YOSE_154910C-100__Final_CDs-Specifications_Part_1_of_3.pdf

PDF 5 MB Posted

Attached to
Correct Critical Safety Hazards & Rehab the Awahnee Hotel NHL
Solicitation number
P15PS00437
Issued by

About this file

Specifications - Part 1 of 3

View the file

Other files

File Type Posted
0023_of_0148_r1_(2).pdf PDF
DOC624.PDF PDF
YOSE_154910_PreProposal_PresentationAHWAHNEE_03172015.pptx PPTX presentation
Revised_Wage_Rates_4-24-15.doc DOC document
Geotechnical_Report.pdf PDF
AHWAHNEE_QUESTIONS2.doc DOC document
addtl_provision_and_clause.docx DOCX document
YOSE_154910C-100__Final_CDs-Specifications_Part_2_of_3.pdf PDF
Ahwahnee_HSR_1.2011_pgs_350-374.pdf PDF
YOSE_Proposal_Submission_Pkg1.pdf PDF
Ahwahnee_-_URS_seismic_report_2002_Part_1_of_3.pdf PDF
5_YOSE_154910C-FinalCDs-Pgs41-54_Drawings.pdf PDF
Ahwahnee_HSR_1.2011_Appendices_Vol_2_Part_3_of_5.pdf PDF
Ahwahnee_HSR_1.2011_Appendices_Vol_2_Part_4_of_5.pdf PDF
wage_rates_3-27-15.doc DOC document
Ahwahnee_HSR_1.2011_Appendices_Vol_2_Part_5_of_5.pdf PDF
SF-1442.YOSE.pdf PDF
Ahwahnee_CLR_3.2011_Part_2_of_3.pdf PDF
Ahwahnee_HSR_1.2011_pgs_205-240.pdf PDF
3_YOSE_154910C_FinalCDs _Pages21-30_Drawings.pdf PDF
Ahwahnee_-_URS_seismic_report_2002_Part_2_of_3.pdf PDF
YOSE_154910C-100__Final_CDs-Specifications_Part_3_of_3.pdf PDF
2_YOSE_154910C-FinalCDs-Pgs12-20_Drawings.pdf PDF
13_YOSE_154910C-FinalCDs-Pgs140-148_Drawings.pdf PDF
Ahwahnee_HSR_1.2011_Appendices_Vol_2_Part_2_of_5.pdf PDF
Ahwahnee_HSR_1.2011_pgs_175-204.pdf PDF
Ahwahnee_HSR_1.2011_pgs_241-264.pdf PDF
Ahwahnee_HSR_signature_page_1.2011.pdf PDF
Ahwahnee_CLR_3.2011_Part_3_of_3.pdf PDF
Ahwahnee_HSR_1.2011_pgs_116-134.pdf PDF
8_YOSE_154910C-Final_CDs-Pgs75-89_Drawings.pdf PDF
Ahwahnee_CLR_3.2011_Part_1_of_3.pdf PDF
12_YOSE_154910C-FinalCDs-Pgs130-139_Drawings.pdf PDF
Solicitation_clauses.docx DOCX document
Ahwahnee_HSR_1.2011_pgs_301-349.pdf PDF
1_YOSE_154910C-FinalCDs-Pgs1-11_Drawings.pdf PDF
Ahwahnee_-_URS_seismic_report_2002_Part_3_of_3.pdf PDF
Ahwahnee_HSR_1.2011_pgs_46-85.pdf PDF
Ahwahnee_HSR_1.2011_pgs_86-115.pdf PDF
Ahwahnee_HSR_1.2011_Appendices_Vol_2_Part_1_of_5.pdf PDF
Ahwahnee_HSR_1.2011_pgs_265-300.pdf PDF
Ahwahnee_Asbestos_Survey_1990.pdf PDF
Ahwahnee_HSR_1.2011_pgs_1-45.pdf PDF
10_YOSE_154910C-FinalCDs-Pgs112-120_Drawings.pdf PDF
9_YOSE_154910C-FinalCDs-Pgs90-111_Drawings.pdf PDF
6_YOSE_154910C-FinalCDs-Pgs55-65_Drawings.pdf PDF
11_YOSE_154910C-FinalCDs-Pgs121-129_Drawings.pdf PDF
Ahwahnee_HSR_1.2011_pgs_135-174.pdf PDF
7_YOSE_154910C-FinalCDs-Pgs66-74_Drawings.pdf PDF
4_YOSE_154910C-FinalCDs-Pgs31-40_Drawings.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

