OIAA_-_Special_Provisions_-_Ground_Power_Unit_(GPU)_Lifecycle_Replacement_R1.pdf

PDF 265 KB Posted

Attached to
Ground Power Unit (GPU) Lifecycle Replacement
Solicitation number
2025-IFB-065
Issued by
San Bernardino County, California

About this file

This document is a Special Provisions for Airport Construction file for the Ontario International Airport Authority (OIAA) concerning a Ground Power Unit (GPU) Lifecycle Replacement project in Terminals 2 and 4. The project involves construction during terminal operations, requiring careful coordination with various stakeholders including Terminal Operations, Airlines, Concessions, Transportation Security Administration (TSA), OIAA Public Safety, and Airport Police. The total project timeline is 300 calendar days, divided into 170 days for mobilization, 110 days for construction, and 20 days for demobilization. The contractor must develop detailed work plans, provide temporary barricades and signage, and ensure continuous access for emergency responders and maintenance teams.

The contract includes specific provisions for safety, utility investigation, material testing, and documentation requirements. Liquidated damages are set at $5,000 per calendar day for schedule overruns. The contractor is responsible for construction water, dust control, and maintaining airport security, with specific requirements for access routes, utility protection, and work hour limitations. Certified payroll verification is required monthly, and the contractor must provide detailed photographic documentation before and after construction. The project emphasizes safety, operational continuity, and minimal disruption to airport functions, with strict guidelines for working around existing infrastructure and maintaining terminal operations.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ground Power Unit (GPU) Lifecycle Replacement

3(c): Special Provisions for Airport Construction Page 1 of 16 Issued for Bid May 6, 2025

SPECIAL PROVISIONS FOR AIRPORT CONSTRUCTION

1. OVERVIEW. This Section provides for construction safety in an Airport environment; limitations on construction operations; minimum requirements for construction management and scheduling; and site-specific information pertaining to potential impacts on construction activities. All work shall be performed in compliance with OIAA’s Design Code and Construction Handbook and TSA Guidelines and Requirements.

2. SAFETY PLAN COMPLIANCE DOCUMENT (SPCD). The Contractor shall comply with the Pro-ject-specific Construction Safety and Phasing Plans (CSPP) included in these Specifications. Included as part of the requirements is the Safety Plan Compliance Document (SPCD), which Contractor must com-plete and submit to the Engineer for approval. (Notice to Proceed for Construction will not be issued until SPCD is approved.)

Construction of the Ground Power Unit (GPU) Lifecycle Replacement in Terminals 2 and 4 will occur dur-ing terminal operations and public occupancy of the terminal building that includes temporary and perma-nent relocation of operational functions. Accordingly, the terminal operations and the safety of the public and the terminal employees must be paramount throughout construction. The high-level project phasing diagrams shall be developed by the contractor taking into consideration the operational and logistical constraints identified by the stakeholders. Stakeholders include, but are not limited to Terminal Opera-tions, Airlines, Concessions, Transportation Security Administration (TSA), OIAA Public Safety and Air-port Police. The development of the Construction Safety and Phasing Plans requires Contractor(s) inter-face and coordination with OIAA, including but not limited to Transportation Security Administration (TSA), Airport Police, Airlines and others.

The Contractor shall provide detailed Work Plans and submittals for temporary barricades / partitions, utilities and other applicable temporary components showing paths of egress, construction details and provisions for temporary wayfinding and signage for specific areas and/or sub-phases for review and ap-proval by OIAA, OIAA Stakeholders, Fire Department, and Airport Police at least 30 days prior to date of proposed installation.

The contractor shall prepare a detailed work plan prior to starting work for review and approval. At no time shall the contractor impact more than one aircraft gate unless approved in writing by the owner

3. CONSTRUCTION SITE OFFICE. Contractor is NOT required to provide a site office for the duration of this Project.

4. LINES AND GRADES. The Contractor shall provide construction and layout staking for the Engineer to review and confirm prior to work being started. The Engineer will be given 48 hours' notice of pavement marking and electrical facility layout so it may be checked.

Contractor shall notify the Engineer immediately regarding any survey monuments, benchmarks, control points, stakes or marks, etc., that are in jeopardy of being disturbed or destroyed by construction, so that they may be relocated and perpetuated.

