Summary

This Invitation for Quote/Bid (IFQ/B) from Palm Beach County's Capital Improvements Division seeks qualified contractors on the Annual Contract - Low Voltage to furnish and install access control and fire alarm replacement systems at Senior Supportive Housing, located at 5981 Okeechobee Blvd, West Palm Beach, Florida. The project scope includes removal and installation of a multi-tenant building access control solution featuring Schlage Allegion XE360 Series Wireless Mortise Locks on 114 tenant rooms and 16 common area doors, a Honeywell Prowatch access control system for administrative areas, fire alarm control panel replacement with Notifier NFW-100X units and associated battery systems, installation of 32 System Sensor weatherproof back boxes, and comprehensive system testing with NFPA72 documentation. A mandatory pre-bid conference is scheduled for September 23, 2025, at 10:00 a.m. at the project site. Quotes/bids are due by October 16, 2025, at 2:00 p.m. at the Capital Improvements Division, 2633 Vista Parkway, West Palm Beach, Florida 33411. The contractor must substantially complete all work within 30 calendar days from the Notice to Proceed. Liquidated damages of $240 per day apply for failure to achieve substantial completion within the specified timeframe.

Bid security and a public construction bond are required for bids of $200,000 or more, with the bid security set at a minimum of 5% of the bid price and the public construction bond at 100% of the work order amount. The contract is subject to Palm Beach County's Equal Business Opportunity Program requirements, including completion of EBO Schedules 1 and 2 documenting all subcontractors and SBE participation. An SBE Price Preference provision applies, whereby a certified SBE's bid within 10% of the lowest non-SBE bid shall be awarded the contract. To be considered, contractors must be pre-qualified under the Annual Contract - Low Voltage and submit their qualification application at least 10 days before the bid due date. The contract incorporates the Annual Contract - Low Voltage terms and conditions, includes a 24-month warranty on all equipment, materials, and labor from substantial completion, and requires the contractor to provide a Certificate of Occupancy or Completion prior to final payment processing.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFQ/B Page 1 Form Rev. 6/9/25 Invitation for Quote/Bid - NonFederal

INVITATION FOR QUOTE/BID

ANNUAL CONTRACT

DATE: 8/29/2025

SENT TO: Qualified Contractors

On the Annual Contract - Low Voltage

SENT FROM: Capital Improvements Division

SENDER: Marc Hartley, Facilities Systems Project

Manager

PHONE: (561)233-2053

PROJECT NAME: Senior Supportive Housing - Access Control

& FA Replacement

PROJECT NUMBER: P-2025-000140

Mandatory Pre-Bid Conference. There will be a Mandatory Pre-Bid Meeting at

Senior Supportive Housing, located at 5981 Okeechobee Blvd, West Palm Beach

(meet at main entrance) at 10:00 a.m. on September 23, 2025. The purpose of this pre-bid meeting will be to review the requirements for the project described in this Invitation for Quote/Bid. You must attend this meeting if you intend to bid this work.

The work is to be done under the terms and conditions of Palm Beach

County’s Annual Contract - Low Voltage as supplemented by this

Invitation for Quote/Bid.

Questions must be e-mailed to FDO-CID-Bids@pbc.gov at least seven (7) calendar days prior to the bid due date. Only questions received in writing will be responded to regarding this Invitation for Quote/Bid.

“An Equal Opportunity

Employer”

Interim County Administrator

Todd J. Bonlarron file://///pbcgov.org/FDO/common/Business/Znachko%20Working%20File/CID%20Forms/Contracts/Construction%20-%20Annual%20(Pre-Qual)/NonFederal/Invitation%20for%20Quote/FDO-CID-Bids@pbc.gov

IFQ/B Page 2

Submitting the Quote/Bid Package

The Quote/Bid Package must be enclosed in a sealed opaque envelope. The envelope must be addressed as follows:

Project Name: Senior Supportive Housing - Access Control & FA Replacement

Project Number: P-2025-000140

Capital Improvements Division

2633 Vista Parkway

West Palm Beach, Florida 33411

Attention:

No responsibility will be attached to the Owner for premature opening of or failure to open a quote/bid not properly identified. If the quote/bid is sent by mail, the sealed envelope must be enclosed in a separate mailing with the notation "SEALED QUOTE/BID ENCLOSED" on the face thereof.

PROJECT NAME: Senior Supportive Housing - Access Control & FA Replacement

PROJECT NO.: P-2025-000140

*DUE: October 16, 2025 by 2:00 p.m.

* The Quotes/Bids received by this time will be opened at this time at a public meeting at the below address.

RETURN TO: Capital Improvements Division

2633 Vista Parkway

West Palm Beach, FL 33411

Qualification of Contractors. In order to submit a quote/bid in response to this IFQ/B, a contractor must be qualified under the Annual Contract - Low Voltage. A contractor may obtain a Qualification

Application for this Annual Contract by sending an email with the Project # in the subject line to:

FDO-CID-Bids@pbc.gov or call (561) 233-0261. Qualification applications may also be downloaded from the County’s on-line Vendor Self-Service (VSS) system at https://pbcvssp.pbc.gov/vssprd/Advantage4. The contractor must submit the Qualification

Application at least 10 days before the Quote/Bid Due Date in order for its quote/bid to be considered.

file://///pbcgov.org/FDO/common/Business/Znachko%20Working%20File/CID%20Forms/Contracts/Construction%20-%20Annual%20(Pre-Qual)/NonFederal/Invitation%20for%20Quote/FDO-CID-Bids@pbc.gov https://pbcvssp.pbc.gov/vssprd/Advantage4 https://pbcvssp.co.palm-beach.fl.us/webapp/vssp/AltSelfService

IFQ/B Page 3

1. SCOPE OF WORK: This Quote/Bid is to furnish all material, labor, supervision, permits and supplies necessary and reasonably incidental to provide and install a fully functional multi-tenant building access control solution and fire alarm replacement per the project requirements provided by Capital Improvements

Division in this Invitation for Quote/Bid at Attachment “C” and all exhibits and addenda thereto. Work is to be done under the terms and conditions of Palm Beach County’s Annual Contract - Low Voltage, and pursuant to the conditions of the Work Order, both of which are incorporated into the Contract

Documents by reference.