100% FINAL CONSTRUCTION DOCUMENTS

SPECIFICATIONS

CORRECT CRITICAL SAFETY HAZARDS AND

REHABILITATE THE AHWAHNEE HOTEL NHL

Yosemite National Park, California pr e par ed f o r

National Park Service / Yosemite National Park & Delaware North Companies Parks & Resorts at Yosemite, Inc.

pr e par ed by

Architectural Resources Group, Inc.

and Hornberger + Worstell

August 29, 2014

YOSE – 154910C TOC-1

TABLE OF CONTENTS

01 10 00 Contract Modification Procedures

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation for Historic Preservation Projects 01 33 23 Submittal Procedures 01 35 23 Safety Requirements 01 35 50 Natural, Cultural and Physical Resources Protection 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 References 01 50 00 Temporary Facilities and Controls 01 57 19.11 Indoor Air Quality Management 01 57 19.12 Noise & Acoustics Management 01 57 23 Under-An-Acre Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 79 00 Demonstration and Training

02 41 13 Selective Site Demolition

DIVISION 02 – EXISTING CONDITIONS

02 41 19 Selective Demolition

03 01 30 Treatment of Historic Concrete

DIVISION 03 – CONCRETE

03 31 00 Cast-in-place Concrete 03 33 00 Architectural Concrete

NOT USED

DIVISION 04 – MASONRY

05 12 00 Structural Steel

DIVISION 05 – METALS

05 31 00 Steel Deck

YOSE – 154910C TOC-2

05 51 00 Metal Stairs 05 73 00 Decorative Metal Railings

06 20 10 Site Carpentry

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 20 13 Exterior Finish Carpentry 06 20 23 Interior Finish Carpentry 06 20 50 Treatment of Historic Carpentry 06 41 14 Wood Veneer Casework and Paneling

07 01 31 Crack Injection

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 18 00 Traffic Coatings 07 21 00 Thermal Insulation 07 25 00 Weather Barriers 07 26 00 Vapor Retarders 07 52 16 Styrene-Butadiene-Styrene (SBS) Modified Bituminous Membrane Roofing 07 62 00 Sheet Metal Flashing and Trim 07 92 00 Joint Sealants

08 11 13 Steel Doors and Frames

DIVISION 08 – OPENINGS

08 14 00 Wood Doors 08 12 33.98 Treatment of Historic Wood Doors 08 31 13 Access Doors and Frames 08 52 00 Wood Windows 08 71 00 Door Hardware 08 80 00 Glazing 08 91 19 Fixed Louvers

09 22 16 Non-Structural Metal Framing

DIVISION 09 – FINISHES

09 23 00 Gypsum Plaster 09 26 13 Gypsum Veneer Plaster 09 29 00 Gypsum Board Assemblies 09 30 13 Tile 09 51 13 Acoustical Tile Ceilings 09 68 00 Sheet Carpeting 09 77 39 Fiberglass Wall Panels 09 91 13 Exterior Painting and Coating 09 91 23 Interior Painting and Coating

YOSE – 154910C TOC-3

10 14 23 Panel Signage

DIVISION 10 – SPECIALITIES

10 28 13 Toilet and Bath Accessories

11 40 00 Food Service Equipment

DIVISION 11 – EQUIPMENT

DIVISION 12 – SPECIAL CONSTRUCTION

DIVISION 13 – FURNISHINGS

14 26 00 Limited-Use/Limited-Application Elevators

DIVISION 14 – CONVEYING EQUIPMENT

21 03 00 Fire Protection

DIVISION 21 –FIRE SUPPRESSION

22 04 00 Plumbing System

DIVISION 22 –PLUMBING

23 00 50 General Mechanical Requirements

DIVISION 23 – HEATING, VENTILATION, AND AIR CONDITIONING

23 00 60 General Electrical Requirements for Mechanical Systems 23 06 00 HVAC System 23 83 13 Radiant-Heating Electric Cables