5. RECORD DRAWINGS. The Contractor shall maintain Record Drawings of all work continuously as the job progresses. A separate set of prints, for this purpose only, shall be kept at the job site at all times. It shall be required that these Drawings be up to date and be reviewed by the field inspector at the time each progress bill is submitted. All deviations from the Drawings, exact locations and sizes of all util-ities, mechanical and electrical lines, equipment details, and all stub outs and connections for future ex-pansion, shall be incorporated. Fees for documentation of Record Drawings shall be included in other items of work and no separate payment will be made.

3(c): Special Provisions for Airport Construction Page 2 of 16 Issued for Bid May 6, 2025

6. MATERIAL TESTING AND RETESTING. All Quality Control shall be performed by the Contractor;

acceptance testing will be performed by the Engineer as stipulated in the technical specifications. The Quality Control Testing shall include but is not limited to:

• Compaction testing for soils, aggregates, and pavements prior to acceptance testing of cores by Engineer. The Contractor is allotted one acceptance test per area per material per lot. In the event the acceptance tests do not pass, and the Engineer is required to retest the area, the cost for each retest shall be borne by the Contractor.

• Concrete strength mix design and other conformance testing required for structural Portland cement concrete.

• Electrical grounding and circuit testing.

7. TIME LIMITATIONS AND LIQUIDATED DAMAGES. The overall time of completion for this Project is 300 calendar days. Should this time schedule not be met, liquidated damages will be assessed.

• Liquidated damages shall be at $5000 per calendar day.

• “A bidder may not withdraw its bid submittals for hundred and eighty (180) days from the date bids are due, or until after a contract for the work described in these bid documents is fully executed by OIAA, whichever date is earlier.”

Contract time is divided as follows:

A. Mobilization. Notice to Proceed with Mobilization shall be given after award of Contract. Mobiliza-tion cost shall consist of obtaining all required insurance, bonds pulling and payment for all permits;

preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; preparation of a construction schedule; furnishing and erecting field offices and other facilities necessary for work on the project; The percentage allocation to the mobilization in the schedule of value shall be limited to a maximum of 4% of the total contract price. All work included in Mobilization shall be completed in 170 calendar days.

B. Construction. Notice to Proceed with construction work shall be issued at the Airport’s discretion after completion of Mobilization and approval of SPCD. All work in the Bid documents if awarded, shall be completed in 110 calendar days.

C. Demobilization. All work included in Demobilization shall be completed in 20 calendar days.

8. ACCESS AND SECURITY.

A. Contractor Access. Contractor access to the various work areas shall be via the closest access routes indicated on the Construction Phasing Drawings. Haul routes on Airport property shall be approved by the Airport. All access routes and haul roads shall be kept clean and free of debris.

Dust control shall be maintained. Where haul routes may cross active runways, taxiways, taxilanes, or aprons, radio-equipped flaggers shall be provided by the Contractor, as required, and all Contractor vehicle traffic must yield to aircraft and airport vehicles.

B. B. Emergency Responders and Maintenance: The contractor is responsible for coordinating with emergency responders and maintenance teams to ensure continuous access to all areas under construction. This includes facilitating access to utility rooms and other confined spaces within the contractor's closures for both emergency and routine maintenance.

C. Security Control.

3(c): Special Provisions for Airport Construction Page 3 of 16 Issued for Bid May 6, 2025

1) The Contractor shall be responsible for maintaining Airport security at all roads and gates designated for his use. Gates must be locked or manned by the Contractor's personnel to ensure no unauthorized access.

2) All access gates shall be kept clear of equipment and material.

3) Contractor is directed to use the following security companies for security control for work areas:

a. Prosegur (Primary) Contact Kameron Persaud at kameron.persaud@prosegur.com

b. Allied Protection Services Contact Jasmine Bennet at Jbennet@alliedprotection.com

9. WORK HOUR LIMITATIONS. The Airport’s normal work hours are from 7:00 a.m. to 4:00 p.m., PST, Monday through Friday, excluding holidays. All work performed outside of this schedule, unless already stated in this contract, shall be coordinated and approved in advance by the OIAA. At the pre-construction meeting, the Contractor shall provide a schedule of proposed work hours and days for the duration of the project to allow adequate time for OIAA and Engineering team to schedule inspection and observation efforts.

1) Unless restricted elsewhere in the contract documents, or directed by OIAA in writing, the project working hours at the existing check point areas will be limited from Midnight to 3:00 am.