2. SCHEDULE OF TIME FOR COMPLETION. The time of completion for this Project will be as follows: The Contractor must substantially complete the work within thirty 30 calendar days from the

Notice to Proceed from Owner.

3. LIQUIDATED DAMAGES. Liquidated Damages are $240/day for failure to achieve certification of

Substantial Completion within the Work Order time or approved extension thereof.

4. BID SECURITY AND PUBLIC CONSTRUCTION BOND. Bid Security and Public Construction

Bond are required for this Project in accordance with Section 5.2 of the Instructions to Bidders of the Annual

Contract as follows:

Bid Security. If Bid is $200,000 or over, this Bid must be accompanied by a Bid Security (in the form of, at Bidder's option, cashier's check, certified check, money order or Bid Bond in favor of the County) in the amount of at least five percent (5%) of the bid price, see Section 5.2.2 of the

Instructions to Bidders of the Annual Contract for detailed requirements regarding Bid Security and Attachment “B”.

Public Construction Bond. If Bid is $200,000 or over (or if cumulative open work orders are

$200,000 or over), then prior to execution of a Work Order, and not later than fourteen (14) calendar days after notification from Owner, the successful Bidder must furnish a Public

Construction Bond in the amount of 100% of the Work Order and Guarantee, see Section 5.2.3 of the Instructions to Bidders of the Annual Contract for detailed requirements regarding the Public

Construction Bond and Guarantee.

5. Equal Business Opportunity Program. Section 5.3 of the Instruction to Bidders of the Annual Contract sets out the requirements of the County’s Equal Business Opportunity Program. All Bidders are required to submit with their bid the appropriate EBO Program schedules. EBO Schedules to be submitted with the quote/bid are as follows:

a) Schedule 1 - List of All Proposed Subcontractors, including SBE Participation. A completed Schedule 1 shall list the names of all subcontractors, including SBE subcontractors, intended to be used in performance of the Work Order, if awarded. This schedule shall also be used if an SBE prime bidder is performing any work and/or using any subcontractors.

b) Schedule(s) 2 - Letter(s) of Intent to Perform as a Subcontractor, including SBE

Subcontractors. A Schedule 2 for each subcontractor, including each SBE subcontractor, listed on Schedule 1, shall be completed and executed by the proposed subcontractor. The type of Work to be performed by each subcontractor and the dollar value or percentage shall also be specified. Additional copies may be made as needed. A completed Schedule 2 is a binding agreement between the prime contractor and the subcontractor and should be treated as such.

Attachment “A” identifies the affirmative procurement initiatives (APIs) applicable to this Invitation for Quote/Bid.

IFQ/B Page 4

If Bidder is unable to comply with the API requirements (Attachment “A” hereto), such Bidder shall submit a request for a waiver or partial waiver at least (7) days prior to the quote/bid due date If

Bidder requests a waiver from an API from the Office of EBO at least 7 days prior to the quote/bid due date, then the quote/bid due date will be extended pending the outcome of a waiver request.

Additionally, if the waiver is granted, the solicitation will be amended accordingly and the due date extended again.

6. Addendum. Any interpretation, clarification, correction, or change of the Bidding Documents will be made only by Addendum. The Department will send written instructions regarding discrepancies, omissions or unclear intents to all Bidders who are Qualified Contractors with an Annual Contract. For projects

$150,000 and over all Addendum to a solicitation will also be posted under the applicable solicitation on the County’s on-line Vendor Self-Service (VSS) system at https://pbcvssp.pbc.gov/vssprd/Advantage4.

Interpretations, corrections or changes to the Bidding Documents made in any other manner will not be binding, and Bidders shall not rely upon such interpretations, corrections and changes. Prior to submission of its Bid/Quote, each Bidder must ascertain that it has received all Addenda issued. The Bidder must acknowledge receipt of each individual Addendum at the time of issuance and final receipt of all Addenda by completing the acknowledgment space provided on the Addendum Form. Failure to acknowledge receipt may result in rejection of a bid/quote.

7. Failure to Provide the Required Documents after Notification of Award. If after Notification of award from the County, the successful Bidder does not provide within 14 Days of Notification the signed

Work Order, the Public Construction Bond and Guarantee (when required), and the required certificates of insurance, the County may: 1. Call in the bid security when provided; 2. Cancel the notification of recommended award and award the project to the next responsive, responsible low bidder; 3. Terminate this Annual Contract for cause; 4. Suspend or debar the Bidder from bidding on future projects for a period of two (2) years, in accordance with the Palm Beach County Purchasing Ordinance; and/or 5. Pursue any and all remedies available against the Bidder for damages resulting from its failure to enter into a Work

Order and provide all required documents within 14 Days after notification.

8. Prohibition against Considering Social, Political or Ideological Interests in Government

Contracting - F.S. 287.05701. Bidders are hereby notified of the provisions of section 287.05701, Florida

Statutes, as amended, that the County will not request documentation of or consider a Bidder's social, political, or ideological interests when determining if the Bidder is a responsible Bidder. Bidders are further notified that the County's governing body may not give preference to a Bidder based on the Bidder's social, political, or ideological interests.

9. Human Trafficking Affidavit. Contractor warrants and represents that it does not use coercion for labor or services as defined in section 787.06, Florida Statutes. Contractor shall execute

Attachment “D”, Nongovernmental Entity Human Trafficking Affidavit, which is attached hereto and incorporated herein by reference.

10. Living Wage Ordinance. Pursuant to section 255.0992, Florida Statutes, the County’s Living Wage

Ordinance shall not apply to this Invitation for Quote/Bid and any resulting Work Order(s), notwithstanding any provision of an existing Annual Contract to the contrary, including, but not limited to, the Instructions to Bidders, the General Conditions to the Annual Contract and the Certification of Compliance with the

Living Wage Ordinance.

11. CONTRACT AMENDMENTS. The Annual Contract is amended as follows:

The following General Conditions are added to the General Conditions:

https://pbcvssp.co.palm-beach.fl.us/webapp/vssp/AltSelfService

IFQ/B Page 5

GC 84 INTERACTIONS WITH COUNTY STAFF

In all interactions with County staff, Contractor and its employees will conduct themselves in a professional manner at all times and treat County staff with respect and dignity. Use of offensive and demeaning language will not be tolerated. Failure to comply with this requirement will be considered a default under this Contract and may result in termination of this Contract.