DIVISION 24-25

26 05 00 Basic Electrical Requirements

DIVISION 26 – ELECTRICAL

26 08 00 Testing 26 24 00 Service and Distribution System 26 27 00 Basic Electrical Materials and Methods 26 51 00 Lighting

YOSE – 154910C TOC-4

27 00 00 Voice and Data Communication System

DIVISION 27 – TELECOMMUNICATIONS

28 31 01 Fire Alarm System

DIVISION 28 – ELECTRONICS SAFETY AND SECURITY

31 10 00 Site Clearing and Demolition

DIVISION 31 – EARTHWORK

31 10 01 Plant Protection 31 23 00 Site Excavation and Grading 31 23 16 Structure Excavation and Backfilling 31 23 33 Trenching and Backfilling

32 01 90 Pruning

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 13 20 Site Concrete 32 14 00 Unit Paving 32 15 40 Decomposed Granite Paving 32 40 11 Boulders 32 90 00 Planting

33 10 30.13 Storm Drain Line and Manhole Testing

DIVISION 33-UTILITIES

33 05 13 Manholes and Structures 33 05 26 Utility Identification 33 40 00 Storm Drain Pipe and Appurtenances

DIVISION 34-49

YOSE - 154910 01 10 00 - 1

060613 CONTRACT MODIFICATION PROCEDURES

SECTION 01 10 00 –

PART 1 - GENERAL

CONTRACT MODIFICATION PROCEDURES

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit as identified in Part 31 of the Federal Acquisition Regulation

(FAR):

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications.

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums.

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

YOSE - 154910 01 10 00 - 2

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer’s Representative (COR) upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.

All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated http://en.wikipedia.org/wiki/Surety_bond� http://en.wikipedia.org/wiki/Insurance� http://en.wikipedia.org/wiki/Bank� http://www.nps.gov/dscw/publicforms.htm#ct� http://www.nps.gov/dscw/publicforms.htm#ct�

YOSE - 154910 01 10 00 - 3

herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

YOSE - 154910 01 10 00 - 4

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. The following percentages establish the maximum allowable markups (OH&P) for contractor self-performed work:

Overhead………………10% Profit………………7%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 10 00

YOSE - 154910 01 11 00 - 1

050611 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Contractor use of premises.

3. Public use of site.

4. Occupancy requirements for buildings.

5. Work Restrictions.

6. Special Construction Requirements.

7. Soils Investigation Report.

8. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Yosemite Valley, Yosemite National Park, California.

B. The Work consists of the following: The Work includes correction of accessibility and fire safety egress issues at The Ahwahnee. The project is comprised of the following measures:

1. Replacement of the existing non-code compliant exit stairway serving the East Wing of the hotel.

2. Remodeling of four guest rooms on the First Floor and Second Floor East Wing to add two (2) accessible guest suites, one (1) with accessible outdoor balcony.

3. Provision of an elevator providing accessibility from the Ground Floor to the Mezzanine Level meeting rooms.

4. Rehabilitation and remodeling of the Ahwahnee Bar and its existing non-original service additions at the east end of the Ground Floor, including construction of a new Bar Kitchen.

C. Project will be constructed under a single prime contract.

D. Priority of Construction: Coordination and Sequence of construction must be determined before the commencement of work and be approved by Contracting Officer (CO).

E. Concessioner (Tenant) will occupy the building and the hotel will remain open throughout the construction period, although the areas of work will be closed for construction. The Contractor shall have limited use of the rest of the building during construction.

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

YOSE - 154910 01 11 00 - 2

1. Limits: Confine constructions operations to work areas noted on drawings.

B. Storage of Materials: Confine storage of materials to staging areas noted on drawings.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with CO and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

G. Hantavirus Risk: Infection with hantavirus can progress to Hantavirus Pulmonary Syndrome (HPS), which can be fatal. Several hantaviruses that are pathogenic to humans have been identified in the United States, including Yosemite National Park (see Yosemite National Park Directive #9:

Hantavirus Risk Reduction Program). The Contractor must protect their employees from the hazards associated with Hantavirus exposure. Upon undertaking any work, the Contractor must become fully informed of all hazards associated with hantavirus exposure and must provide all protective measures necessary to avoid illness associated with hantavirus exposure. The Contractor’s Accident Prevention Plan (See Section 01 35 23 – Safety Requirements) must provide measures to be undertaken by the Contractor to provide work conditions necessary to prevent illness associated with hantavirus exposure.