2) Construction areas behind the barricade and indicated in the Contract Documents are typically available 24 hours a day, Monday through Friday, unless otherwise indicated in the Contract Documents and/or identifies specific restrictions on phasing drawings. Construction areas may be available on Saturday and Sunday if necessary for work completion, but such work must be coor-dinated and approved by OIAA.

3) Given the changing dynamics of the security/operational requirements, additional restrictions may be placed upon the Contractor prior to the start of construction. The Contractor is required to make note of all restrictive work hours indicated in the Contract Documents or discussed during the pre-construction meeting.

4) The scheduled durations for each sub-phase anticipate all tasks to be performed on a single-shift during off-peak hours only for each respective area. Off-peak hours are defined as the hours dur-ing which the passenger and the airline/OIAA personnel traffic is minimal. These hours vary be-tween various floors/areas of the building. The Contractor will not be permitted to perform the fol-lowing activities during regular day shifts, unless approved by OIAA at least three (3) weeks prior to commencement of such work activity:

a. Any work that is not contained within the limits of a phased construction zone or requiring the shutdown of any terminal systems (fire sprinklers, electrical, fire alarm, ACAMS, etc.).

b. Any work that will generate and expose the public to a high level of DUST, ODOR, VIBRATION or NOISE (such as the jack hammering, chopping/cutting of construction materi-al, sandblasting, structural steel erections, pile drilling near active gate operations/building, saw cutting, etc.).

c. Any work that will impact or interrupt airport operations or security such as work inside OIAA/Airlines offices, hold rooms and concession areas, TSA Security Screening Checkpoint (SSCP), TSA SSCP queuing area or TSA breakrooms.

d. Any work that may have a direct exposure to public areas, such as all MEP upgrade work around active TSA SSCP area, Passenger/Employee regular/ADA path.

e. An 8-hour "off-hours/overnight shift/second shift" will be allowed to the Contractor. The actual start and stop time for each second shift may have to be reviewed depending on work/operations areas basis and adjusted based on TSA, airline and operations require-ments.

10. AREA SHUTDOWN REQUEST (ASR) & UTILITY SHUT DOWN REQUEST (USR)

3(c): Special Provisions for Airport Construction Page 4 of 16 Issued for Bid May 6, 2025

a. The Contractor shall send a 30-day notification to OIAA in the form of an Area Shutdown Request or a Contractor Utility Shutdown Request ASR/USR of any change of condition to any existing security portals.

b. The ASR/USR shall be in the form of a controlled document formally transmitted to OIAA.

c. OIAA shall review the ASR/USR and contact Airport Police or affected stakeholders of the request.

d. OIAA shall setup a review of the change of condition with Airport Police and if required a field walk of the area or portal affected by OIAA and Airport Police within 5 business days.

e. Once the Airport Police have reviewed the change of condition and have determined that the

Contractor has accommodated all security requirements; Airport Police shall send notification to OIAA in the form of e-mail of acceptance and will allow the Contractor to proceed as noted or correction required.

f. During the review by Airport Police, it may be determined that a 14 business days notification be sent to TSA of the change of condition. Airport Police will require an additional 3 business days for administrative paperwork to be processed.

g. Once OIAA receives the notice from Airport Police, OIAA shall send to the Contractor notice to proceed with the change of condition in the form of an e-mail.

h. At no time shall the Contractor proceed with any work that creates a change of condition without proper authorization from OIAA or Airport Police.

i. The Contractor shall be responsible for maintaining all security requirements of the change of condition until receipt of notification or release of responsibility in writing or e- mail from OIAA.

j. The ASR/USR shall consist of a plan of the area affected by the change of condition, a barricade plan if one will be erected, start date and end date of the change of condition, a description of how the area or portal will be secured (Airport Police may require the Contractor to place Security Guards at specified areas with an approved Go List).

k. After all work has been completed that Contractor shall be required to submit another 30-day ASR/USR that is subject to the same process listed above. Activation will require following the same process.

11. STORM WATER DISCHARGE PERMIT.

A. Construction activity under this PROJECT will be subject to requirements of the State Water Re-sources Control Board (SWRCB), Division of Water Quality Order No. 2010-0014-DWG, National Pollutant Discharge Elimination System (NPDES) Construction General Permit (CGP) No.

CAS000002, Discharges of Storm Water Runoff Associated with Construction and Land Disturbance Activities. The Permit requires that a Storm Water Pollution Prevention Plan (SWPPP) be prepared and implemented during construction of this Project.