GC 85 DISCLOSURE OF FOREIGN GIFTS AND CONTRACTS WITH FOREIGN

COUNTRIES OF CONCERN

Pursuant to F.S. 286.101, as may be amended, by entering into a contract or performing any work in furtherance thereof, the Contractor certifies that it has disclosed any current or prior interest of, any contract with, or any grant or gift received from a foreign country of concern where such interest, contract, or grant or gift has a value of $50,000 or more and such interest existed at any time or such contract or grant or gift was received or in force at any time during the previous five

(5) years.

Section 4.2.3 of the “Instructions To Bidders” of the Contract, the third sentence of this section is amended and modified to reflect the revised threshold amount for advertisement on the vendor self-service (VSS) website as follows:

For projects $150,000 and over, all Addendum to a solicitation will also be posted under the applicable solicitation on the County’s on-line Vendor Self-Service (VSS) system at https://pbcvssp.pbc.gov/vssprd/Advantage4.

Section 4.3.1 of the “Instructions To Bidders” of the Contract, the second sentence of this section is

For projects $150,000 and over, all Addendum to a solicitation will also be posted under the applicable solicitation on the County’s on-line Vendor Self-Service (VSS) system at https://pbcvssp.pbc.gov/vssprd/Advantage4.

Section 6.3.2 of the “Instructions To Bidders” of the Contract is deleted in its entirety and replaced with the following:

6.3.2 For awards of $150,000 or greater, bid/quote tabulations and Notification from Owner, with recommended awards, will be posted at the location where bids were opened, for review by interested parties prior to submission through the appropriate approval process, and will remain posted for a period of five (5) business days. For awards of $150,000 or greater, any bidder who is aggrieved in connection with the recommended award of a Work Order under an Annual

Contract may protest to the County’s Director of Procurement. The protest must be received by the Procurement Director within five (5) business days after posting of the award recommendation. The protest must be submitted in writing, must identify the protestor and the solicitation, must include a factual summary of the basis of the protest and must include a protest bond in the amount of: (1) one thousand five hundred dollars ($1,500.00) for solicitations less than one million dollars ($1,000,000.00); (2) three thousand dollars ($3,000.00) for solicitations one million dollars ($1,000,000.00) to less than five million dollars ($5,000,000.00); or (3) five thousand dollars ($5,000.00) for solicitations five million dollars ($5,000,000.00) or greater, which bond shall be remitted in the form of a money order, certified check, a cashier’s check, or a

IFQ/B Page 6 bank check payable to Palm Beach County. Such protest is considered filed when it is received and date/time stamped by the Department of Procurement. The date/time stamp of the

Procurement Department shall control when determining whether the protest was received by the

Director of Procurement within the time frame specified for the notice of protest. Neither the

Director of Procurement nor a special master shall consider any issue not submitted in writing within the time frame specified for the notice of protest.

Section 10.0 of the “Instructions To Bidders” of the Contract, is amended and modified to reflect the revised threshold amount for the Lobbying section to apply as follows:

LOBBYING (for Bids that Exceed $150,000)

Section 14.1 of the Instructions To Bidders of the Contract, the fourth sentence of this section is

Projects $150,000 and over will also be advertised on VSS.

Quote/Bid Form Page 1 Form Rev. 6/9/25 Quote/Bid Form - NonFederal

QUOTE/BID FORM

PROJECT NAME: Senior Supportive Housing - Access Control & FA Replacement

IN ORDER TO BE DEEMED RESPONSIVE TO THIS INVITATION FOR QUOTE/BID,

THE QUOTE/BID PACKAGE MUST CONTAIN:

a) This Quote/Bid Form completed and executed.

b) EBO Schedules 1 and 2 completed and executed.

c) Bid Security. (If the bid is $200,000 or more).

d) Signed Addenda, if any issued

THE FOLLOWING MUST BE COMPLETED AND SIGNED BY CONTRACTOR

1. TOTAL QUOTE/BID AMOUNT $ ____________

Written amount ____________

2. Bidder commits to achieving the APIs applicable to this solicitation as designated on Attachment

A and as submitted on its EBO Schedules 1 and 2.

3. Is the Bidder a Palm Beach County certified SBE? Yes_____ No_____

4. Commercial Non-Discrimination Certification. The undersigned Bidder hereby certifies and agrees that the following information is correct: In preparing its response to this Solicitation, the

Bidder has considered all proposals submitted from qualified, potential Subcontractors and suppliers, and has not engaged in "discrimination" as defined in the County’s Commercial

Nondiscrimination Policy as set forth in Resolution 2025-0748, as may be amended, to wit:

discrimination in the solicitation, selection or commercial treatment of any Subcontractor, vendor, supplier or commercial customer on the basis of race, color, national origin, religion, ancestry, sex, age, marital status, familial status, sexual orientation, disability, or genetic information, or on the basis of any otherwise unlawful use of characteristics regarding the vendor's, supplier's or commercial customer's employees or owners; provided that nothing in this policy shall be construed to prohibit or limit otherwise lawful efforts to remedy the effects of discrimination that have occurred or are occurring in the County’s relevant marketplace of Palm Beach County.

Without limiting the foregoing, "discrimination" also includes retaliating against any person or other entity for reporting any incident of "discrimination." Without limiting any other provision of the solicitation, it is understood and agreed that, if this certification is false, such false certification will constitute grounds for the County to reject the bid submitted by the Bidder for this Solicitation, and to terminate any contract awarded based on the response. As part of its bid, the Bidder shall provide to the County a list of all instances within the immediate past four (4) years where there has been a final adjudicated determination in a legal or administrative proceeding in the State of Florida that the Bidder discriminated against its Subcontractors, vendors, suppliers or commercial customers, and a description of the status or resolution of that complaint, including any remedial action taken. As a condition of submitting a bid to the County, the Bidder agrees to

Quote/Bid Form Page 2 Form Rev. 6/9/25 Quote/Bid Form - NonFederal comply with the County’s Commercial Nondiscrimination Policy as described in Resolution 2025-

0748, as may be amended.

5. The Bidder shall be bound by the terms of its Bid for a period of one hundred twenty (120) calendar Days from the date of the bid opening and may not withdraw its Bid within that time period. If the County issues a Notification from Owner within the above 120-Day period, then the

Bidder will be bound by the Bid as submitted. If the County fails to issue a Notification from

Owner to the successful Bidder within the above identified 120-Day period, the successful bidder will not be required to honor its bid unless otherwise agreed to by both parties. County anticipates, but does not guarantee, the award of a Work Order and written notice to proceed within ninety (90) calendar Days of Notification from Owner, absent the filing of a timely bid protest.

