STLI 201065 – Pre-Bid Comments/Clarifications
1. There is no “Call before You Dig” service for Liberty Island. The contractor shall utilize a private utility locating company.
2. The Sallyport access path from the Monument is the emergency egress route and access must be maintained at all times.
3. The contractor is required to protect the public at all times. The contractor may utilize the existing metal crowd control barriers for staging of the fence work. More substantial barriers will be required for activities that are potentially harmful to the public.
4. The contractor is required to protect the existing grounds. The contractor will be required to replace sod, as necessary, upon completion of the work.
5. The contractor will be required to provide portable toilets for workers.
6. The contractor may utilize the early staff boat (approximately 6:45pm) from Ellis Island for worker access to Liberty Island. Contractor’s workers will be required to carpool to Ellis Island due to limited parking.
7. A known company for landing barge is Miller’s Launch.
8. United States Park Police (USPP) will be performing K-9 screenings for all deliveries.
All costs associated with screenings shall be paid for by the Government.
9. Contractor will be required to provide temporary construction power. Noise levels need to be kept to a minimum during public hours. Coordination of public hours generator use will be required.
10. Construction trailer may be located in the back of house area by the landing beach.
Location to be coordinated with NPS.
11. The contractor will be required to coordinate with other contractors who will be working on Liberty Island during this project.
12. The contractor will be required to maintain 50% access for all areas at all times. This includes main walkways, paths and building access routes.
13. The contractor shall provide six (48” high x 36” wide) project information signs and install at a location to be determined by the Government. The price of the work shall be included in the Install Fencing at Fort Wood, and Site Preparation (Approach Mall/Flag Plaza and Main Mall and Tree Panels) bid items. Please see the attached document describing the requirements.
14. Contractors are encouraged to propose alternate working schedules that may be beneficial to the project provided they are described in detail in the Project Approach and Project Schedule technical evaluation factors.
STLI 201065 – Modification to Contract Documents
1. Sheet C2 Replacement (Approach Mall/Flag Plaza – Construction Staging and Staging Plan) – Replace Sheet C2 with attached updated sheet that indicates the new staging area.
2.A
Option 2.A | Projects ≥ $1M < $10M 48" x 48" Sign - Text Only
Notes:
Download sign logos from:
http://www.nps.gov/dsc/ workflows/upload/ NPS-SignLogos.zip
See framing and foundation details on drawings 2.C, 2.D, and 4.0.
DRAWING NUMBER
National Park Service U.S. Department of the Interior UniGuide Sign Program
Design and Construction of a New Visitor Center
World War II Valor in the Pacific National Monument Recovery Act Program | National Park Service
Your Recovery Dollars at Work U.S. Department of the Interior
WWW.RECOVERY.GOV
Visitor Information Recovery Sign, 48" x 48"
Visitor Information Recovery Sign, 48" x 48"
This is a general information style panel that is post mounted.
4' - 0"
3' - 0"
4' - 0"
4 x 4 Wood Post Painted Matthews Paint, Modeling Clay MP10277
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Fusce iaculis auctor sapien. Nam bibendum. Morbi ornare ante at neque. Phasellus cursus. Nulla pulvinar, enim eu volutpat venenatis, magna mauris lobortis libero, quis hendrerit diam erat nec enim.
Morbi lacus orci, semper a, sagittis egestas, interdum ac, est. Proin facilisis enim et lacus.
Pellentesque habitant morbi tristique senectus et netus et malesuada fames ac turpis egestas. Fusce nunc. Proin vel metus. Nullam vel quam vel tellus aliquet semper.
Design and Construction of a New Visitor Center
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Fusce iaculis auctor sapien. Nam bibendum. Morbi ornare ante at neque. Phasellus cursus. Nulla pulvinar, enim eu volutpat venenatis, magna mauris lobortis libero, quis hendrerit diam erat nec enim.
Morbi lacus orci, semper a, sagittis egestas, interdum ac, est. Proin facilisis enim et lacus.
Pellentesque habitant morbi tristique senectus et netus et malesuada fames ac turpis egestas. Fusce nunc. Proin vel metus. Nullam vel quam vel tellus aliquet semper.
