Addendum 4 Parkers River Bridge.pdf
PDF 561 KB Posted
- Attached to
- Parkers River Bridge
- Solicitation number
- BD-19-1355-TYARM-YADPW-40968
- Issued by
- Barnstable County, Massachusetts
About this file
This document is Addendum No. 4 to the Invitation for Bid (IFB) issued by the Town of Yarmouth Department of Public Works for the Parkers River Bridge Complete Replacement and Widening project. The addendum revises several key dates, including the bid opening, which is now scheduled for July 31, 2019, and the deadline for written questions, which is now July 25, 2019. The addendum also reduces the number of days prior to the bid opening that addenda can be issued, from 7 days to 5 days. Additionally, the addendum removes sections regarding suspension of work and termination, as the payment conditions are covered in the Yarmouth contract which is part of the bid documents.
The Parkers River Bridge project is located in the state of Massachusetts. The project involves the complete replacement and widening of the Parkers River Bridge. Bidders are required to submit their proposals by the July 31, 2019 deadline. No further details are provided regarding pricing, set-asides, incumbents, funding, or other salient information.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO.4
Town of Yarmouth Department of Public Works 99 Buck Island Road West Yarmouth, MA 02673
DATE ISSUED: I:uJy 17,2019 TO: All Respondents of Record SUBJECT: Invitation For Bid:
Parkers River Bridge Complete Replacement and Widening
ADDENDUM NO. 4
l. Invitation to Bid (00020)/Introduction to Invitation for Bids (1.0). Page 1.1, First Paragraph, DELETE 'on Jiuly 24,2019.' And REPLACE with the following 'on July 3I , 2019' . Bid opening is now July 3 I , 2019 .
2. Invitation to Bid (00020)Antroduction to Invitation for Bids (1.0). Page 3,2.
SUMMARY OF INFORMATION AND CALENDAR, DELETE information in 'Deadline for Written Questions' 'on July 14,2019.' under DATE column and REPLACE with the following'on July 25,2019'. Written questions will allowed until July 25thby 4:00 p.m.
3. Invitation to Bid (O0020)Antroduction to Invitation for Bids (1.0). Page 3,2.
SUMMARY OF INFORMATION AND CALENDAR, DELETE information in 'Addenda' 'up to 7 days prior.' under DATE column and REPLACE with the following'up to 5 days prior'.
4. Invitation to Bid (00020)/Introduction to Invitation for Bids (1.0). Page 3,2.
SUMMARY OF INFORMATION AND CALENDAR, DELETE information in 'When and Where Bids are Due. ..' 'July 24,2019' under DATE column and REPLACE with the following 'July 3 1 ,2019' .Bid opening is now July 3 1,2019.
5. Instruction to Bidders (00100) Page 5, Article 7 7.1, DELETE 'Tuesday, July 16,2019' and REPLACE with the following 'Thursday, }uly 25'.
6. General and Supplementary Conditions: Please delete all of # 16.04 A and B under Article l6- Suspension of Work and Termination on page 63. Payment conditions are covered in the Yarmouth contract which is part of the bid documents.
Please sign below as receipt of ADDENDUM NO. 4 and include this page with your submission.
We have received and acknowledge ADDENDUM NO. 4 as part of IFB- Parkers River Bridge Complete Replacement and Widening
Company Name:
Addendum #4Pagel