6. It is agreed that the undersigned has received all addenda complete as issued by the County and that related costs are included in the bid submitted. The undersigned acknowledges receipt of said addenda as follows:

Addendum # dated Addendum# dated

Addendum # dated Addendum# dated

The undersigned has included the signed addenda, if issued, in its bid package.

7. The undersigned does hereby declare that the Bid covers all expenses of every kind incidental to the completion of said Work in accordance with the Contract Documents, including all claims that may arise through damages or other causes whatsoever. The undersigned does hereby declare that it shall make no claim on account of any variation from any estimate in the quantities of Work to be done, nor on account of any misunderstanding or misconception of the nature of the Work to be done or the grounds, subsurface conditions, or place where the Work is to be done.

QUOTE/BID PROVIDED BY:

Contractor Name

Date Signature

Print Name and Title

Quote/Bid Must Contain Original Signatures. No Copies or Emailed/Faxed Quotes/Bids Will

Be Accepted

OEBO SCHEDULE 1*

SOLICITATION/PROJECT/BID NAME: SOLICITATION/PROJECT/BID NO.:

SOLICITATION OPENING/SUBMITTAL DATE: COUNTY DEPARTMENT:

Section A PLEASE LIST THE DOLLAR AMOUNT OR PERCENTAGE OF WORK TO BE COMPLETED BY THE PRIME CONTRACTOR/CONSULTANT* ON THE PROJECT:

NAME OF PRIME RESPONDENT/BIDDER: ADDRESS:

CONTACT PERSON: PHONE NO.: E-MAIL:

PRIME’S DOLLAR AMOUNT OR PERCENTAGE OF WORK: Non-SBE SBE

Section B PLEASE LIST THE DOLLAR AMOUNT OR PERCENTAGE OF WORK TO BE COMPLETED BY ALL SUBCONTRACTORS/SUBCONSULTANTS ON THE PROJECT BELOW:

Subcontractor/Sub consultant Name (Check all Applicable Categories)

Non-SBE SBE

DOLLAR AMOUNT OR

PERCENTAGE OF WORK

1.

2.

3.

4.

5.

(Please use additional sheets if necessary) Total _________________________

Total Bid/Offer Price $ Total Certified SBE Participation $

I hereby certify that the above information is accurate to the best of my knowledge:

Name & Authorized Signature Title Note: 1. The amount listed on this form for a Subcontractor/sub consultant must be supported by price or percentage listed on the properly executed Schedule 2 or attached signed proposal.

2. Only those firms certified by Palm Beach County at the time of solicitation due date are eligible to meet the established OEBO Affirmative Procurement Initiative (API). Please check the applicable box and list the dollar amount or percentage under the appropriate demographic category.

3. Modification of this form is not permitted and will be rejected upon submittal.

4. If a Mandatory API goal applies, failure to submit a properly executed Schedule 2 will result in a determination of non-responsiveness to the solicitation.

SBE Prime’s must include their percentage or dollar amount in the Total Participation line under section B.

*Revised 6.5.2025 pursuant to Emergency Ordinance 2025-014, approved on June 3, 2025

OEBO LETTER OF INTENT – SCHEDULE 2*

A completed Schedule 2 is a binding document between the Prime Contractor/consultant and a Subcontractor/subconsultant (for any tier) and should be treated as such. All Subcontractors/subconsultants, including any tiered Subcontractors/ subconsultants, must properly execute this document. If a Mandatory API goal applies, failure to submit a properly executed Schedule 2 will result in a determination of non-responsiveness to the solicitation. Each properly executed Schedule 2 must be submitted with the bid/proposal.

SOLICITATION/PROJECT NUMBER:

SOLICITATION/PROJECT NAME:

Prime Contractor: Subcontractor:

(Check box(s) that apply)

□ SBE □ Non-SBE □ Supplier Date of Palm Beach County Certification (if applicable): .

SBE PARTICIPATION – SBE Primes must document all work to be performed by their own work force on this form. Specify in detail, the scope of work to be performed or items supplied with the dollar amount and/or percentage for each work item. When applicable, identify the line item(s) associated with the service/product being supplied. SBE credit will only be given for the areas in which the SBE is certified. A detailed quote/proposal may be attached to a properly executed Schedule 2 for additional information.

The undersigned Subcontractor/subconsultant is prepared to self-perform the above-described work in conjunction with the aforementioned project at the following total price or percentage:

Print Name of Prime

By:

Authorized Signature

Print Name of Subcontractor/subconsultant

By:

Authorized Signature

Print Name Print Name

Title Title

Date: Date:

Line Item

Item Description Unit Price Quantity/ Units

Contingencies/ Allowances

Total Price/Percentage

If the undersigned intends to subcontract any portion of this work to another Subcontractor/subconsultant, please list the business name and the amount below accompanied by a separate properly executed Schedule 2.

Price or Percentage:

Name of 2nd/3rd tier Subcontractor/subconsultant

OEBO SCHEDULE 1*

SOLICITATION/PROJECT/BID NAME: SOLICITATION/PROJECT/BID NO.:

SOLICITATION OPENING/SUBMITTAL DATE: COUNTY DEPARTMENT:

Section A PLEASE LIST THE DOLLAR AMOUNT OR PERCENTAGE OF WORK TO BE COMPLETED BY THE PRIME CONTRACTOR/CONSULTANT* ON THE PROJECT:

NAME OF PRIME RESPONDENT/BIDDER: ADDRESS:

CONTACT PERSON: PHONE NO.: E-MAIL:

Non-SBE SBE

Section B PLEASE LIST THE DOLLAR AMOUNT OR PERCENTAGE OF WORK TO BE COMPLETED BY ALL SUBCONTRACTORS/SUBCONSULTANTS ON THE PROJECT BELOW:

Subcontractor/Sub consultant Name (Check all Applicable Categories)

Non-SBE SBE

DOLLAR AMOUNT OR

PERCENTAGE OF WORK

1.

2.

3.

4.

5.

