This document is an addendum to an Invitation for Bid (IFB) issued by the Town of Yarmouth Department of Public Works for the Parkers River Bridge Complete Replacement and Widening project. The addendum includes clarifications and revisions to the scope of work, bid form, special provisions, and technical drawings. Key details include the addition of existing bridge plans, revisions to bid items and quantities, updates to special provisions related to sediment sampling and disposal, work schedule restrictions, and revisions to various plan sheets. The project involves the complete replacement and widening of the Route 28 (Main Street) bridge over Parkers River in Yarmouth, Massachusetts.
The bid form and special provisions outline pricing terms, measurement, and payment for the various work items, including excavation, piling, concrete, steel, and landscaping. No set-asides or incumbent information is provided. The project is funded by the municipality, and the contract term is not specified, though the work must be completed within the outlined schedule restrictions.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO.5
Town of Yarmouth Department of Public Works 99 Buck Island Road West Yarmouth, MA 02673
DATE ISSUED: Iuly 26,2019 TO: All Respondents of Record SUBJECT: Invitation For Bid:
Parkers River Bridge Complete Replacement and Widening
ADDENDUM NO.5
1. Please add 1932 Existing plans and 1896 Existing plans to the IFB documents. Both 1932 Existing Plans and 1896 Existing Plans are attached with this addendum.
2. Please add ITEM 143 to the end of Division 01 Special Provisions.
3. Delete Bid Form Pages 00410-6 through 00410-15 as included in Addendum
#2 dated June 24,2019 in its entirety and Replace with the attached revised bid form Pages 00410-6 through 00410-15 noted as Addendum #5.
4. Delete Special Provision page SP-I, and Replace with Addendum 5 Parkers River Special Provisions SP-l dated July 24,2019.
5. Delete Special Provision pages SP-3 through SP-6, and Replace with Addendum 5 Parkers River Special Provisions SP-3 through SP-6 dated July 24,2019.
6. Insert Addendum 5 Parkers River Special Provisions SP-9 dated JuJy 24,, 2019-
7. Delete Special Provision pages SP-17 through SP-18, and Replace with
Addendum 5 Parkers River Special Provisions SP-17 through SP-18 dated Jaly 24,2019.
8, Delete Special Provision pages SP-20 through SP-21, and Replace with Addendum 5 Parkers River Special Provisions SP-20 through SP-21 dated July 24,2019.
9. Delete Special Provision page SP-25, and Replace with Addendum 5 Parkers River Special Provisions SP-25 dated July 24,2019.
10. Delete Special Provisions page SP-27 and Replace with Addendum No.S, July
24,2019 SP-27.
11. Delete Special Provision page SP-82, and Replace with Addendum 5 Parkers River Special Provisions SP-82 dated July 24,2019.
12. Delete Special Provision page SP-84, and Replace with Addendum 5 Parkers River Special Provisions SP-84 dated Jaly 24,2019.
13. Delete Special Provisions page SP-96 and Replace with Addendum No.5, July 24,2019.
14. Delete Special Provisions pages SP-97 through SP-98 and Replace with Addendum No. 5, July 24,2019 SP-97 through SP-98.
Addendum #5 Page I
15. Delete Special Provisions pages SP-171and Replace with Addendum No. 5' July 24,2019 SP-l71.
16. Delete Sheet l-Title Sheet in its entirety and Replace with the revised sheet I noted Addendum no.5, July 24,2019
17. Delete Sheet S-Construction Plan in its entirety and Replace with the revised sheet 5 noted Addendum no.5, July 24,2019
18. Delete Sheet 6-Temporary Conditions Plane in its entirety and Replace with the revised sheet 6 noted Addendum no.5, July 24..2019
19. Delete Sheet l0-Drainage and Utility Plan in its entirety and Replace with the revised sheet 10 noted Addendum no.5, July 24,2019
20. Delete Sheet ll-Drainage and Utility Plan in its entirety and Replace with the revised sheet 11 noted Addendum no.5, July 24' 2019
21. Delete Sheet 2O-Temporaty Traffic Control Plan in its entirety and Replace with the revised sheet 20 noted Addendum no.5, July 24,2019
22. Delete Sheet 27-Key Plan, Profiles, Locus and Drawing Index (aka sheet 1 of33 Bridge No. Y-01-002)in its entirety and Replace with the revised sheet 27 noted Addendum no.5, July 24, 2019
23. Delete Sheet 35-Stage Construction- Bridge (aka sheet 9 of 33 Bridge No.Y-01-
002) in its entirety and Replace with the revised sheet 35 noted Addendum no.S, Jrrly 24,2019
24. Delete Sheet 45-Miscellaneous Details (aka sheet 19 of 33 Bridge No.Y-01-002) in its entirety and Replace with the revised sheet 45 noted Addendum no.5' Jnly 24,2019
25. Delete Sheet S4-Superstructure Details Sheet 1 of2 (aka sheet 28 of33 Bridge No.Y-01-002) in its entirety and Replace with the revised sheet 54 noted Addendum no.5, July 24, 2019
26. Questions and Answers:
o Question #l: On the Bid Form provided in Addendum 2, Items with Index numbers 8 & 9 are both Item 144 Class B Rock Excavation. There are two different quantities, what is the difference between these items?
o Answer #1: Refer to revised bid sheet within this addendum correcting the bid items and their quantities.
r Question #2: The specifications indicate that no silt producing in-water work is allowed between January l5th - June 30th and September I st - November 15th of each year. The specifications also indicate that work is not allowed between Memorial Day and Labor Day. Based on these restrictions, is it the intent to only perform work between November 1 5th and January 1 5th of each year? Will work in the water be allowed behind the cofferdam outside of the limits listed above? If so, will cofferdam installation and removal be limited to November 15th - January 15th ofeach year? Typical ACOE general permits allow for installation of cofferdams outside ofany in-water work restriction dates.
