This is a Scope of Work document prepared by the County of Volusia, Florida for professional engineering design services related to the Orange Camp Road Widening project (Segment 1). The project encompasses design services for Orange Camp Road from Woodland Boulevard (US 17/92) to Kirkaldry Court, a major east-west collector roadway serving as a critical connection between Woodland Boulevard and Dr. MLK Jr. Highway and Interstate 4. The scope requires the selected firm to prepare a complete set of construction contract plans, specifications, and special provisions for a combination of roadway typical sections including a 4-lane divided urban section (Woodland Boulevard to Bentley Green Drive/Glen Eagles Drive) with two 11-foot travel lanes in each direction, 5-foot bike lanes, a 22-foot raised median, and an 8-foot to 10-foot shared-use path; a 2-lane divided urban section (Bentley Green Drive/Glen Eagles Drive to Kirkaldry Court) with similar bike and pedestrian accommodations; and a single-lane roundabout at Princeton Road/Wellington Woods Avenue with a 135-foot inscribed diameter. The project scope includes supplemental planning, roadway design, stormwater management, permitting, environmental assessments, signing and pavement markings, utility coordination with up to twelve existing utility agency owners, survey, geotechnical investigation, lighting design, and right-of-way identification and mapping services.
The roadway currently experiences traffic congestion during AM and PM peak hours in both directions, with the project designed to address capacity issues, improve safety by reducing operational conflicts, and accommodate future traffic demands generated by west Volusia County development. Stormwater management will utilize onsite wet and dry retention ponds (Ponds 2A, 2B, 2C, and Pond 3) designed in compliance with Volusia County standards, FDOT Drainage Manual, and St. Johns River Water Management District requirements. The existing right-of-way varies from 65 feet to 150 feet along the corridor, which is characterized by commercial uses at the western end and residential neighborhoods moving eastward. Both the design and construction phases are funded by Volusia County, with no response deadline, due date, or award date specified in this scope document.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 13, 2026
#5892.1 Orange Camp Road Widen Segment 1 (Woodland Blvd to Kirkaldry Court)
Introduction
Orange Camp Road is a major east-west collector roadway that serves as a connection between Woodland Boulevard (US 17/92) and Dr. MLK Jr. Highway and Interstate 4. It is considered an Access Management Class 7 facility. The posted speed limit is 35 mph along Orange Camp Road from Woodland Boulevard to S. Oak Park Drive. The posted speed limit increases to 45 mph from Oak Park Drive to S. Hill Avenue. Within the project limits, there is one traffic signal at the intersection of Orange Camp Road and Woodland Boulevard. The corridor is predominately a two-lane rural roadway with left and right turn lanes from Woodland Boulevard to Country Club Corners. From Country Club Corners, there are center left turn lanes present but, mostly a two-lane roadway facility. There are sidewalks on the north side of Orange Camp Road from the first Plaza entrance to Bentley Green Drive. The sidewalk continues from Oxford Road to Blue Lake Avenue. The existing right-of-way varies along the corridor from 65-feet to 150-feet.
The corridor is characterized by commercial uses at the west end, including the West Volusia Regional Shopping Center and Country Club Corners (Publix) Shopping Center. Moving east, there are residential properties on both sides of the roadway. Neighborhoods include Country Club Estates, Westminster Wood, Carriage Homes. Immanuel Presbyterian Church is also located along the corridor.
Due to the development of west Volusia County, Orange Camp Road is experiencing heavier traffic volumes and congestion. Presently, during AM and PM peak hours, both eastbound and westbound directions of Orange Camp Road are failing. With the increase of traffic demand created by growth and future roadway widening, a substantial need to provide additional capacity is justified.
Scope of Work
The County of Volusia is seeking the services of professional consultants to provide Professional Engineering Design Services to prepare a complete set of construction contract plans, specifications, and special provisions, if necessary, for the combination of a 4-lane divided urban, a single lane roundabout, and a 2-lane divided urban typical section with raised medians along Orange Camp Road from Woodland Boulevard (US 17/92) to Kirkaldry Court. The 4-lane urban typical section from Woodland Boulevard to Bentley Green Drive/Glen Eagles Drive will consist of two 11-foot travel lanes in each direction, a 5-foot bike lane in both directions, a 22-foot raised median, and an 8-foot to 10-foot wide concrete shared-use path on the north side (instead of the 5-foot sidewalk) where there is less right-of-way impacts and utility obstructions. The 2-lanes urban typical section from Bentley Green Drive/Glen Eagles Drive to Kirkaldry County will consist of one 11-foot travel lane in each direction, a 5-foot bike lane in both directions, a 22-foot raised median, an 8-foot to 10-foot wide concrete shared-use path on the north side, and a 5-foot concrete sidewalk on the south side. A single lane roundabout typical section is proposed at Princeton
May 13, 2026
Road/Wellington Woods Avenue with an inscribed diameter of 135-foot with 18-foot circular lanes and an 8-foot to 10-foot shared used path. The new combined typical section matches the surrounding land use, will satisfy future traffic demands, provide bike lanes and continuous concrete sidewalks, address capacity issues, and reduce operational conflicts which in turn improve safety.
A Full median opening is provided at Bentley Green Drive and S. Glen Eagles Drive. Direction median openings are provided at Oxford Road, Point Pleasant Road, S. Oake Park Drive, and Clay Mark Lane.
Stormwater management for water quality treatment and runoff attenuation will be provided using onsite wet and dry retention ponds. A Pond Siting Report was prepared sufficient for property acquisition efforts for the project. The attached Roadway Concept shown in Exhibit A proposes two wet retention ponds (Ponds 2A and 2B) and two dry retention ponds (Ponds 2C and Pond 3). The design of the drainage and stormwater management facilities will comply with the latest standards set forth by Volusia County, FDOT Drainage Manual, and the St. Johns River Water Management District (SJRWMD) Environmental Resource Permit (ERP) Manual, Volumes I and II.
In addition to serving vehicular traffic, Orange Camp Road right-of-way also accommodates various underground and overhead utilities. There are potentially twelve existing Utility Agency Owners (UAOs) located within the corridor. Utility Coordination and horizontal/vertical location of these utilities will be required.
There is existing lighting at the signalized intersection of Orange Camp Road and Woodland Boulevard.
There is no roadway lighting throughout most of Orange Camp Road. The addition of roadway lighting will be required at the roundabout at Princeton Road/Wellington Woods Avenue and the remainder of the corridor within the project limits will be reviewed during design phase.
The County intends for the selected firm to provide supplemental planning, roadway design, stormwater management, permitting, environmental assessments, signing & pavement markings, utility coordination, survey, geotechnical investigation services, lighting, public and stakeholder coordination, and identification of all right-of-way and right-of-way mapping services. The design and construction phases are funding by Volusia County.