(Please use additional sheets if necessary) Total _________________________

Total Bid/Offer Price $ Total Certified SBE Participation $

I hereby certify that the above information is accurate to the best of my knowledge:

Title

DIRECTION: List Firm Name, Address & Provide PBC Vendor ID#. (https://www.pbcgov.org/pbcvendors)

Subcontractor 1 1222 Easy St., WPB, FL 33401

561-123-4567 VC178229

Subcontractor 2 5600 Carefree Lane, WPB, FL 33411

954-345-6789 VC123459

SAM

PLE

John Doe

PRIME’S DOLLAR AMOUNT OR PERCENTAGE OF WORK:

SBE Prime’s must include their percentage or dollar amount in the Total Certified SBE Participation line under section B.

Name & Authorized Signature Note: 1. The amount listed on this form for a Subcontractor/sub consultant must be supported by price or percentage listed on the properly executed Schedule 2 or attached signed proposal.

2. Only those firms certified by Palm Beach County at the time of solicitation due date are eligible to meet the established OEBO Affirmative Procurement Initiative (API). Please check the applicable box and list the dollar amount or percentage under the appropriate demographic category.

3. Modification of this form is not permitted and will be rejected upon submittal.

4. If a mandatory API goal applies, failure to submit a properly executed Schedule 2 will result in a determination of non-responsiveness to the solicitation.

*Revised 6.5.2025 pursuant to Emergency Ordinance 2025-014, approved on June 3, 2025 ddelriocabrera Textbox MUST List ALL Subcontractors/Subconsultants ddelriocabrera Textbox Add All Certified SBE Amounts, Including Prime SBE ddelriocabrera Typewriter $145,385.80 ddelriocabrera Typewriter 181,380.85 ddelriocabrera Textbox

SAMPLE

ddelriocabrera Textbox $86,380.85

Subcontractor:

SBE PARTICIPATION – SBE Primes must document all work to be performed by their own work force on this form. Specify in detail, the scope of work to be performed or items supplied with the dollar amount and/or percentage for each work item. When applicable, identify the line item(s) associated with the service/product being supplied. SBE credit will only be given for the areas in which the SBE is certified. A detailed quote/proposal may be attached to a properly executed Schedule 2 for additional information.

The undersigned Subcontractor/subconsultant is prepared to self-perform the above-described work in conjunction with the aforementioned project at the following total price or percentage:

Print Name of Prime

By:

Authorized Signature

Print Name of Subcontractor/subconsultant

By:

Authorized Signature

Print Name Print Name

Line Item

Item Description Unit Price Quantity/ Units

Contingencies/ Allowances

Total Price/Percentage

If the undersigned intends to subcontract any portion of this work to another Subcontractor/subconsultant, please list the business name and the amount below accompanied by a separate properly executed Schedule 2.

Price or Percentage:

Name of 2nd/3rd tier Subcontractor/subconsultant

*Revised�6.5.2025�pursuant�to�Emergency�Ordinance�2025-014,�approved�on�June�3,�2025

SAMPLE OEBO LETTER OF INTENT – SCHEDULE 2*

SOLICITATION/PROJECT NUMBER:

SOLICITATION/PROJECT NAME:

19600

Carlin Park, Maintenance Bldg, Roofing Replacement

$95,000Remove and replace existing roof

President

John Doe

Roofers Are Us, Inc.

Prime Contractor: Roofers Are Us, Inc.

(Check box(s) that apply)

☒ SBE □ Non-SBE □ Supplier

Title

Date: 6/4/2025

A completed Schedule 2 is a binding document between the Prime Contractor/consultant and a Subcontractor/subconsultant (for any tier) and should be treated as such. All Subcontractors/subconsultants, including any tiered Subcontractors/ subconsultants, must properly execute this document. If a mandatory API goal applies, failure to submit a properly executed Schedule 2 will result in a determination of non-responsiveness to the solicitation. Each properly executed Schedule 2 must be submitted with the bid/proposal.

Date of Palm Beach County Certification (if applicable):3/30/2024 .

Title

Date: 6/4/2025 dlynch Highlight dlynch Highlight

Subcontractor:

SBE PARTICIPATION – SBE Primes must document all work to be performed by their own work force on this form. Specify in detail, the scope of work to be performed or items supplied with the dollar amount and/or percentage for each work item. When applicable, identify the line item(s) associated with the service/product being supplied. SBE credit will only be given for the areas in which the SBE is certified. A detailed quote/proposal may be attached to a properly executed Schedule 2 for additional information.

The undersigned Subcontractor/subconsultant is prepared to self-perform the above-described work in conjunction with the aforementioned project at the following total price or percentage:

Print Name of Prime

By:

Authorized Signature

Print Name of Subcontractor/subconsultant

By:

Authorized Signature

Print Name Print Name

Title

Date:

Line Item

Item Description Unit Price Quantity/ Units

Contingencies/ Allowances

Total Price/Percentage

If the undersigned intends to subcontract any portion of this work to another Subcontractor/subconsultant, please list the business name and the amount below accompanied by a separate properly executed Schedule 2.

Price or Percentage:

Remove and replace existing roof

Subcontractor 1

President Assistant Vice President

John Doe James Doe

Roofers Are Us, Inc.

SAM

PLE

Subcontractor 1

$50,385.80

Date: 6/4/2025 6/4/2025

SAMPLE OEBO LETTER OF INTENT – SCHEDULE 2*

A completed Schedule 2 is a binding document between the Prime Contractor/consultant and a Subcontractor/subconsultant (for any tier) and should be treated as such. All Subcontractors/subconsultants, including any tiered Subcontractors/ subconsultants, must properly execute this document. If a mandatory API goal applies, failure to submit a properly executed Schedule 2 will result in a determination of non-responsiveness to the solicitation. Each properly executed Schedule 2 must be submitted with the bid/proposal.

SOLICITATION/PROJECT NUMBER: 19600

SOLICITATION/PROJECT NAME: Carlin Park, Maintenance Bldg, Roofing Replacement

Date of Palm Beach County Certification (if applicable):1/1/2024

Prime Contractor: Roofers Are Us, Inc.

(Check box(s) that apply)

☒ SBE ☐ Non-SBE □ Supplier dlynch Highlight dlynch Highlight dlynch Highlight dlynch Highlight dlynch Highlight dlynch Placed Image

Placed Image

SBE PARTICIPATION – SBE Primes must document all work to be performed by their own work force on this form. Specify in detail, the scope of work to be performed or items supplied with the dollar amount and/or percentage for each work item. When applicable, identify the line item(s) associated with the service/product being supplied. SBE credit will only be given for the areas in which the SBE is certified. A detailed quote/proposal may be attached to a properly executed Schedule 2 for additional information.