o Answer #2: Work is not limited as summarized in the question. Although silt producing in-water work is not allowed between January 15th - June 30th and
Addendum #5 Page 2
September 1st - November 15th ofeach year, work in the water behind cofferdams is allowed between January 15th - June 30th and September 1st - November 1 5th of each year. Installation and removal of the cofferdams are required to be in place prior to the time-of-year (TOY) restrictions noted above as noted in Condition #3 of the ACOE permit (Attachment G of the
Supplementary Conditions). No construction from Memorial Day weekend through Labor Day, except the Town and District Highway Director may consider approving a request from the Contractor to work between Memorial Day and June 15th as long as the proposed work activities are determined by the Town and District Highway Director to not impact traffic and are of minimal impact to the abutting business owners. Between Labor Day and
Memorial Day, no work will be performed on legal holidays and associated day before and after the long weekend as noted in the Work Schedule (SP-3).
o Question #3: There are two Bid Items for 144. Class B Rock Excavation, with different quantities. Please Clarify.
o Answer #3: Refer to answer for Question #1.
o Question #4: Can you please confirm t}rat grouted Rip Rap will be required at all locations where Rip Rap is shown, above Elevation 0.0? Ifnot, please provide the limits.
o Answer #4: Yes; all riprap above Elevation 0.0 shall be grouted.
o Question #5: Can you please provide drawings of the existing bridge' if available?
o Answer #5: Refer to two attachments labeled '1932 Existing Plans' & '1896 Existing Plans' o Question #6: Please confirm that work can occur during the summer months if two lanes ofvehicular and pedestrian traffic is maintained, per the provided
TTCP Phase Drawings.
o Answer #6: Refer to answer for Question #2.
o Question #7: The Method of Measurement and Basis of Payment Section for Item 942.124 Steel Pile HP 12x24 mentions "making and maintaining the pre-augured holes at the integral abutments." Can you please confirm pre-augured holes are not proposed for use on this project?
o Answer #7: Based on the soil information on the boring logs, pre-augering of pile holes is likely not needed. Refer to revised Special Provision for that item.
o Question #8: Please provide an anticipated duration/schedule for utility relocations to be used for bidding purposes, as this project has a hard end date and numerous time-of-year restrictions. This includes overhead utility relocations as well as Verizon's service connection activities.
o Answer #8: The Contractor shall be responsible for the coordination oftheir work supporting the utilities noted in the drawings and communicate the
Contractor's schedule with those individuals. Each utility is required to obtain
Addendum #5 Page 3 a separate MassDOT Highway access permit for their work 'by others' (BO) as noted within the Contract Drawings to integrate to their existing utility.
There has been coordination with utilities for the past 5+ years.
o Question #9: Please clariff whether disposal of the existing timber piles gets paid under Item 941.1 or Item 184.1.
o Answer #9: Removal of existing treated timber piles is measured in FT and paid under Item 941 . 1 Disposal of removed existing treated timber piles is measured in TON and paid under Item 184.1 o Question #10: Item # 143 - Channel Excavation - will fall under classification of "dredged materials" ,as specified in the DEP Dredge Permit, thereby requiring special testing/handling/disposing. MassDOT formatted bids incorporate bid items for the same-will the Town be adding bid items for dredged materials testing/handlingidisposing?
o Answer #10: The Town will not add bid items for dredged materials testingftrandling/disposing. Revised Section 1 43 is provided.
o Question #11: Bid Item # 995.01- Bridge Structure Y-01-002(BNF) - has no sub items for #482.31-sadseal ;960.1Structural Steel (utility supports).
Will items be included under the lump sum item 995.01?
o Answer #ll:ltem482.3l is included as a separate Item. Item 960.1 Structural
Steel- Coated Steel shall be included under the Bridge Lump Sum. Revised last page of special provisions Item995.01 is attached.
o Question#l2z Article 13.2Preparation of Bid (00100-6) states that the Bid Form must be completed in ink. We just wanted to clarify if this was indeed the case or if typed pages would be allowed?
o Answer #12: Ink applies to pen and computer ink. Signatures must be completed with pen ink.
Please sign below as receipt of ADDENDUM NO. 5 and include this page with your submission.
We have received and acknowledge ADDENDUM NO. 5 as part of IFB- Parkers River Bridge Complete Replacement and Widening
Company Name:
Authorized Signature:
Addendum #5 Page 4
Date:
'lbu,n of Yarmouth
ITEM 143. CHANNEL EXCAVATION CUBIC YARI)
The work to be done hereunder consists of removing dewatering and disposing in accordance with the relevant provisions of Section 140, all materials required for execution ofthe required work as shown on the Plans and as directed, except material for which payrnent is made under the items of Bridge Excavation, unclassified excavation and Class B Rock Excavation of this Contract, and except materials for which payment is made under other items ofthis Contract.
Sediment samples cannot be collected directly from the proposed excavation area because it is covered with large riprap armor. Two samples immediately upstream ofthe bridge were collected.
The results ofthe gradation and analysis revealed that the samples were course material with both having 1.5% of particles passing the number 200 US standard series testing sieve. According to the regulations chemical analysis ofthe sediment was not necessary because less than l0% past the number 200 sieve and the due diligence review demonstrated that the area was unlikely to contain and anthropogenic concentrates ofoil or hazardous material.
Construction Methods
The work shall be in accordance with MassDOT Standard Specifications and the Department Of Environmental Protection Combined PermiV40l Water Quality Certification Combined Permit For Dredging.