1.4 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

YOSE - 154910 01 11 00 - 3

1.5 OCCUPANCY REQUIREMENTS FOR BUILDINGS

A. Existing Buildings

1. Full Occupancy: Tenant will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Tenant usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

1.6 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be performed during normal business working hours of 9 a.m. to 5:30 p.m., Monday through Friday, except when otherwise indicated. Quiet activities such as construction meetings or preparatory work may occur in the staging and field office areas outside the 9 a.m. to 5:30 p.m. time period.

1. If weekend, evening, or early morning hours are needed to complete project on schedule, Contractor shall obtain approval for hours proposed from CO.

2. Hours for drilling or other noisy activities: 9 a.m. to 5:30 p.m., Monday through Friday

B. Existing Utilities

1. Existing Utilities: Notify CO and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify CO not less than 14 days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without CO’s written permission.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

YOSE - 154910 01 11 00 - 4

1.7 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

B. Rain, seasonal snow, and snowmelt flooding may interfere with construction at the Work location and in the Yosemite Valley. Snow plowing of main access routes into Yosemite Valley will be performed by the Government only when required for public safety or convenience. Plowing of access roads to and within the Project work area is the responsibility of the Contractor

C. The Park or Park roads may be closed by the Government during emergencies. Park roads are frequently congested by tourist traffic during the summer months, weekends, and holiday periods.

The Contractor shall take into consideration operational limits on site access.

D. Furniture in work areas will be removed prior to construction by Concessioner. Concessioner will return furniture after construction is complete.

E. Sequencing and Scheduling of the Work: In order to minimize the disruption of guest experiences, hotel operations, traditional holiday programs, and hotel revenue, the architects, NPS staff, and concessioner have developed a schedule and sequencing that is outlined below. The Contractor shall create a detailed schedule and work plan based on this schedule and sequencing.

1. To the greatest extent possible, submittals and mock-ups shall be scheduled for review and approval prior to commencing construction work within the hotel. A Notice to Pro-ceed is expected to be issued after the Pre-Construction Conference in August or Sep-tember 2015. A significant Preinstallation Conference shall be held in December 2015 prior to allowing physical construction that shall commence on January 4, 2016 for work at the East Wing and on February 8, 2016 for work at the South Wing..

2. Preferred Scheduling and Sequencing

a. LU/LA Elevator Installation (South Wing): The Colonial Room, Tudor Lounge, Tresidder Room and Solarium will be closed for installation of the LU/LA Elevator, beginning February 8, 2016. A closure of 14 weeks is anticipated with Beneficial Occupancy by May 20, 2016.

b. Ahwahnee Bar (East Wing): The Ahwahnee Bar will be closed for demolition and construction of improvements to the bar and seating area, beginning January 4, 2016. A closure of 14 weeks is anticipated with Beneficial Occupancy by April 15, 2016. The bar will then reopen for limited service until the bar kitchen is complete.

c. Ahwahnee Bar Kitchen (East Wing): The Ahwahnee Bar Kitchen will be closed for demolition and construction of a new kitchen, beginning January 4, 2016. A closure of 29 weeks is anticipated with Beneficial Occupancy by July 29, 2016.

d. Accessible Guest Rooms (East Wing): Guest Rooms at the east end of the East Wing will be closed for demolition and construction of two new guest suites and an

YOSE - 154910 01 11 00 - 5

interior egress stair, beginning January 4, 2016. A closure of 21 weeks is anticipat-ed with Beneficial Occupancy by May 27, 2016.

e. Egress Issues:

1. Temporary egress from the first and second floors of the east wing will be established through Guest Rooms 105 and 205 to metal scaffold stair as indicated on drawings. Demolition of existing addition at north end of Bar must be complete before temporary stair can be installed. Existing egress at east end of east wing must be maintained until temporary egress is ready for use.