The undersigned Subcontractor/subconsultant is prepared to self-perform the above-described work in conjunction with the aforementioned project at the following total price or percentage:

Print Name of Prime

By:

Authorized Signature

Print Name

Date:

Line Item

Item Description Unit Price Quantity/ Units

Contingencies/ Allowances

Total Price/Percentage

If the undersigned intends to subcontract any portion of this work to another Subcontractor/subconsultant, please list the business name and the amount below accompanied by a separate properly executed Schedule 2.

Price or Percentage:

President

John Doe

Roofers Are Us, Inc.

SAM

Prime Contractor: Roofers Are Us, Inc.

Subcontractor 2 Print Name of Subcontractor/subconsultant

By:

Authorized Signature

Jane Doe Print Name

Vice President

Subcontractor: Subcontractor 2

Date of Palm Beach County Certification (if applicable):

$35,995.05

$25,995.05

$10,0002nd Tier Subcontractor

Date: 6/4/2025 6/4/2025

SAMPLE OEBO LETTER OF INTENT – SCHEDULE 2*

A completed Schedule 2 is a binding document between the Prime Contractor/consultant and a Subcontractor/subconsultant (for any tier) and should be treated as such. All Subcontractors/subconsultants, including any tiered Subcontractors/ subconsultants, must properly execute this document. If a mandatory API goal applies, failure to submit a properly executed Schedule 2 will result in a determination of non-responsiveness to the solicitation. Each properly executed Schedule 2 must be submitted with the bid/proposal.

SOLICITATION/PROJECT NUMBER: 19600

SOLICITATION/PROJECT NAME: Carlin Park, Maintenance Bldg, Roofing Replacement

(Check box(s) that apply)

□ SBE ☒ Non-SBE □ Supplier dlynch Highlight dlynch Highlight dlynch Highlight dlynch Highlight dlynch Highlight

Placed Image

SBE PARTICIPATION – SBE Primes must document all work to be performed by their own work force on this form. Specify in detail, the scope of work to be performed or items supplied with the dollar amount and/or percentage for each work item. When applicable, identify the line item(s) associated with the service/product being supplied. SBE credit will only be given for the areas in which the SBE is certified. A detailed quote/proposal may be attached to a properly executed Schedule 2 for additional information.

The undersigned Subcontractor/subconsultant is prepared to self-perform the above-described work in conjunction with the aforementioned project at the following total price or percentage:

Print Name of Prime

Line Item

Item Description Unit Price Quantity/ Units

Contingencies/ Allowances

Total Price/Percentage

If the undersigned intends to subcontract any portion of this work to another Subcontractor/subconsultant, please list the business name and the amount below accompanied by a separate properly executed Schedule 2.

Price or Percentage:

SOLICITATION/PROJECT NAME: Carlin Park, Maintenance Bldg, Roofing Replacement

SAM

Date of Palm Beach County Certification (if applicable):

Prime Contractor: Subcontractor 2 Subcontractor: 2nd Tier Subcontractor

$10,000.00

Jude Doe

Manager

Jane Doe Print Name

Vice President

Subcontractor 2 2nd Tier Subcontractor Print Name of Subcontractor/subconsultant

(Check box(s) that apply)

□ SBE ☒ Non-SBE □ Supplier

SAMPLE OEBO LETTER OF INTENT – SCHEDULE 2*

A completed Schedule 2 is a binding document between the Prime Contractor/consultant and a Subcontractor/subconsultant (for any tier) and should be treated as such. All Subcontractors/subconsultants, including any tiered Subcontractors/ subconsultants, must properly execute this document. If a mandatory API goal applies, failure to submit a properly executed Schedule 2 will result in a determination of non-responsiveness to the solicitation. Each properly executed Schedule 2 must be submitted with the bid/proposal.

SOLICITATION/PROJECT NUMBER: 19600

Title

Date: 6/4/2025

Title

Date: 6/4/2025 dlynch Highlight dlynch Highlight dlynch Highlight dlynch Highlight

Highlight

Form Rev. 10/28/24 Attachment A for Asphalt, Demolition, Electrical, Flooring, HVAC, Low Voltage, Painting and Weatherproofing, Roofing

ATTACHMENT “A”

(for Asphalt, Demolition, Electrical, Flooring, HVAC, Low Voltage, Painting and Weatherproofing, Roofing)

AFFIRMATIVE PROCUREMENT INITIATIVES (APIs) FOR CONSTRUCTION

PROCUREMENT

The API(s) approved for this project are selected below by ☒. Fillable pdfs of all EBO forms can be found on the OEBO website at http://discover.pbcgov.org/oebo/Pages/Compliance- Programs.aspx. Also, see the EBO Ordinance and Countywide PPM CW-O-043 for further information on APIs.

X SBE Price Preference For Single Trade Construction

The work orders under this contract shall be awarded to the lowest, responsive, responsible bidder unless a certified SBE’s bid is within ten percent (10%) of the lowest non-SBE bid, in which case the award shall be made to the certified SBE bidder. Construction contracts where there are no opportunities for subcontracting (i.e.

single trade), may include a provision requiring awards of the contract to be made to the lowest responsive, responsible respondent or bidder unless a certified SBE’s bid is within ten (10) percent of the lowest non-small business bid, in which case the award shall be made to the certified small business bidder submitting the lowest responsive, responsible bid at the price that it bid.

http://discover.pbcgov.org/oebo/Pages/Compliance-Programs.aspx http://discover.pbcgov.org/oebo/Pages/Compliance-Programs.aspx

Bid Bond / Page 1 Form Rev. 6/9/25 Bid Bond - NonFederal

IFQ/B ATTACHMENT B

Return Attachment B if bid is $200,000 or more

DATE:

BID BOND

STATE OF FLORIDA

COUNTY OF PALM BEACH

KNOW ALL MEN BY THESE PRESENTS: That we, (hereinafter called "Principal"), and

(hereinafter called "Surety") are held and firmly bound unto Palm Beach County, a Political Subdivision in the State of Florida, by and through its Board of