Once construction progresses and the armor is removed the Contractor is responsible for collecting two additional samples and analyze in accordance with 314 CRM 9.07. Upon completion of the sediment analysis, a sediment management plan shall be submitted to MassDEP for review and approval. The excavated sediment shall be dewatered on site. The Contractor must submit a dewatering plan prior to construction for review by MassDEP.
The Contractor shall handle and dispose ofthe dredged material ofproperly in a licensed facility accepting dredged material. Documentation of the facility must be provided to MassDEP no dredged material shall be transported to any facility without concurrence of MassDEP. A dredged material tracking form or material shipping record shall be used to track the dredged material to the licensed upland facility a fully executed copy of the forms shall be provided to MassDEP within 30 days offinal shipment to the reuse location or facility.
The Contractor shall implement best management practices during transportation ofthe dredged material to the licensed receiving facility. At a minimum the transporting upon public roadways of all dredged material shall have no flee liquid as determined by the paint filter test or other suitable methodology acceptable to MassDEP. A toppling or other material shall be used to cover the dredged material during transport within 30 days of completion ofdredging photographs ofthe affected areas depicting post-dredged conditions shall be taken and submitted to Derek Standish of MassDEP Boston office-
Method of Measurement
The method ofmeasurement shall be per Cubic Yard as stipulated under Subsection 140.80 ofthe Standard Specifi cations.
Parker's River Bridge Replacement
O .ldd"ndr. No. 5, July 24, 2019
Town of Yarmouth Parfter's River Bridge Replacement
Payment
Payment for work under this Item will be made at the Contract Unit Price per Cubic Yard of all materials as designated under Subsection 140.61 of the Standard Specifications for Item 143
Chanel Excavation and as specified in this special provision.
Payment shall include full compensation for all testing dewatering transportation and disposal as well as, labor, materials, equipment and incidental costs required to complete the work.
To\ln ofYarmouth Parker's River Bridge Rcplaccmcnt
O Add"rdr- No. 5, July 24, 2019
SPECIAL PRO\'ISIONS
YARMOUTH
Bridge Replacement, Bridge No. Y-01-002 (Concrete) Route 28 (Main Street) over Parkers River
Labor participation soals for this proiect shall be X% for minorities and X% for women for each iob category. The goals are apolicable to both contractor's and subcontractor's on-site construction workforce. Refer to document 00820 for details.
Definitions Used in These Special Provisions
The "Municipality" and the "Town" shall mean the Town of Yarmouth, the municipality in which the Contract work is to be performed.
"MassDOT", "Department", "Massachusetts Highway Department" and "MassHighway" shall mean the Massachusetts Department of Transportation - Highway Division.
"Engineer" shall mean the authorized representative ofthe Town of Yarmouth.
"Standard Specification" shall be MassDOT Standard Specification.
SCOPEOFWORK
OAll *ork under this contract shall be done in conformance with the Massachusetts Highway Department Standard Specifications for Highways and Bridges dated 1988, the Supplemental Specifications dated April l, 2019; the 2017 Construction Standard Details, lhe 1990 Standard Drawings for Signs and Supports;the 1996 Construction and Traflic Standard Details (as relates to the Pavement Markings details only); the 2009 Manual on Unifurm Trafic Control Devices (MUTCD) wilh Massachusetts Amendments and the Standard Municipal Trafiic Code; the 1968 Standard Drawings for Trafic Signals and Higlrway Lightingi the latest edition of American Standard for Nursery Stock;
the Plans and these Special Provisions.
The work under this Contract consists ofthe bridge replacement ofthe Route 28 (Main Street) Bridge (MassDOT Bridge No. Y-01-002) over Parkers River in the Town of Yarmouth. The work includes the complete bridge replacement, as well as, modifications to the riprap channel in the area of the bridge. The new superstructure will comprise a single-span butted-precast deck beams with a 6" cast-in-place concrete deck and asphalt wearing surface. The structure shall remain open to one lane of traffic in each direction at all times during construction in accordance with the Temporary Traffic Control Plans.
SP-I
Town of Yarmouth Parker's River Bridge Replacement
O lddendum xo. 5, J\ty 24,2oty shall conform to provisions found in the Access Permit
WORKSCHEDULE
Owork hours and days on this Project Document.
OWitn the exception of paving operations the work on this project shall be a normal 8-hour day, 5-day week, from 7:00 AM to 3:30 PM, with the Prime Contractor and all Subcontractors working on the same shift. Without prior approval by the District 5 Construction Engineer, no work shall be done on this Contract on Saturdays, Sundays or legal holidays, on a day before and/or a day after a long weekend involving a legal holiday, including the July 4th and Thanksgiving Holidays. No work that requires a lane closure shall be allowed during the day time work hour restrictions for peak hour traffic which are from 6:00 AM to 9:00 AM and 3:00 PM to 6:00 PM. No construction from Memorial Day weekend through Labor Day, except the Town and District Highway Director may consider approving a request from the Contractor to work between Memorial Day and June l5th as long as the proposed work activities are determined by the Town and District Highway Director to not impact traffic and are of minimal impact to the abutting business owners.
The Contractor shall notifu the District 5 Highway Director at least two (2) weeks in advance ofany anticipated night time work to be performed during a night time window, or any short-term temporary roadway closures necessary for the work. All detour traffic control requirements must be in place and approved by the Engineer a minimum of two days in advance ofthe closure. The Contractor shall begin work on those portions of roadway so designated only after proper placement of necessary waming devices for the segment ofroadway. The road shall remain open to trafTic until all signs for the detour are in place. The Contractor is directed to the MassDOT access permit document for further construction schedule limitation. Any modifications to these proposed work hours are subject to the written approval of the District Highway Director and the Town of Yarmouth.