B. The Contractor shall comply with all terms and conditions of this Permit for the duration of permit coverage. The Contractor shall be held solely responsible for any sanctions, fines, penalties, or other actions taken against the OIAA as a result of the Contractor's failure to meet the terms and conditions.

C. The OIAA will submit to the SWRCB the initial Permit Registration Documents (PRD) in accordance with requirements of the CGP for the discharge of storm water from the site during the construction of the Project. Prior to commencing work, the Contractor’s Qualified SWPPP Developer (QSD) shall review the SWPPP and make any modifications required. Upon commencing work, the Contractor shall be responsible for managing the SWPPP for the duration of the Project, including revisions and updating the SWPPP via SMARTS (Storm water Multi-Application and Report Tracking System) online database as necessary and as approved by the OIAA.

D. The CONTRACTOR’s QSD shall be in charge of the SWPPP until coverage under the permit is terminated. A paper copy of the SWPPP shall be kept on file at the construction site for the duration

3(c): Special Provisions for Airport Construction Page 5 of 16 Issued for Bid May 6, 2025 of the Project. The SWPPP shall be implemented and Best Management Practices (BMPs) monitored by the Contractor’s Qualified SWPPP Practitioner (QSP) for the duration of permit coverage.

E. Post construction monitoring responsibility shall remain with the Contractor. The final Project inspection shall include verification of SWPPP compliance.

F. OIAA requires weekly inspections per Caltrans Standard Specifications Section 13-1.03C.

The BMP and Best Available Technology (BAT) measures called for in these Bid Documents and shown on the Plans shall be considered as minimum requirements. The Contractor shall comply with all BMP and BAT provisions in the Contract and shall implement additional and ongoing BMP and/or BAT measures as deemed necessary to comply with the SWPPP.

Payment for the BMPs called for on the Plans will be made under applicable pay items. The cost of SWPPP management, including revisions, all required monitoring, and meeting all reporting requirements as specified by the PRD and CGP shall be included in the bid item #3 “COMPLIANCE WITH POLLUTION, EROSION, AND SILTATION CONTROL”. Contractor shall be responsible for all electronic submittals required.

12. DUST CONTROL. Contractor must comply with NAAQS and CAAQS for the South Coast Air Basin and comply with ER4 Air Quality Requirements for the City of Ontario. Contractor is responsible for providing dust control measures to limit dust nuisance during the Project. Prevent and alleviate dust by applying water and covering active and inactive stockpiles. Apply water in the quantity, at the location, and for the purpose described or ordered. Apply water with the appropriate equipment to ensure the uniform application of water.

1) The Contractor shall be responsible for removing from the Site, demoed materials and debris result-ing from the Work. Vehicles exiting the Site shall have all the dirt clouds and mud removed from their tires prior to leaving the site.

2) The Contractor shall contain dust and remove it from the Site at intervals sufficient to prevent con-tamination outside work limits and as directed by OIAA.

3) The Contractor shall be responsible for containment of dust emission from all construction, transport, storage, or handling activities, in accordance with South Coast Air Quality Management District (SCAQMD) Rule 403: Fugitive Dust.

4) The Contractor shall be responsible for the continuous clean-up of all construction- related dirt and on all approach routes to the Site.

5) The Contractor shall post a publicly visible sign(s) with the telephone number and person to contact regarding dust complaints; this person will respond and take immediate corrective action

13. SUBMITTAL PROCEDURE. The Contractor shall prepare, review, approve, and transmit all required submittals and any necessary re-submittals. Submit originally prepared information drawn accurately to scale. Do not reproduce construction documents.

Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination. On the transmittal the Contractor shall identify any and all related submittals requiring coordination. Engineer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received. The Engineer’s review period will not begin until all related submittals are received by the Engineer.

If resubmittal is necessary, process it in the same manner as original submittal and clearly identify as a resubmittal. For resubmittal, Contractor shall reference the original submittal.

3(c): Special Provisions for Airport Construction Page 6 of 16

No extension of the Contract Time will be authorized because of the Contractor’s failure to transmit submittals enough in advance of the Work to permit processing.

Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Engineer.

d. Name and address of Contractor.

e. Name and address of subcontractor.

f. Name and address of supplier.

g. Name of manufacturer.

h. Unique identifier, including revision number. Submittals shall be numbered consecutively, and the numbering system shall be retained throughout all revisions.

i. Number and title of appropriate Specification Section.

j. Drawing number and detail references, as appropriate.

k. Other necessary identification.

l. Annotation of material details.

m. Specifically identify, by itemizing on a list on the transmittal, any deviations from the Contract

Documents.

n. Identify a list of other related submittals that require coordination.

o. Contractor’s signature.