County Commissioners, (hereinafter called "County") in the sum of

Dollars,($ ), (which sum is at least 5% of the bid price), lawful money of the United States of America, for the payment of which sum will and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly be these presents;

WHEREAS, the "Principal" contemplates submitting or has submitted a bid to the Board of County

Commissioners, Palm Beach County, Florida, for furnishing and paying for all necessary labor materials, equipment, machinery, tools, apparatus, services, all state workmen's compensation and unemployment compensation taxes incurred in the performance of the Contract, means of transportation for and complete

Construction of: (Senior Supportive Housing - Access Control & FA Replacement, P-2025-000140), in the County of Palm Beach, State of Florida; and

WHEREAS, it was a condition precedent to the submission of said bid that a certified check cashier's check, money order or bid bond in the amount of five percent (5%) of the base bid be submitted with said bid as a guarantee that the bidder would, if given a Notification from Owner, enter into a written contract with the

County, and furnish a public construction bond in an amount equal to one hundred (100%) of the total

Contract, within fourteen (14) consecutive calendar days after the County issues the Notification from

Owner.

NOW THEREFORE, THE CONDITIONS OF THIS OBLIGATION ARE SUCH that, if the bid of the "Principal" herein is accepted and said "Principal", within fourteen (14) consecutive calendar days after written notice being given of such acceptance, (i) enter into a written contract with the County and (ii) furnishes a public construction contract bond in the amount equal to one hundred percent (100%) of the total contract amount and in a form satisfactory to the County, then this obligation shall be void. If the

Principal fails to complete (i) and (ii) above, the sum herein stated shall be due and payable to the "County", and the "Surety" herein agrees to pay said sum immediately upon demand of the "County", in good and lawful money of the United States of America, as liquidated damages for failure of said "Principal".

Bid Bond Must Contain Original Signatures. No Copies Will Be Accepted.

Bid Bond / Page 2 Form Rev. 6/9/25 Bid Bond - NonFederal

PROJECT NUMBER: P-2025-000140

DATE:

IN WITNESS WHEREOF, the said as "Principal" herein, has caused these presents to be signed in its name, by its

, and attested by its under the corporate seal, and the said as "Surety" herein, has caused these presents to be signed in its name, by its

, and attested by its corporate Seal, this day of , A.D., 20 .

ATTEST:

TITLE:

(SEAL)

(Contractor Name)

(Signature)

Print Name and Title:

ATTEST:

TITLE:

(SEAL)

(Surety Name)

(Signature)

Print Name and Title:

Bid Bond Must Contain Original Signatures. No Copies Will Be Accepted.

CAPITAL IMPROVEMENTS DIVISION

IFQ/B ATTACHMENT C

PROJECT REQUIREMENTS

Annual Contract - Low Voltage

Contact: Marc Hartley, Facilities Systems Project Manager Phone: (561)233-2053 Project Title: Senior Supportive Housing - Access Control & FA Replacement Project #: P-2025-000140 Project Location: 5981 Okeechobee Blvd, West Palm Beach, FL

1. GENERAL

a. The work covered by this Request for Quote consists of the furnishing of all labor, equipment, devices, tools, materials, transportation, professional services, supervision, drawings, permitting, and all miscellaneous requirements to perform all operations necessary to accomplish the work set forth below and shall be considered part of the Scope of Work.

b. Please reference the Annual Contract – Low Voltage for additional requirements.

c. Work to be completed during the hours of 7:30 a.m. to 6:00 p.m., Monday through

Saturday.

d. Contractor shall contact the Project Manager within seventy-two (72) hours of notice to proceed to establish scheduling, etc. required for project implementation.

e. Work to be completed within thirty (30) calendar days from Notice to Proceed. Permit application, if required, is to be submitted by Contractor within five (5) days of “Notice to Proceed” and due diligence exercised to address all Building Department comments.

f. Liquidated damages will accrue in the amount of $240 per day.

g. The Contractor will provide a Certificate of Occupancy or Certificate of Completion, as appropriate, obtained from the proper Building official, prior to processing of final payment.

h. Contractor is responsible for obtaining all measurements during the site inspection.

2. SCOPE OF WORK

To provide and install a fully functional multi-tenant building access control solution and fire alarm replacement per the project requirements provided below:

Building Access Control

a. Remove and dispose of existing access control system hardware from all one hundred thirty (130) doors.

b. Provide and install a turnkey Multi-Tenant access control system, Schlage Allegion

XE360 Series Wireless Mortise Lock on all one hundred fourteen (114) tenant rooms and sixteen (16) common area doors, with compatible door wrap around.

c. Provide and install a client workstation with ability to access the Allegion ENGAGE Cloud

App, and the Schlage MT20W Enrollment Reader for staff to administer credentials to the tenants in office.

d. Provide and install a turnkey Honeywell Prowatch access control system that includes

DPS, REX, card readers, and strikes on administrative, and IDF room doors.

Fire Alarm Replacement

e. Replace existing Notifier NFW-100X control panel with a new Notifier NFW-100X control panel, with new 7AH standby batteries. See attached data sheet.

f. Replace existing Altronix NAC panel in building B, with a new Honeywell PSE-10 NAC Power Supply, with new 7AH standby batteries.

g. Provide and install Bosch B465 IP Communicator with enclosure B10R-1640-120WI, B46 annunciator, and 7AH standby battery. Connect to PBC ESS Proprietary Monitoring Station. PBC to provide data drop at IP Communicator.

h. Install thirty-two (32) System Sensor SA-WBB weatherproof back boxes for exterior horn strobes.

i. Test and inspect 100% of system and provide current NFPA72 Test and Inspection and Record of Completion forms.

j. Update existing hardcopy drawings to CAD and provide battery calculations for Fire Alarm Control Panel and two (2) NAC Power Supplies.

k. Provide fire alarm program on USB flash drive.

l. Remove existing Altronix Power Supply and Cellular Communicator and return to Palm Beach County.

3. SUBMITTALS

All submittals shall be sent to the Project Manager for approval. This includes, but is not limited to, products to be used, methods of installation and requests for information and/or clarification. All submittals must be made by the Contractor and must include all details necessary for the Project Manager and Palm Beach County to make any necessary determinations. A transmittal form must be included which clearly requests data or information and deviations from the contract requirements for which approval is being requested. Failure to provide sufficient information will result in the rejection of the submittal.