Winter restriction: paving, grading/seeding activities work are restricted for winter season. The Contractor shall submit concrete placement heating and containment plan to the Engineer for approval for any cast in place concrete construction activities.
Utilitv Services: During construction, all utilities to properties abutting the project shall be maintained during their business hours and a minimum oftwo (2) hours prior to opening. Notification of any service disruptions shall be provided to the Town of Yarmouth and directly to the property owners a minimum of48 hours in advance ofany planned outages. Hydrants shall remain in service during construction.
Access: Vehicular access through a minimum of one curb cut shall be maintained at all times to abutting properties when abutting businesses are open. Curb cut access through both curb cuts to 6791681 Route 28 (Lobster Boat Restaurant) shall be maintained during their business hours for the Memorial Day Weekend (Noon on Friday through Memorial Day) and from June l5th through Labor Day.
Temporarv Easements: Temporary Easement areas located outside the Work Zones identified on the Temporary Traffic Control Plans shall not be used for staging, equipment storage or material storage.
Temporary Easement areas shall be kept free from accumulation of waste materials, debris or rubbish.
SP-3
Toun oI Yarmouth Parker's River Bridge Replacement
All temporary easement areas shall be restored to their original condition, or better, upon completion ofthe project.
MASSHIGHWAY TO MASSDOT NAME CHANGE
The following definitions in Section 100 ofthe Standard Specifications for Highways and Bridges are revised as follows:
(Amend definition of Department)
1.17 -Department .....Effective November l, 2009, St. 2009, c.25 abolishes the Massachusetts
Department of Highways and all assets, liabilities, and obligations become those of the Massachusetts Department of Transportation ("MassDOT).
Anlrvhere in this contract the terms Commission, Commonwealth, Department of Public Works, Department, Massachusetts Highway Department, MassHighway, Party ofthe First Part, or any other term intending to mean the former Massachusetts Department of Highways is used, it shall be interpreted to mean MassDOT or applicable employee of MassDOT unless the context clearly requires otherwise. Furthermore, MassDOT by operation of law inherited all rights and obligations pursuant to any contract, and therefore parties to this contract hereby acknowledge and agree that its terms shall be liberally construed and interpreted to maintain the rights and obligations of MassDOT. Furthermore, the parties hereby acknowledge and agree that the transfer of all rights and obligations from the Massachusetts Depa(ment of Highways to MassDOT shall not have the effect of altering or eliminating any provision of this contract in a manner that inures to the detriment of MassDOT.
(Add a definition for MassDOT) I .46 - MassDOT........ The Massachusetts Department of Transportation, a body politic and corporate, under St. 2009, c.25 "An Act Modemizing the Transportation Systems of the Commonwealth", as amended.
ENGINEERING DIRECTIVES
Contractors can access MassDOT, Highway Division Engineering Directives at:
http://www.mass. qov/massdot/hishway Select Doing business with us Select Design/Engineering Select Engineering & Policy Directives Select Engineering Directives
PERSONAL PROTECTTVE SAFETY EOTIIPMENT FOR CONTRACTOR PERSONNEL
The Contractor is responsible to ensure that all personnel, including all subcontractors, working on the project are issued and are wearing all necessary personal protective safety equipment while working within the project limits. This equipment shall include, as a minimum, a hardhat and a safety vest, SP.4
Town ofYarmouth Parker's River Bridge Replacement regardless ofthe type of work being performed. Other safety equipment shall be added as required to perform the work in which they are engaged and in accordance with all local, state and federal requirements in effect. Safety equipment shall be provided at no additional cost to the Department.
CONTRACTOWSUBCONTRACTOR CERTIFICATION - CONTRACT
COMPLIANCE (Revision 03-23- I 0)
Pursuantto23C.F.R.$633.101 et seq., the Federal Highway Administration requires each contractor to "insert in each subcontract, except as excluded by law or regulation, the required contract provisions contained in Form FHWA-1273 and further requires their inclusion in any lower tier subcontract that may in turn be made. The required contract provisions of Form FHWA-I273 shall not be incorporated by reference in any case. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the requirements contained in the provisions of Form FHWA-1273." The prime contractor shall therefore comply with the reporting and certification requirements provided in MassDOT's CONTRACTOR/SUBCONTRACTOR CERTIFICATION Form (DOT-DIST-192) certifying compliance with 23 C.F.R. $ 633.101 for each subcontract agreement entered into by the contractor. The contractor shall provide a fu[y executed original copy of said CONTRACTOR/SUBCONTRACTOR CERTIFICATION Form to MassDOT upon execution ofany subcontract agreement. Failure to comply with the reporting and certification requirement of the CONTRACTOPJSUBCONTRACTOR CERTIFICATION Form may result in action against the prequalification status ofthe prime contractor with MassDOT.
SUBSECTION 4.04 CHANGED CONDITIONS.
This Subsection is revised by deleting the two sequential paragraphs near the end that begin "The Contractor shall be estopped..." and "Any unit item price determined ..." (116/2006).
PROTECTION OF UNDERGROUND FACILITIES
The Contractor's attention is directed to the necessity ofmaking his own investigation in order to assure that no damage to existing structures, drainage lines, traffic signal conduits, etcetera, will occur.
The Contractor shall notifo Massachusetts DIG SAFE and procure a Dig Safe Number for each location prior to disturbing existing ground in any way. The telephone number of the Dig Safe Call Center is l - 888-344-7233.
DISPOSAL OF EXCESS MATERIAL
Surplus materials obtained from any type ofexcavation, and all existing and other materials not required to be removed and stacked or needed for use on the project, as determined by the Engineer, shall become the property of the Contractor and disposed of subject to the regulations and requirements of local authorities goveming the disposal ofsuch materials, at no additional compensation.