2. Once in use, temporary egress must be maintained until safe egress from the east wing is established using the new stair. Safe egress using new stair shall be available when work at Accessible Guest Rooms is com-plete (May 27, 2016). Site work affecting the egress path must be com-plete by the same date.

1.8 HISTORIC BUILDING FEATURES

A. The Ahwahnee Hotel is a designated national historic landmark of extreme architectural significance. Work within the building and the surrounding site shall be of the highest quality and shall comply with the requirements of the United States Secretary of the Interior’s Standards for the Treatment of Historic Properties.

B. The contractor shall make no assumptions regarding the significance of historic building elements and details. All questions regarding significance shall be directed to the CO, who will direct the question to the appropriate personnel per Section 013591.

1.9 SOILS INVESTIGATION REPORT

A. A soils investigation report entitled Geotechnical Investigation Ahwahnee Hotel, Yosemite National Park, California, dated 24 November 2009, has been prepared by Treadwell & Rollo Geotechnical Consultants.

B. A copy of the report is available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

1.10 HAZARDOUS MATERIALS REPORT

A. An investigation for Asbestos Containing Building Materials (ACBM) was performed by hazard Management Services, Inc. The resulting report is dated 22 October 1990.

B. A copy of the report is available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

YOSE - 154910 01 11 00 - 6

1.11 ADDITIONAL REPORTS

A. Two related reports entitled The Ahwahnee Historic Structures Report and The Ahwahnee Cultural Landscape Report, both dated January 2011, have been prepared by Architectural Resources Group.

B. A copy of the reports is available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

YOSE - 154910 01 27 00 - 1

050611 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No. 1: Limited-Use/Limited-Application Elevator Installation.

1. This item consists of all work associated with installation of Limited-Use/Limited Application Hydraulic Passenger Elevator in South Wing, including installation of elevator and machine room, modifications to existing stair, and installation of guardrail attachment to existing railing at Tudor Lounge.

2. Payment will be made at the contract lump sum price.

B. Contract Line Item No. 2: East Wing Egress Stair.

1. This item consists of all work associated with installation of new interior egress stair from second floor to first floor, including metal stair and handrails, stair enclosure, new interior door at the second floor, and new exterior door at first floor. This item does not include new exterior egress stair from first floor to grade at East Wing (see Contract Line Item No. 4 for this scope).

2. Payment will be made at the contract lump sum price.

C. Contract Line Item No. 3: Guest Room Upgrades.

1. This item consists of all work associated with modifications required to convert Guest Rooms 106/107 and 206/207 into two accessible guest suites, including access from first floor suite to new balcony terrace above new Bar Kitchen. This item includes the paving system and the raised platform supporting it at the new accessible terrace, but it does not include the structure around or below it (see Contract Line Item No. 4 for this scope).

2. Payment will be made at the contract lump sum price.

YOSE - 154910 01 27 00 - 2

050611 DEFINITION OF CONTRACT LINE ITEMS

D. Contract Line Item No. 4: Remodel Ahwahnee Bar.

1. This item consists of all work to demolish existing wood-frame additions to the Ahwahnee Bar, to construct new Bar Kitchen addition and to make modifications to the Ahwahnee Bar. This item includes the new exterior egress stair from first floor to grade at East Wing. This item also includes all site work, including landscaping, paving and site utilities.

2. Payment will be made at the contract lump sum price.

E. Option A: South Glazed Wall of Bar, East Wing.

1. Contract Line Item No. 5: South Glazed Wall of Bar, East Wing.

a. This item consists of all work associated with demolition of existing glazed wall at south wall of Bar and installation of new glazed wall in same location.

b. Payment will be made at the contract lump sum price.