14. CONTRACTOR’S REQUEST FOR INFORMATION. Submit a Request for Information to the Engineer when an unforeseen condition or constructability question occurs, questions regarding information contained in the Contract Documents arise, or information not found in the Contract Documents is required. Submit all RFI’s in writing to Engineer as soon as possible in accordance with the requirements in the contract documents. Submit RFI's as soon as possible and within a reasonable time frame so as not to interfere with or impede the progress of the Work.

Submit the RFI as follows:

1. RFI's shall be identified by sequential numbering starting with 001.

2. Submit a legible written request on a form approved in advance by the Engineer. Include the follow-ing information:

a. Project name, as listed on the Contract Documents, Engineer's project number, or other identify-ing number, if any.

b. Date.

c. Name, address, telephone number, and email addresses of the Contractor.

d. Number and title of affected Specification Section or Sections.

e. Drawing numbers and detail references, as appropriate.

f. Clear, concise explanation of information or clarification requested.

g. Desire response date.

RFIs from subcontractors or material suppliers shall be submitted by the Contractor. The Contractor shall review and sign all subcontractors RFI’s prior to submittal to the Engineer.

Engineer’s responses to Requests for Information shall not be construed as approvals to perform extra work or to change the requirements of the Contract Documents. If the Contractor believes that a response to an RFI may result in a change to the Contract price and/or time, the Contractor shall notify the Engineer, in writing, within two (2) days of receipt of the RFI response. If the Contractor fails to do so, the Contractor accepts the response to the RFI as Work included in the Contract Documents and waives all

3(c): Special Provisions for Airport Construction Page 7 of 16 Issued for Bid May 6, 2025 rights to additional compensation or time. If the Contractor properly notifies the Engineer that the RFI response is interpreted by the Contractor to be a changed Work direction, then the Contractor shall not proceed with the Work until the Engineer makes a finding and issues a field directive accordingly. All costs associated with such work performed by the Contractor without the proper written direction from the Engineer, Field Directive, Change Directive or Change Order, shall be to the account of the Contractor and may be subject to rework at the Contractor’s expense.

15. CONSTRUCTION WATER. The source of construction water for the Project shall be coordinated by the Contractor. The Contractor shall pay water and meter fees and make all necessary arrangements with appropriate local utility or OIAA to secure construction water for the duration of the Contract, if necessary.

No direct payment will be made for this work. The Contractor shall include all costs associated with construction water in the price of the work.

16. UTILITY INVESTIGATION AND SAFETY REQUIREMENTS. The following companies are believed to have utility and other facilities present within the project area. As part of site investigation of the project, bidders shall contact the below listed companies and ascertain to the bidder’s satisfaction the extent and presence of facilities which may affect the contract operations. By submission of a bid, the bidder warrants such contact has been made and the bidder is familiar with all utilities and non-highway facilities which may affect the work.

COMPANY/CONTACT TITLE/AGENCY PHONE

Dennis Anderson ONT Director of Operations (909) 215-5612 Ricardo Martorana ONT Director Of Maintenance (909) 544.5243 John Hall AvAirPros Services-ONT-TEC (909) 390-8900 Jose Najera AvAirPros Services-ONT-TEC (909) 390-8901 Stephanie Sosa ONT Operations (TBI) (909) 214-7892

Certain underground facilities exist that may require special precautions to protect the health, safety and welfare of workmen and of the public. Facilities requiring special precautions include, but are not limited to: conductors of petroleum products, oxygen, chlorine, and toxic or flammable gases; natural gas in pipelines greater than 6 inches in diameter or pipelines operating at pressures greater than 60 psi (gauge); underground electric supply system conductors or cables, with potential to ground of more than 300 volts, either directly buried or in duct or conduit which do not have concentric grounded conductors or other effectively grounded metal shields or sheaths.

All utilities encountered along the line of the Work shall be maintained continuously in service during all the operations under the Contract, unless otherwise agreed to by the utility and OIAA. All valves, switches, vaults, and meters shall be maintained readily accessible for emergency shutoff. Where protection is required to ensure support of existing utilities, the Contractor shall, unless otherwise provided, furnish and place the necessary protection at its expense.