Where the specifications do not specify a brand name product or where a substitution of a product is not specifically prohibited, the Contractor shall submit their selected products for approval by the Project Manager. Such submittals shall include as much detail, and in a format, as required by the Project Manager, so as to allow the Project Manager to evaluate the proposed substitution.

4. MATERIALS

a. All material shall meet or exceed Florida Building Code and product submittals shall be reviewed and approved by the Owner’s Representative prior to ordering.

b. Materials shall be delivered in their original, unopened packages, and protected from exposure to the elements. Damaged or deteriorated materials shall not be used.

5. TEMPORARY PROTECTION

The Contractor shall protect all workers, staff and the general public from injury. The Contractor shall coordinate and schedule all work with the Project Manager.

6. PROJECT CONDITIONS

Contractor is to coordinate all space and security requirements with the Project Manager. A construction schedule shall be submitted for review and approval prior to pre-construction meeting, including a start date, substantial completion date, and work plan defining which space shall be scheduled on what day. The Contractor shall conduct all work on weekends/holidays to cause the least interference possible with the normal activities of the operations of the facility and surrounding areas. Any damage caused by Contractor (including landscaping and irrigation) shall be the responsibility of the Contractor to repair and return to its original state.

7. PREPARATION

It shall be the responsibility of the Contractor to prep the site at the construction locations.

8. EXAMINATION

Report to the Project Manager, in writing, any imperfections, unacceptable conditions and/or corrections required to be made before commencing work. Any items not identified, documented and reported to PBC in writing, will become part of the contractors’ scope. All other items identified in writing, if approved, shall result in a change order.

9. INSTALLATION

All materials shall be installed in strict accordance with Manufacturer’s written instructions and recommendations. All work shall be done in conformance with applicable Federal, State and Local codes, and established standards.

10. WARRANTY

Contractor warrants all equipment, materials and labor furnished or performed against defects in design, materials and workmanship for a period of twenty-four (24) months from substantial completion.

11. CLEAN UP

Remove all materials, tools and equipment from job site prior to the opening of the facility on Monday mornings or the mornings following a holiday. Area shall be clean and safe to walk on prior to the opening of the facility. Thoroughly clean the entire job area prior to requesting final inspection.

12. SECURITY

All bidders must have badged employees prior to commencement of work.

This project is subject to: [ ] Critical Facilities Background Check

[ ] CJI Facilities Background Check [X] No Background Check

IFQ/B ATTACHMENT D

NONGOVERNMENTAL ENTITY HUMAN TRAFFICKING AFFIDAVIT

Section 787.06(13), Florida Statutes

THIS AFFIDAVIT MUST BE SIGNED AND NOTARIZED

I, the undersigned, am an officer or representative of

(Entity) and attest that Entity does not use coercion for labor or services as defined in section

787.06, Florida Statutes.

Under penalty of perjury, I hereby declare and affirm that the above stated facts are true and correct.

(signature of officer or representative) (printed name and title of officer or representative)

State of Florida, County of Palm Beach

Sworn to and subscribed before me by means of ☐ physical presence or ☐ online notarization this, day of , by

Personally known ☐ OR produced identification ☐. Type of identification produced

NOTARY PUBLIC

My Commission Expires:

State of Florida at large

(Notary Seal)

1_P-2025-000140 INVITATION FOR QUOTE
2_Schedule 1 Revised Emergency Ordinance 2025-014 - Fillable
3_Schedule 2 Revised Emergency Ordinance 2025-014 - Fillable
SOLICITATION/PROJECT NUMBER: SOLICITATION/PROJECT NAME:
□ SBE □ Non-SBE □ Supplier Date of Palm Beach County Certification (if applicable): .
4_REVISED Emergency Ordinance SAMPLE SCHEDULE 1 & 2
Sample 2.pdf
SOLICITATION/PROJECT NUMBER: SOLICITATION/PROJECT NAME:
SOLICITATION/PROJECT NUMBER: SOLICITATION/PROJECT NAME:
SOLICITATION/PROJECT NUMBER: SOLICITATION/PROJECT NAME:
□ SBE □ Non-SBE □ Supplier Date of Palm Beach County Certification (if applicable): .
□ SBE □ Non-SBE □ Supplier Date of Palm Beach County Certification (if applicable): .
□ SBE □ Non-SBE □ Supplier Date of Palm Beach County Certification (if applicable): .
5_IFQ ATTACHMENT A - Asphalt, Demo, Elec, Floor, HVAC, Low Volt, Paint, Roof 102824
6_P-2025-000140 Attachment C-SOW
SOLICITATION/PROJECT/BID NAME: Senior Supportive Housing - Access Control & FA Replacement
SOLICITATION OPENING/SUBMITTAL DATE:
SOLICITATION/PROJECT/BID NO: P-2025-000140
COUNTY DEPARTMENT:
NAME OF PRIME RESPONDENT/BIDDER:
ADDRESS:
CONTACT PERSON:
PHONE NO:
E-MAIL:
Title:
Total Bid/Offer Price $:
Total:
Total Certified SBE Participation $:
PERCENTAGE OF WORK_1:
2:
PERCENTAGE OF WORK_2:
PERCENTAGE OF WORK_3:
PERCENTAGE OF WORK_4:
PRIME’S DOLLAR AMOUNT OR PERCENTAGE OF WORK:
Non-SBE: Off
SBE: Off
Non-SBE_1: Off
SBE_1: Off
Non-SBE_2: Off
SBE_2: Off
Non-SBE_3: Off
SBE_3: Off
Non-SBE_4: Off
SBE_4: Off
Check Box0: Off
Check Box01: Off
Subcontractor 2:
Subcontractor 3:
Subcontractor 4:
Subcontractor 1:
SOLICITATION/PROJECT NUMBER: P-2025-000140
SOLICITATION/PROJECT NAME: Senior Supportive Housing - Access Control & FA Replacement
Prime Contractor:
Subcontractor:
Print Name of Prime:
Print Name of Subcontractor/subconsultant:
Print Name:
Title_F0:
Date:
Print Name_1:
Title_1:
Date_1:
SBE_F1: Off
Non-SBE_F2: Off
Supplier: Off
Date of Palm Beach County Certification (if applicable):
The undersigned Subcontractor/subconsultant is prepared to self-perform the above-described work in conjunction with the aforementioned project:

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .