL, STATE AND LOCAL CODES,
LAWS, SAFETY REGULATIONS AND HAZARDOUS WASTE LAWS, ETC.
DO NOT SCALE DRAWINGS. DIMENSIONS SHALL GOVERN EACH BUILDING COMPONENT
LOCATION. BRING ANY DISCREPANCIES TO THE ARCHITECT'S ATTENTION IN WRITING
IMMEDIATELY.
ALL WORK SHALL BE PERFORMED IN A SKILLED WORKMANSHIP TYPE AND MANNER
ACCEPTABLE TO THE ARCHITECT AND OWNER.
CAULK INTERSECTION BETWEEN DIFFERENT MATERIALS.
CAULK TOILET FIXTURES AND COUNTERTOP SPLASHES TO FINISH SURFACE IN
ACCORDANCE WITH SEALANT SCHEDULE IN SPECIFICATIONS.
EXISTING CONDITIONS SHALL BE FIELD VERIFIED PRIOR TO BIDDING OR BEGINNING OF
WORK. ANY ERRORS OR OMISSIONS SHALL BE BROUGHT TO THE ARCHITECT'S
ATTENTION IN WRITING IMMEDIATELY.
COVER ALL RETURN AIR AND EXHAUST GRILLES WITH FILTER MEDIA FOR DURATION OF
JOB AND CHANGE REGULARLY.
EARTH
NOTE: PATTERNS SHOWN REPRESENT CUT
MATERIALS IN PLAN OR SECTION, UNLESS NOTED
OTHERWISE.GRANULAR FILL
CONCRETE, CAST-IN-PLACE
CONCRETE, PRECAST/CAST
STONE
CONCRETE MASONRY UNIT
BRICK MASONRY
STONE: LIMESTONE, GRANITE,
MARBLE OR AS NOTED
METAL: TYPE AS NOTED
METAL: ROLLED SHAPES
WOOD FRAMING / BLOCKING:
CONTINOUS
WOOD SHIM
WOOD/FINISHED,
SHOWN CUT AND ELEVATION
PLYWOOD
PARTICLEBOARD
EIFS
SPRAYED FIREPROOFING
SHOWN ON ROLLED SHAPE
BATT INSULATION: THERMAL OR
ACOUSTICAL, UNO
RIGID INSULATION: THERMAL,
ACOUSTICAL, OR SAFING
SHEATHING: GYPSUM, OR AS
NOTED
GYPSUM WALL BOARD
TILE: CERAMIC, QUARRY, UNO
RESINOUS FLOORING: TERRAZO,
TROWEL-ON, UNO
ACOUSTICAL CEILING TILE
GRATING (PLAN)
INSULATED GLASS:
(SMALL SCALE)
GRATING (SECTION)
MEMBRANE: WATERPROOF,
ROOF, DAMPPROOFING
AIR BARRIER SYSTEM
INSULATED GLASS:
(DETAIL)
TERRA COTTA, STRUCTURAL CLAY
TILE
CARPET, CARPET TILE (DETAIL)
SAND, GROUT
AS NOTED
GLASS FIBER REINFORCED
CONCRETE SIDING OR TRIM
WOOD/ENGINEERED: GLUE
LAMINATED
PLASTER ON METAL LATH
WOOD FLOOR, WOOD SHINGLES,
OR SIDING
F2
F3
F6
F1 F1S
WALL PARTITION TYPE
4"
PL
AN
V
IE
W
SE
CT
IO
N
VI
EW
SE
CT
IO
N
VI
EW
REMARKS
NON-
RATED
NON-
RATED
NON-
RATED
REFER TO SCHEDULE BELOW FOR PARTITION WIDTH
NON-
RATED
F
METAL STUD FRAMING @ 16" O.C. MAX.
ONE LAYER 5/8" (TYPE-X) GYPSUM WALL BOARD, ONE SIDE
PROVIDE SOUND ATTENUATION INSULATION AS REQUIRED - SEE SCHEDULE BELOW
METAL RUNNER
SEALANT AND BACKER ROD; ONE SIDE, CONT.