World War II Valor in the Pacific National Monument Recovery Act Program | National Park Service
Your Recovery Dollars at Work U.S. Department of the Interior
WWW.RECOVERY.GOV
10" Blue Header (C 92, M76, Y37, K 25)
6"
Agency Logo and Park/Site or Facility Name
5"
PMS Warm Grey 2 (C 6, M7, Y9, K 11)
2" Blue Footer (C 92, M76, Y37, K 25)
Recovery Tagline 136 pt Frutiger LT Std 75 Black
Website 64 pt Frutiger LT Std 75 Black
Park Name 112 pt NPS Rawlinson OT Book
Program 64 pt Frutiger LT Std 75 Black
Project Name 256 pt NPS Rawlinson OT Bold
Project Description 80 pt NPS Rawlinson OT Bold
Font sizes are given at Full Size
Painted Exterior Grade 1/2" MDO or Plywood Panel Backer. Panel Back Painted Matthews Paint, Modeling Clay MP10277. Graphic is an Exterior Grade Digital Print on Adhesive Vinyl.
Project Information Sign - 48" high x 36" wide
4'-0"
Project Information Sign - 48" high x 36" wide
36"
48" High by 36" Wide Project Information Sign - Graphic to be Provided by Government upon Contract Award
3'-0"
2'-0"
2.C
Notes:
Include this drawing with either Option 2.A or Option 2.B.
DRAWING NUMBER
National Park Service U.S. Department of the Interior UniGuide Sign Program
4 x 4 Wood Post Painted Matthews Paint, Modeling Clay MP10277
2 x 4 Panel Frame Painted Matthews Paint, Modeling Clay MP10277
No.8 – #2 Drive x 3" Long Phillips Head, Deckboard Countersunk Head Wood
Screw
VIS Panel 48" x 48" - Sign Frame Assembly
36" 48"
48"
4.0
4.0
Project Information Sign - 48" high x 36" wide
48"
24"
36"
Additional may be required
2.D
Include this drawing with either Option 2.A or Option 2.B.
DRAWING NUMBER
National Park Service U.S. Department of the Interior UniGuide Sign Program
Design and Constructio n of a New Visito r Center
Lorem ipsum dolor sit a met, c onsectetur adipiscing elit.
Fusce iaculis auctor sapien. N am bibendum. M orbi ornare ante at neque. Phasellus cursus. N ulla pulvinar, e nim eu volutpat venenatis, m agna mauris lobortis lib ero, quis hendrerit d iam erat nec enim.
Morbi la cus orci, semper a, sagittis egestas, in terdum ac, est. P roin facilisis enim et la cus.
Pellentesque habitant m orbi tr istique senectus et netus et m alesuada fames ac turpis egestas. Fusce nunc. Proin vel m etus. N ullam vel quam vel te llus aliquet semper.
World War II Valor in the Pacific
Natio nal M onument
Recovery Act P rogram | N atio nal Park Service
Your R ecovery Dolla rs at W ork
U.S. D epartm ent o f t he In terio r
WWW.RECOVERY.GOV
4 x 4 Wood Posts Painted Matthews Paint, Modeling Clay MP10277
2 x 4 Painted Panel Frame Painted Matthews Paint, Modeling Clay MP10277
1/2" MDO or Exterior Grade Plywood Panel, Panel Back Painted Matthews Paint, Modeling Clay MP10277
Digital Print on Adhesive Vinyl
No.8 – #2 Drive x 3" Long Phillips Head, Deckboard Countersunk Head Wood
Screws, 4 Per Side
Sign Frame Assembly Exploded Axonometric
Additonal may be required
4.0
Include this drawing with either Option 2.A, Option 2.B, or Option 3.0.
DRAWING NUMBER
National Park Service U.S. Department of the Interior UniGuide Sign Program
No.8 #2 Drive x 3" Long Phillips Head, Deckboard Countersunk Head Wood
Screw, 4-6 Per Side
4 x 4 Wood Post 2 x 4 Wood Frame
1/2" MDO or Plywood
Typical Frame/Post Connection Detail
Scale: 3" = 1' - 0"
Typical Direct Embedment Detail
Scale: 1 1/2" = 1' - 0"
Concrete Footer or Sakrete Mix
Backfill
Gravel Layer (For Drainage)
4 x 4 Post
12"
V ar ie s
6"
48"
Additonal may be required
30" Min
MKutch Polygon
MKutch Callout Staging Area - No Longer to be Used
MKutch Callout New Staging Area - To be separated with 6' high chain link fence with green privacy construction screen.
File details come from the government source that posted it. Updated .