SP.5
'lb\m of Yarmouth Parker's fuver Bridge Replacement
O nodendr. No. 5, July 24, 2019
MATERIAL REMOVE,D AND STACKED
All materials owned by the municipality and noted on the Contract documents to be removed and stacked shall be carefully removed, transported and stacked (on boards) at the discretion ofthe Town of Yarmouth Department of Public Works (DPW) Director to the DPW yard during normal business hours. The Town of Yarmouth specifically requests that the granite blocks comprising the existing abutments be removed and transported to the DPW Garage at 507 Buck lsland Road, and stacked in a |ocation on site to be determined by the Town.
The Contractor shall be held responsible for any damage to the materials to be stacked before final removal. The Contractor's responsibility shall cease upon final acceptance of the work or 60 days from the time a certified notice (with a copy sent to the Engineer) is sent to the owner ofthe material advising him that it is available for removal. Ifthe Engineer or the Town determines that any part of the stacked material is unsuitable for reuse, said materials shall become the property ofthe Contractor, and the Contractor shall dispose ofthem away flom the site.
No separate payment -with exception ofthe Existing Abutment Granite Block Removed and Stacked-will be made for material removed and stacked, but all costs in connection therewith shall be included in the prices bid for various Contract items. Existing Abutment Granite Block Removed and Stacked will be paid for under ltem 712.12 - Granite Blocks Removed and Stacked.
ENVIROI\IMENTAL PROTECTION
The Contractor shall operate only in those areas approved by the Engineer and shall provide protective measures called for in various Contract Items or at the direction of the Engineer. All protective measures shall be maintained by the Contractor until removal is approved by the Engineer or at the end ofthe Project.
The Contractor shall maintain all construction and storage areas free ofdebris and trash.
The Contractor shall be responsible for restoration of disturbed areas as provided for in the various items. Any damage to areas not approved by the Engineer shall be restored at the Contractor expense.
Should the Contractor fail to make the necessary repairs, the Town may make such repairs and charge them against the Contractor.
Daily maintenance and fueling ofequipment shall be conducted away fiom all wetland areas.
The Contractor shall have sufficient materials on hand to control and clean up any spillage. In the event ofan accidental spillage within any wetland area, the Contractor shall take immediate action to prevent contamination of wetland areas, and he shall cease operations and notiry the Engineer. The cost ofcleanup ofany contamination shall be the responsibility ofthe Contractor.
Maintenance and repair other than daily requirement shall be done off-site at the Contractor's own facility or service yard.
From time to time the site may be visited or inspected by Local, State or Federal agencies responsible for protection ofthe environment. The Contractor shall cooperate with the representatives and shall not hinder or impede their work. All protective measures shall be paid for in the costs ofthe various items.
SP.6
OAddendum No. 5, July 24,2019
O ***THIS PAGE INTENTIONALLY LEFT BLANK'**T
SP.9
Toun of Yarmoulh Parker's River Bridge Replacement
@Addendum No. 5, July 24, 2019
EXISTING BORING INT'ORMATION PROVIDED (Supplementing Subsection 2.03)
The borings as indicated on the Plans were taken for the purpose ofdesign ofthe bridge foundations.
They do not necessarily show the actual nature of the material that may be encountered in the excavation. Material encountered in the excavation may include various materials such as rock fill, and may also include various other materials liom previous constructions. The Contractor shall make his/her own investigations to ascertain the presence ofthe utilities and former constructions. The bid by the Contractor will be considered as a mutual agreement that the removal and disposal ofall the materials encountered in the excavation and in the excavating for walls and bridge structures, regardless of their nature or size (except for materials defined as Class B Rock Excavation) will be considered as included under the general items for excavation, and that there shall be no addition to the Contract Unit Price for the item regardless if the operation is more difficult or more costly than is implied by the preliminary information.
PUBLIC SAFETY AND COIWENIENCE (Supplementing Subsection 7.09)
The Contractor shall provide, in accordance with the Contract Plans, all traffic barriers, signs and other specified traffic control devices needed to provide the necessary traffic management in the vicinity ofthe construction site as indicated on the Plans. No construction activities shall begin until all traffic control devices, signs and baniers have been provided and approved by the Engineer.
Construction work on the project.shall not commence until the construction signing and traffic barriers as described in the Contract Drawings have been installed and approved by the Engineer.
Particular care shall be taken to establish and maintain such methods and procedures that will not create hazards of an unusual nature. Miscellaneous construction activities needing temporary lane closures for access to the construction shall be done at the approval of the Engineer. Travel lane closures shall be allowed based solely on the discretion of the Engineer and with the presence of police detail officers as scheduled by the Contractor.
Access to abutting properties shall be maintained in a reasonable and safe manner for the duration of the construction period.
OThe Contractor shall maintain the temporary walkways and the temporary bridge during the entire duration ofthe contract. The Contractor shall provide snow removal for these areas and maintain an accessible path through the construction area.
The Contractor shall carry on his,4rer work concurrently and in conjunction with the Utility Companies involved with the project so as to provide for all possible cooperation towards the satisfactory completion of the work with minimal delay and inconvenience to the utility owners and the general public.
The Contractor shall order all materials and services required for the work immediately after the execution ofthe Contract. The Contractor shall not start any operation until all materials required for the operation are at the site or until the Engineer is satisfied that the materials will be delivered in such order that there will be no interruption to continuous and efficient progress.
SP- I7
Town of Yarmou0r Parker's River Bridge Replacement
@,tddendum No. 5, July 24,2019
NOTICE TO OWNERS OF UTILITIES
Written notice shall be given by the Contractor to all public service corporations or olTicials owning or having charge ofpublic or private utilities, ofhis/her intention to commence operations affecting such utilities at least one week in advance ofthe start of such operations. The Contractor shall at the same time file a copy of said notice with the Engineer.