ADDITIONAL WALL FINISH (SHOWN DASHED) ON ONE OR BOTH SIDES WHERE
OCCURS; REFER TO FLOOR PLANS AND ROOM FINISH SCHEDULE FOR
OCCURRENCE, LOCATION, AND EXTENT OF WALL COVERAGE. 5/8" MOISTURE
RESISTANT GYPSUM WALL BOARD REPLACES TYPE-X AS SUBSTRATE IN ALL
RESTROOMS AND JANITOR'S CLOSETS,TYPICAL.
METAL RUNNER
LINE OF
STRUCTURE
UNDERSIDE
OF
STRUCTURE
LINE OF
CEILING
STUD
WIDTH
PART.
WIDTH
FIRE
RATING
UL LISTING
WITH SOUND
ATTENUATION
DESIGNATION
NO SOUND
ATTENUATION
DESIGNATION
NA
NA
NA
NA
2 - 1/4"
3 - 1/8"
4 - 1/4"
6 - 5/8"6"
3 - 5/8"
2 - 1/2"
1 - 5/8"
STC:
NO SOUND
WITH SOUND
F2S
F3S
F6S
F8
NON-
RATED NA8 - 5/8"8"
F8S
LATERAL BRACING AT 4'-0" O.C. MAX.
ABBREVIATIONS
P
PERM PERMANENT
PH PHASE
PL PLATE
PLAM PLASTIC LAMINATE
PLAS PLASTIC
PNL PANEL
PREFAB PREFABRICATED
PREFIN PREFINISHED
PRELIM PRELIMINARY
PREP PREPARATION
PROJ PROJECT
PT PRESERVATIVE
TREATED
PTD PAINTED
PTN PARTITION
Q
QT QUARRY TILE
R
R RADIUS
RD ROOF DRAIN
REC RECESSED
RECPT RECEPTACLE
REF REFER(ENCE)
REINF REINFORCE(D)(ING)(M
ENT)
REQD REQUIRED
RESIL RESILIENT
RM ROOM
RO ROUGH OPENING
RTU ROOF TOP UNOT
S
SAN SANITARY
SCW SOLID CORE WOOD
SF SQUARE FOOT
SPKLR SPRINKLER
SS STAINLESS STEEL
STD STANDARD
STL STEEL
STOR or ST STORAGE
STRUCT STRUCTURAL
SUSP SUSPENDED
SYM SYMBOL
SYS SYSTEM
T
T&G TONGUE AND
GROOVE
T/ TOP OF
TEL TELEPHONE
TEMP TEMPORARY
THRES THRESHOLD
TOT TOTAL
TYP TYPICAL
U
UNIF UNIFORM
UNO UNLESS NOTED
OTHERWISE
UR URINAL
V
VB VINYL BASE
VCT VINYL COMPOSITION
TILE
VERT VERTICAL
VIN VINYL
VT VINYL TILE
VWC VINYL WALL
COVERING
W
W/W WALL TO WALL
WC WATER CLOSET
WD WOOD
WDW WINDOW
WH WALL HUNG
WT WEIGHT
G
GALV GALVANIZED
GLZ GLAZING
GUT GUTTER
GYP BD/GWB GYPSUM BOARD
H
HC HANDICAP(PED)
HCW HOLLOW CORE WOOD
HDWE/HDW HARDWARE
HM HOLLOW METAL
HMD HOLLOW METAL DOOR
HORIZ HORIZONTAL
HT HEIGHT
HVAC HEATING,
VENTILATION, AIR
CONDITIONING
I
ICF INSULATED
CONCRETE FORM
ID INSIDE DIAMETER
IF INSIDE FACE
INCAND INCANDESCENT
INDIC INDICATE
INSTL INSTALL(ATION)
INSUL INSULATION
INT INTERIOR
J
JST JOIST
JT JOINT
L
LAV LAVATORY
LD BRG LOAD BEARING
LF LINEAR FOOT
LTG LIGHTING
LTWT LIGHTWEIGHT
LVR LOUVER
M
MAS MASONRY
MATL MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MED MEDICINE (MEDICAL)
MET METAL
MFG MANUFACTURER (ING)
MIN MINIMUM
MISC MISCELLANEOUS
MLWK MILLWORK
MO MASONRY OPENING
MTD MOUNTED
MTG MOUNTING
MULL MULLION
MULT MULTIPLE
N
N/A NOT APPLICABLE
NIC NOT IN CONTRACT
NOM NOMINAL
NTS NOT TO SCALE
O
O/O OUT TO OUT
OA OVERALL
OC ON CENTER
OD OUTSIDE DIAMETER
OF OUTSIDE FACE
OFCI OWNER FURNISHED -
CONTRACTOR
INSTALLED
OH OVERHEAD
OPNG OPENING
OPP OPPOSITE
OPT OPTIONAL
ORD OVERFLOW ROOF
DRAIN
ORIG ORIGINAL
A
A/E ARCHITECT/ENGINEER
ACOUS ACOUSTICAL
ACT ACOUSTICAL CEILING
TILE
ADA AMERICAN'S WITH
DISABILITIES ACT
ADD ADDENDUM
ADJ ADJACENT
AFF ABOVE FINISH FLOOR
ALT ALTERNATE
ALUM ALUMINUM
ANOD ANODIZED
ARCH ARCHITECT (URAL)
B
BLDG BUILDING
BLK BLOCK
BLKG BLOCKING
BM BEAM
BOT BOTTOM
BRG BEARING
C
C/C CENTER TO CENTER
CAB CABINET
CB CORNER BEAD
CER CERAMIC
CF CUBIC FOOT
CFCI CONTRACTOR
FURNISHED /
CONTRACTOR
INSTALLED
CHAN CHANNEL
CJ CONTROL JOINT
CL CENTER LINE
CLG CEILING
CMU CONCRETE MASONRY
UNIT
CONC CONCRETE
CONSTR CONSTRUCTION
CONT CONTINUOUS
CP/CPT CARPET
D
DEMO DEMOLITION (ISH)
DF DRINKING FOUNTAIN
DIFF DIFFUSER
DIM DIMENSION
DISP DISPENSER
DO DOOR OPENING
DS DOWNSPOUT
DWG DRAWING
E
EJ EXPANSION JOINT
ELEC ELECTRICAL
(ELEVATOR)
ELEV ELEVATION
ENCL ENCLOSURE
ENGR ENGINEER
EQUIP EQUIPMENT
EWC ELECTRICAL WATER
COOLER
EXST EXISTING
F
F/F FACE TO FACE
FDN FOUNDATION
FE FIRE EXTINGUISHER
FHC FIRE HOSE CABINET
FIN FINISH
FIN FL FINISHED FLOOR
FLR (FLRG) FLOOR(ING)
FLUOR FLUORESCENT
FOC FACE OF CONCRETE
FOF FACE OF FINISH
FOM FACE OF MASONRY
FOS FACE OF STUD
FR FIRE RATING
FT FIRE TREATED
FTG FOOTING
FURN FURNITURE
FURR FURRING
WALL PARTITION TYPEGRAPHIC LEGEND
MATERIALS LEGEND
GENERAL NOTES
GENERAL PARTITION NOTES
P. THE CONTRACTOR IS RESPONSIBLE FOR MOVING, STORING AND PROTECTING ALL
EXISTING FURNITURE AND EQUIPMENT IN EACH AREA FOR THE DURATION OF THE PROJECT.
FURNITURE AND EQUIPMENT DAMAGED BY THE CONTRACTOR WILL BE REPLACED OR
RESTORED TO COMPLETE FUNCTIONALITY AND APPEARANCE BY THE CONTRACTOR AT NO
COST TO THE VA.
CONSULTANTS: ARCHITECT/ENGINEERS:
Revisions: Date:
Drawing Title
VA Health Care System Approval:
Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
Drawing # of
Veterans Health
Administration
FCA - REPLACE MECHANICAL
EQUIPMENT IN BUILDINGS 23 & 25
657-20-109JB
www.daengineering.com www.daengineering.com voice (317) 464-9090 2707 Rand Road Indianapolis, Indiana 46241 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC. JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
07-09-2021 DEH MV
ARCHITURA CORPORATION
9880 Westpoint Drive, Suite #400 Indianapolis, IN 46256-3384
PH: (317) 348-1000
POC: Michael Conly, AIA, NCARB, President
P R O F E S S I O N A L E N G I N E E R
PE-2021014461
HANNAH
ROSE
KIGER
S
TA
TE
OF MI SSOUR
I
23 & 25
00-AE-001
ARCHITECTURAL SYMBOLS AND
ABBREVIATIONS
BID DOCUMENTS
9 36
H103AH103A
AT CONTRACTORS
DISCRETION SUPPORT
MAY BE RELOCATED
INSTEAD OF PROVIDING
NEW; SEE REVISED PLAN
REMOVE PORTION OF
CATWALK AT
SUPPORTS AS SHOWN
NEW SUPPORT POST
OR RELOCATED; SEE
DEMO PLAN
BLDG. 25 ENLARGED FIRST
FLOOR DEMOLITION PLAN
SCALE: 1/4" = 1'-0"
D
BLDG. 25 ENLARGED FIRST
FLOOR REVISED PLAN
SCALE: 1/4" = 1'-0"
D
PLAN NOTES:
1. SAW CUT STRAIGHT EDGE ACROSS METAL DECK. GRIND EDGE SMOOTH; SEE
DETAIL C1, THIS SHEET.
2. SAW CUT HAND RAILS AS REQUIRED.
3. NEW VERTICAL RAIL TO MATCH DIAMETER AND LENGTH OF EXISTING. WELD TO
EXISTING "C" CHANNEL BASE AS REQUIRED.
4. INSTALL TWO CHAIN CATCH AND HOOK FOR FALL PROTECTION AS REQUIRED.
5. REMOVE PORTION OF CATWALK AND RAILINGS.
6. SEE REVISED DETAIL C3, THIS SHEET.
7. NEW 4' STEEL POST TO MATCH EXISTING CONSTRUCTION, FROM FLOOR UP TO
EXISTING CATWALK.
EXISTING CATWALK SUPPORT DETAIL
NO SCALE
D
SQUARE STEEL PLATE
BOLTED TO
CONCRETE FLOOR
4"Ø STEEL POST
8"x 2-1/4" STEEL
CHANNEL
8"x 2-1/4" STEEL
CHANNEL
STEEL ANGLE
1/4" CHECKERED
STEEL FLOOR PLATE
CATWALK DEMO
NO SCALE
C
CATWALK REVISED
NO SCALE
C
EX VERTICAL RAIL
EXISTING UPPER
CATWALK
EXISTING CATWALK
PLATFORM
DN
EXISTING CATWALK
PLATFORM
EXISTING CATWALK
PLATFORM
EXISTING UPPER
CATWALK
CONSULTANTS: ARCHITECT/ENGINEERS:
Revisions: Date:
Drawing Title
VA Health Care System Approval:
Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
Drawing # of
Veterans Health
Administration
FCA - REPLACE MECHANICAL
EQUIPMENT IN BUILDINGS 23 & 25
657-20-109JB
www.daengineering.com www.daengineering.com voice (317) 464-9090 2707 Rand Road Indianapolis, Indiana 46241 fax (317) 464-9393
Mechanical, Electrical, and Energy Engineering
DESIGN-AIRE ENGINEERING, INC. JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
07-09-2021 DEH MV
ARCHITURA CORPORATION
9880 Westpoint Drive, Suite #400 Indianapolis, IN 46256-3384
PH: (317) 348-1000
POC: Michael Conly, AIA, NCARB, President
P R O F E S S I O N A L E N G I N E E R
PE-2021014461
HANNAH
ROSE
KIGER
S
TA
TE
OF MI SSOUR
I
FIRST, SECOND, AND THIRD FLOOR
ARCHITECTURAL PLAN BUILDING 25
25-AE-11231
100% DESIGN DOCUMENTS
10 36
File details come from the government source that posted it. Updated .