At least two working days prior to beginning excavation, Contractor shall notify 811 (Dig-Alert). The Contractor shall contact utility providers after the I.D. number is obtained from Dig-Alert but not less than fourteen (14) days before any excavation Work is started, to mark or identify existing utilities. If the utility is owned by the City of Ontario, a confirmation number indicating that Ontario has been notified shall be obtained by USA and/or the Contractor from the appropriate City Departments.

You will be required to work around public utility facilities and other improvements that are to remain in place within the construction area, or that are to be relocated, and relocation operations have not been completed. You will be liable to owners of such facilities and improvements for any damage or interference with services resulting from his operations.

3(c): Special Provisions for Airport Construction Page 8 of 16 Issued for Bid May 6, 2025

You must determine the exact location of underground facilities and improvements within the construction area before using equipment that may damage such facilities or interfere with the services.

Other forces may be engaged in moving or removing utility facilities or other improvements or maintaining services of utilities and you shall cooperate with such forces and conduct operations in such a manner as to avoid any unnecessary delay or hindrance to the work being performed by such other forces.

Main or trunk line facilities for the purposes of Government Code 4215 shall mean only the primary or principal transmission facilities conveying energy, information, material or product through the construction project site to or from a substantial number of users on the far side of the project from the source of the utility. More than one main or trunk line facility of the same type may be present within the project area. Any other utility facilities or related appurtenances not a main or trunk line, are laterals, particularly where installed to distribute or supply utility services to property abutting the project site, whether such service line or lateral serves one or more abutting property owners, or other users.

You shall infer the presence of underground service laterals and appurtenances from the presence of any visible facilities, including but not necessarily limited to, buildings, meters, valve covers, manholes and junction boxes, whether or not main or trunk lines of the same type are shown on the plans.

You are advised that utility and non-highway facilities, including but not necessarily limited to main or trunk lines, which do not directly affect the immediate work (i.e.: excavation or trench areas) are not necessarily shown on the plans, whether or not such lines may be present within the site. The absence or presence on the plans of such facilities that do not directly affect the immediate work shall not relieve you of your obligation for independent investigation to determine facilities which may affect the work.

For the purposes of Government Code 4215 and this contract, the “site of the construction project” with respect to main or trunk line facilities shall consist only of those areas actually trenched or cut where soil 30 inches below existing grade is disturbed. The phrase “identified...in the plans and specifications” shall mean “identified in the plans and specifications as they relate to areas to actually be trenched or cut, where soil 30 inches below the existing grade is disturbed.”

Contractor shall dewater existing utility structures as needed for utility investigations and/or completion of the work, including existing electrical and communications structures. Dewatering shall be completed in accordance with state and local requirements, and the environmental requirements of these contract documents.

In case of damage, which in the opinion of OIAA threatens the safety of persons or property, the Contractor shall immediately make all repairs necessary for removal of the hazard. Should the Contractor fail to take prompt action to this end, OIAA has the option to remove any hazard resulting from damages caused by the Contractor without waiving any other rights OIAA may have, and costs will be charged to the Contractor.

All materials, labor, supervision and incidentals necessary to construct protections as detailed on the plans or as needed for Contractor’s operations will be considered incidental to the related bid items in the project.

17. CERTIFIED PAYROLL VERIFICATION

The Contractor shall provide a monthly, digital submittal to the Engineer the following items for the Contractor and all Sub-Contractors (paper copies must be supplied on request):

a. Fringe Benefits statement for the contractor and all subcontractors.

b. All weekly and bi-weekly payroll with a signed Statement of Conformance, with 4(a) or appropriate section check-marked.

3(c): Special Provisions for Airport Construction Page 9 of 16 Issued for Bid May 6, 2025

c. For any week in which work was not performed, a dated and signed Statement of Non- Performance (SNP). An SNP for an entire month is acceptable as long as the dates provided are consecutive.

d. A copy of the Department of Industrial Relations (DIR) e-submittal.

For any corrections made as a result of Engineer’s verification or corrections made by the Contractor, a copy of the corrected payroll and/or Fringe Benefit statement and proof of payment to any effected individual (check-copy or other approved method). A revised, corrected DIR e-submittal is also required.

There is no Method of Measurement or Basis of Payment Associated with this item. All costs shall be included in other items as appropriate.