F. Option B: Snow Melt System (Radiant-Heating Electric Cables) at Exterior Stair, East Wing.

1. Contract Line Item No. 6: Snow Melt System at Exterior Stair, East Wing.

a. This item consists of all design-build work associated with the installation of an electrical snow melt system in the new exterior concrete stairs and landings from the edge of the existing first floor balcony (grid line E0.7) to grade at the north face and south face of the new kitchen (grid lines EC.5 and EA.5) as shown on Sheet A2.2 and defined in Specification Section 23 83 13.

b. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

YOSE - 154910 01 31 00 - 1

060613 PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Construction Coordination.

2. Coordination Drawings.

3. Requests for Information (RFIs).

4. NPS/DSC SharePoint Project Website.

5. Project meetings.

6. Environmental Coordination.

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts

YOSE - 154910 01 31 00 - 2

and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

1.3 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

e. Indicate required installation sequences.

2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches (750 by 1000 mm).

3. Number of Copies: Submit electronic files.

4. Refer to individual Sections for Coordination Drawing requirements for Work in those

Sections.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.

YOSE - 154910 01 31 00 - 3

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Mechanical and Plumbing Work: Show the following:

a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.

b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.

c. Fire-rated enclosures around ductwork.

7. Electrical Work: Show the following:

a. Runs of vertical and horizontal conduit 1-1/4 inches (32 mm) in diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.

c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.

d. Location of pull boxes and junction boxes, dimensioned from column center lines.

8. Fire-Protection System: Show the following:

a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.

9. Review: CO will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform Contractor, who shall make changes as directed and resubmit.

10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."

C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Preparation Format: AutoCad.dwg, Version 2008, operating in Microsoft Windows operating system.

3. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.

4. CO will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.

YOSE - 154910 01 31 00 - 4

a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCad.dwg.

D. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer or CO will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).

11. Indoor Air Quality (IAQ) Management Plan.

12. Historic Preservation Treatment Plan.

E. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.

Work shall not commence until written Notice to Proceed has been issued.

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

YOSE - 154910 01 31 00 - 5

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:

1. Enter the general information at the top of the form.

2. Under the “Action” section at the bottom of the form, select “Question” then select

“CMR” in the drop-down of the “Send to” box.

3. Enter the details of the question and attach related documents.

4. Select “Submit Form” at the bottom of the page.

D. CO’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.5 PROJECT WEB SITE

A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period. The NPS/DSC SharePoint Project website will be used for the following functions:

1. Project directory.

2. Project correspondence.

3. Meeting agendas and minutes.

4. Contract modifications forms and logs.

5. RFI form and processing.

6. Task and issue management.

7. Photo documentation.

8. Baseline schedule, schedule updates and calendar management.

9. Submittal form and processing.

YOSE - 154910 01 31 00 - 6

10. Payment coordination documentation.

11. Drawing and specification document hosting, viewing, and updating.

12. Online document collaboration.

13. Reminder and tracking functions.

14. Archiving functions.

15. Notification of submittal and RFI statuses and current responsible party.

16. Permits and addendums

B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.

C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.

D. All users will be required to have the following software packages:

1. Internet Explorer version 7 or later.

2. Adobe Acrobat Professional (Pro) version 9 or later

1.6 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, CO will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

10. Contract time.

11. Liquidated damages.

12. Contractor Performance Evaluation.

13. Display of Hotline posters.

14. Notice to proceed.

15. Correspondence procedures.

16. NPS/DSC SharePoint Project website.

17. Acceptance/rejection of work.

18. Progress meetings.

19. Submittal procedures.

20. NPS Final Accessibility Inspection.

21. Environmental requirements.

http://www.nps.gov/dscw/precon_spproj.htm�

YOSE - 154910 01 31 00 - 7

22. Permit requirements.

23. As-constructed drawings/operation and maintenance (O&M) manuals.

24. Saturday, Sunday, holiday and night work.

25. Reference materials.

26. Value engineering.

27. Performance of interim accessibility inspections by Contractor, utilizing CQC

Accessibility Report (template included in Section 01 40 00).

B. Progress Meetings: The CO will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections,

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

YOSE - 154910 01 31 00 - 8

j. Compatibility requirements.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written instructions.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of authorities having jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

z. Performance of interim accessibility inspections by Contractor, utilizing CQC

Accessibility Report (template included in Section 01 40 00).

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

1.7 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan(WMP).

c.

This is the start of the file's text. The full file is on GovTribe.