Following are the n,rmes and addresses of the companies or agencies that may be affected, but the completeness ofthe list is not guaranteed:
Yarmouth DPW Director Yarmouth Dept. of Public Works (Water) Attn: JeffColby Attn: Gary Damiecki 99 Buck Island Road 99 Buck lsland Road West Yarmouth, MA 02673 West Yarmouth, MA 02673 Telephone: 508-398-2231 Telephone: 508-771-7921
@ Eversource Electric National Grid (Gas) Attn: Kelly-Ann Correia Attn: Mellissa Owens, Richard Logue 247 Station Drive, NWBED 180 40 Sylvan Road,3'd Floor- W3.244 Westwood, MA 02090 Waltham, MA 02451 Telephone:508-305-7163 Telephone:781-907-2845,781-907-3155 kellv-ann.correia@eversource.com Mellissa.owens@nationalgrid.com
@Verizon Open Cape Attn: Peter Decosta Aftn: Garry Fanenkopf 85 High Street PO Box 1148 Pawtuckett, zu 02860 Bamstable, MA 02630-2148 Telephone: 508-944-6701
Comcast Cape Net LLC Attn: Wendy Brown Attn: Shannon Silvas 676 Island Pond Rd, Manchester, NH 03109 1900 West Park drive, Suite 280 Telephone: 603-541-1082 Westborough, MA 0l 581 Wendv Brown@comcast.com Telephone: 508-774-5080
MassDOT - District 5 Utilities Yarmouth DPW-Engineering Attn: Richard Bilski Aftn: Nick Aguiar Telephone: 508-884-4394 I 146 Rte. 28 (town hall) Richard.Bilski@state.ma.us South Yarmouth, MA 02664 Telephone:508-398-2231Ext.1250 YarmouthPoliceDepartment
Kevin Lennon Additional Contact Information: Telephone 508-299-3175 Kal Boghdan klennon@yarmouth.ma.us Yarmouth Police Department Telephone 508-509-91 7l
SP-I8
Toun of Yarmouth Parker's River Bridge Replacement
OAddendum No.5, Jli,ly 24,2019 No separate payment will be made for the cost ofconnecting existing pipes to new structures, but all costs in connection therewith shall be included in the unit price bid for various structure items. Ifnew pipe or pipe section are required to extend the existing line to and through the new structural wall, the new pipe will be paid for under the unit price per foot established under that item.
INSTALLATION OF DRAINAGE SYSTEMS
Where indicated on the Plans or as directed by the Engineer, existing pipe inverts shall be utilized as reference to establish proposed slope for the proposed pipe. The Contractor shall verify existing elevations.
New inverts for proposed catch basins and manholes shall be submitted to the Engineer for approval before installation.
The Contractor also may have to perform field investigation to confirm the configuration of the existing drainage system. The Engineer must approve the methods used to verify the drainage on the Plans. These methods may include, but are not limited to, smoke and/or dye testing, test pits or another form of testing approved by the Engineer. Test pits shall be paid for under Item l4l.l. Smoke or dye tests shall be considered as incidental to the various drainage ltems. The Contractor shall not order any drainage materials (pipe, manholes, catch basins, etc.) until his/her investigation has been completed.
PROJECT IDENTIFICATION AND SIGNS
The Contractor shall provide one project sign as specified herein. Project sign shall be approximately 4 feet by 8 feet in size, mounted on two posts set in the ground where directed. The sign shall be constructed of3-inch painted waterproof plywood for which the wording and colors will be determined by the Town of Yarmouth.
Where and as approved by the Town of Yarmouth, the Contractor shall erect and maintain the sign identiling the Project and indicating participation ofthe multiple sources ofproject funding:
The sign shall be erected at the project site where and as directed by the Engineer for maximum public identification ofthe work and shall be maintained in good condition until completion ofthe project. Upon completion, the sign shall be removed.
The sign shall be cut from standard 4 ft. by 8 ft. waterproof plyrvood sheets, or other suitable material. The size may be varied to meet special requirements, but proportions shall be maintained.
Display Panel . Construction, dimensions, colors and lettering shall be per Town of
Yarmouth requirements . Verbiage: The Town of Yarmouth shall fumish the text, photograph, and other graphics, and the Contractor shall fumish design and layout, and printing which are all subject to the approval ofthe Engineer prior to installation in the display panel. Installation offinal, approved product in the display panels shall be made by the Contractor.
SP.2O
To$n ofYarmouth Parker's River Bridge Replacement
No separate measurement nor payment will be made for work required under this Section. All costs in connection therewith shall be considered incidental to the item or items ofwork to which they pertain.
ITEM IOI. CLEARING AND GRUBBING ACRE
(Note: Paid for under Item 799. Landscaping)
Descriotion Except as indicated below and on the plans, all work shall be in accordance with the pertinent requirements of Standard Specifications Section l0l, Clearing and Grubbing.
Before any clearing is done, the Contractor shall arrange a conference on the site with the Engineer to identifo trees and shrubs which are to be protected or removed. Do no clearing without clear understanding ofexisting conditions to be preserved. All areas to receive landscaping as indicated on the landscaping plans and or areas to receive loam and seed shall be cleared and grubbed.
The Contractor shall be responsible for the protection of all existing trees and plants designated to remain for the length of the construction period, including liability for all damages as specified herein. The placement ofprotection devices, however, is at the Contractor's discretion.
The Contractor shall be liable for all damage and/or disturbance to existing trees and shrubs not otherwise designated for removal. Actual charges for damage to plants shall be in accordance with the schedules defined herein, with assessed charges to be deducted from sums payable under the Construction Contract.
l. Damage which, in the Engineer's opinion, can be remedied by corrective maintenance shall be repaired immediately.
Trees or shrubs which are damaged ineparably shall, at the Engineer's discretion, be replaced by the Contractor with new trees or shrubs ofthe same size and type.
Damaged trees or shrubs which require removal and/or replacement shall be removed according to the Specification requirements for removals, including refilling and repair of ground surface, with such costs to be bome by the Contractor in addition to assessed charges described herein.
Construction Methods The Contractor shall remove all trees, stumps, cuttings, and debris as designated on the plans. If wood chip mulch is generated in the clearing and grubbing process, it shall be removed from the site
Excavated area left after stump removal shall be backfilled with ITEM 751 Loam Borrow.
Measuremeni and Payment Work under ITEM 101. CLEARING AND GRUBBING shall be measured and paid for at the accepted quantities ofLandscaping (Item 799.) and will not be paid separately but will be paid for at the Lump Sum contract unit price for Landscaping for the particular work involved, as defined herein and in the Standard Specifications.
2.
-r.
SP.2I
To$n ofYarmouth Parker's River Bridge Replacement
O aodenouln No. 5, July 24, 2019 o
ITEM 156.13 CRUSHED STONE FOR INTEGRAL ABUTMENT PILES TON
The work under this item shall conform to the relevant provisions ofSection 150 and the following:
Crushed Stone for Integral Abutments for this project shall conform to M2.01.6.
Crushed Stone for Integral Abutments shall be plaoed after piles are installed, concreted in place, and holes backfilled with sand borrow. Crushed Stone for Integral Abutments shall be placed in a 3'-0" deep x 2'-6" wide trench with the top ofthe trench at the elevation ofthe bottom ofthe abutment.
Measurement and payment
Item 156.13 shall be measured for payment by the Ton, measured in place, placed beneath the proposed integral abutment in accordance with the details on the Plans.
Item I56.13 shall be paid by the Ton, which price shall include all labor, materials, equipment, and incidental costs required to complete the work.
SP-25
Tou,n of Yarmouth
ITEM I84.I
Parker's fuver Bridge Replacement
@Addendum No. 5, July 24,2019
DISPOSAL OF TREATED WOOD PRODUCTS TON
O Work under this item shall include the removal and disposal of all treated existing wood product as directed by the Engineer.
O The timber piles on the site are expected to be treated with creosote, pentachlorophenol and/or CCA. This item shall include all costs for sampling, laboratory testing, loading, transportation and disposal ofthe treated wood. The Contractor is required to submit disposal manifests to the Engineer prior to the completion ofthe project. All aspects ofthis Item shall be completed in accordance with state and federal regulations.
@ Measurement and payment shall be by the weight, in tons, of treated timber removed from the structure and subsequently accepted at a licensed facility. The work shall be considered full compensation for all labor, tools, equipment, materials, testing, loading, transportation, approvals, and permits necessary for the completion ofthe disposal ofthe treated wood.
SP-27
Town ofYarmouth Parker's River Bridge Replacement
@Addendum No . 5, JUlly 24,2o19
ITEM 813.80
Description
SERVICE CONNECTION (OVERHEAD)
The work under this Item shall conform to the relevant provisions ofSection 813 ofthe Standard Specifications and the following:
The work shall include the furnishing and installation ofEversource Approved Handhole (Polymer Concrete) for the service connection as shown on the plans and as directed. The Eversource Approved Handhole in accordance with specification ofthe manufacturers shall be submitted for the Engineer's approval before ordering and installation. The work shall include the ground rod, l0 feet long, as shown on the plans. The work will also include the necessary conduit sweeps for connection to the conduit installed under ltem 808.3.
@The work shall include but is not limited to:
Install the standard size handhole at the base ofthe riser pole Install 3 inch RGS pipe for l0 feet riser pipe, install weatherhead Instalt 4X6 CU UG wire from NEMA 3R circuit breaker enclosure to the handhole, with 3 foot loop at handhole.
Install 3x6 CU UG wire from riser pipe to NEMA 3R circuit breaker enclosure, with 20 feet coil at riser pipe.
Install meter socket on the riser pole at an elevation between 3 and 6 feet above finish grade
Eversource is to install and attach a new 100 A UG service Eversource is to make a permanent connection at the pole and handhold Eversource is to install the meter
Construction Methods The Service Connection (overhead) shall be constructed at the location indicated on the Plans and in accordance with the details on the Plans.
Measurement and Payment The accepted quantities for Service Connection (overhead) will not be paid separately but will be paid for at the Lump Sum contract unit price for Service Connection (overhead) (Item 813.8) for the particular work involved, including all labor, materials, grounding, flexiblejoint filler, and equipment and incidental costs required for the work.
LUMP SUM
SP.82
Tolm ofYarmouth Parker's River Bridge Replacement
OAddendum No. 5, July 24,2019
DECORATIVE LED LUMINAIR.E sOWITEM 823.101
The work under this Item shall conform to the relevant provisions of Section 820 ofthe Standard Specifications for Highways and Bridges and the following:
Decorative LED Luminaire
Ofh" I-SO Luminaires to be supplied for this project shall be Marina Pendant type fixtures by Cyclone Lighting (Model CN12P1A-FGC-3MHS-50W-4K-120-PTL-BK-TX-MG) or approved equal, size as indicated on the plans, and shall be designed for operation on a 1201240 volt system.
Luminaries shall be installed on the decorative light poles as described in Item 821.101.
The lighting luminaries shall be installed at the locations indicated on the Contract, complete, wired, lamped and ready for operation.
OThe luminaries shall consist of a housing, flat clear glass (FGC) features cage without globe, lamp sockets, mounting devices, photocell, ballast components, and light source. Upon completion ofthe luminaries installation, the secondary wiring consisting of two (2) No.l0 AWG color-coded single conductors shall be connected to the luminaries line terminals and extended to the cable connector kits in the base ofthe pole shaft. Contractor shall coordinate with the Town and local electrical utility company for connecting streets lights to adjacent power source.
The optical design ofthe units shall be capable ofproducing a cutoff IES Type III light distribution in conformance with the current ANSVIES classification and shall meet the photometric requirements shown on the Plans.
Lamps failing during the first year after the final acceptance shall be considered defective and shall be replaced at no cost to the Town (Yarmouth).
The luminaires shall be set leveled and perpendicular to the road surface (or adjusted as directed by the Engineer) securely fastened, lamped, connected, cleaned and ready for operation.
The luminaires shall have the similar finish and finish color textured black or black.
Measurement and Payment Decorative LED Luminaire will be measured and paid for at the Contract unit price per each, which price shall be full compensation for all labor, materials, grounding, flexiblejoint filler, and equipment and incidental costs required for the work
SP-84
Tou.n of Yarmouth Parker's River Bridge Replacement
O lddenoum No. 5, July 24, 2019
ITEM 94I.I EXISTING TIMBER PILE REMOVAL FT
and 955 of theThe work under this Item shall conform to the relevant provisions of Sections 940 Standard Specifications and the following:
The purpose of this work is to avoid interference ofthe existing timber piles from the proposed piles construction. IfContractor's construction means and methods are such that the existing piles can be left in place without interference with the proposed piles installation, the existing piles can be left in place.
Contractor shall make his own investigation at site to determine the existing pile locations in relation to the proposed pile locations. The exact locations ofthe existing piles should be determined in the field.
O Contractor shall be careful in removing the existing piles so as not to cause disturbance or damage to the adjacent structures. Prior approval from the Engineer shall be obtained prior to the removal of existing piles. Consideration shall be given to relocation ofproposed piles to avoid interference with existing timber piles rather than having the existing timber piles removed.
@ It is anticipated that the existing timber piles were treated.
Method of Measurement
@ 'Existing Timber Pile Removal' shall be measured for payment per FT of existing timber piles removed.
Basis of Payment:
OPul-.rt for this Item shall be made at the Contract Unit Price per Foot of existing timber piles removed. The contract unit price shall be considered full compensation for all other materials, tools, equipment, labor and incidentals necessary to complete the work as specified on the Plans or as required by the Engineer.
Legally discarding the removed existing timber piles, transporting the removed timber piles from the site shall be paid under Item I 84.1 "Disposal ofTreated Wood Products". Measurement and payment ofthe disposal ofthe timber piles shall be by the weight, in TON, oftreated timber removed from the existing structure and subsequently accepted at a licensed facility. The work shall be considered full compensation for all labor, tools, equipment, materials, testing, loading, transportation, approvals, and permits necessary for the completion ofthe disposal ofthe treated wood.
SP.96
To$n ofYarmouth
Orcslr.stz.tzt
Parker's fuver Bridge Replacement
O edd"ndr. No. 5, Juty 24,2019
STEEL PILE HP 12X84 T"T
The work under this item shall conform to the relevant provisions ofSection 940, Driven Piles, ofthe MassDOT Standard Specifications, Supplemental Specifications, except as modified herein.
The piles shall conform to the requirements of AASHTO M270 Grade 50. No substitution of pile size shall be permitted.
Prior to any pile installation operations, the Contractor shall submit for review and approval ofthe Engineerl\4assDOT a schedule of the proposed methods and equipment for all installation procedures, including the driven required capacity initially based upon a WEAP analysis.
As depicted in the Geotechnical Report, a Static - Cyclic (Express) Load Test (ltem 948.31) and a Dynamic Load Test by Contractor (ltem948.4l) shall be performed on a sacrificial pile prior to ordering of production piles. As identified on the boring logs in the plans, the piles shall be driven through the loose Fine Sand layer to the required capacity initially based upon the results from the Static and PDA tests on the sacrificial pile. It is recommended that the Contractor provide extra pile length to account for any variations ofthe actual pile tip elevations in the field. Any differences in pile lengths are to be resolved during construction, under the supervision of the Engineer and/or MassDOT. The sacrificial pile shall be located at a minimum of5 feet but preferably not greater than l5 feet away from the nearest production pile. It is recommended that the sacrificial pile be located at the southwest comer ofthe bridge. Additional Dynamic Load Testing shall be conducted on 2 (two) production piles, one at each abutment. Per the Geotechnical Report, one Dynamic load test on a production pile shall be at the opposite end ofthe sacrificial pile, meaning that the tested production pile is located at the northeast comer ofthe abutment. It is also required to conduct 2 (two) Dynamic load tests on the temporary pedestrian bridge piles, one at each abutment. ln summary, a total of 5
(five) Dynamic Load tests are specified for this project.
Prior to pile driving, the top 30 feet ofthe pile shall be coated with Coal Tar Epoxy in accordance with the manufacturer's recommendation.
It is anticipated that pile splicing will be required. Ifthe lengths ofpiles require splices, the splicing shall conform to its applicable Standard Specification Subsection 960.66. No splices shall be permitted within the top 20 feet of any pile. Welds shall be inspected using ultrasonic testing in accordance with the Bride Welding Code, ANSI/AASHTO/AWS Dl.5 and all Interim Revisions published by AASHTO. Welds shall be considered to be in tension. The Contractor shall submit shop drawings with the type ofprequalified splice weld(s) and procedures that would be used ifrequired.
The Contractor's attention is directed to the required sequence of installing the foundation piles for each portion ofthe integral abutment being constructed to a depth as shown on the plans and filling the hench with Crushed Stone under Item 156.13.