18. STATE CONTRACT ACT NOT APPLICABLE. This contract is not governed by the provisions of the State Contract Act. The adoption and use of the Standard Specifications in the performance of the work called for in this contract and incorporation by reference of language of provisions contained in the said Act shall not be construed as an election by the OIAA to proceed under Section 20396 of the Public Contract Code. Only language of the said Act specifically incorporated by reference shall be included in this contract.

19. REMOVAL OF ASBESTOS AND HAZARDOUS SUBSTANCES. When the Contractor encounters material not shown on the Plans or indicated in the Specifications, and the Contractor reasonably believes that such material is asbestos, as defined in Health and Safety Code section 25914.1, or a hazardous substance which must be removed or remediated by a contractor who has passed an approved hazardous substance removal certification examination in accordance with Business and Professions Code section 7058.7, and the asbestos or hazardous substance has not been rendered harmless, the Contractor may continue to work in unaffected areas reasonably believed to be safe, and shall immediately cease work in the affected area and submit a written report of the condition to the Engineer.

In accordance with Section 25914.1 of the Health and Safety Code, all such removal of asbestos or hazardous substances including any exploratory work to identify and determine the extent of such asbestos or hazardous substance will be performed by separate contract.

If delay of work in the area delays the current controlling operation, the delay will be considered a right of way delay, and the Contractor will be compensated for such delay as provided in Section 8-1.09, “Right of Way Delays,” of the Standard Specifications.

20. ADDITIONAL REQUIRED ENVIRONMENTAL MEASURES. This project will not require biological monitoring.

21. MATERIALS FURNISHED BY THE OIAA. Upon receiving material furnished by OIAA for storage or installation in the Work, the Contractor shall give a signed receipt to the Engineer for the material delivered.

Thereafter the Contractor shall be responsible for the care and necessary replacement of such material if damaged. If, as determined by the Engineer, the material is not adequately protected by the Contractor, such material may be protected by OIAA and the cost thereof charged to the Contractor or deducted from any payment due. Upon receipt of such material, the Contractor shall inspect it, and should any damage, defects, or missing equipment or parts be found, the Contractor shall immediately notify the Engineer in writing. By failing to notify the Engineer, it shall be deemed that the Contractor has accepted such material as being free from said damage, defects, or missing equipment or parts, except for latent defects.

22. PHOTOGRAPHIC DOCUMENTATION. Before starting construction, Contractor shall take photographs of the Project Site and surrounding properties, including existing items to remain, items to be salvaged, items to be demolished, haul routes, laydown areas, and other areas that could be affected by construction. The

3(c): Special Provisions for Airport Construction Page 10 of 16 Issued for Bid May 6, 2025 entire site should be documented, including adjacent areas to constructed. Include a sufficient number of additional wide-angle photographs to determine the general locations of items when correlated between the Construction Drawings and the item-specific photographs.

For final completion, take photographs of the project for submission as part of the final documents. Contractor shall assume all areas previously photographed shall be photographed, and any new appurtenances (vaults, lights, inlets, etc.) shall be photographed as well.

Submittal shall be digital; physical prints are not required. Costs shall be included in Mobilization / Demobili-zation.

The following information is supplemental from FAA General Provisions. (FAA does not permit any revisions to the AC 150/5370-10H standards. Additional information relevant to this project has been incorporated below).

23. DIVISION III, SECTION 10 DEFINITIONS OF TERMS

A. Liquidated Damages Supplement: The amount prescribed in the Specifications, pursuant to the authority of the Government Code Section 53069.85, to be paid to the Owner or to be deducted from any payments due or to become due the Contractor for each day’s delay in completing the whole or any specified portion of the work beyond the time allowed in the Specifications.

B. Lump Sum Supplement: A term used to describe a Contract item, which means the total payment or price of the item, including all labor, materials, equipment, incidentals, profit and overhead, and for which a schedule of values is to be provided upon request.

24. DIVISION III, SECTION 30 AWARD AND EXECUTION OF CONTRACT SUPPLEMENT

A. Award of Contract Supplement: Project will be awarded to the lowest responsible bidder. The lowest bid shall be the lowest total of the bid prices on the base contract and those additive or deductive items that were specifically identified in the bid solicitation as being used for the purpose of determining the lowest bid price.

Owner has the right, at their discretion, to award a contract for the base bid and any number of alternates or combination of alternates that fit within the funds available for the project. Owner, at their discretion has the right to not award a contract for alternates that exceed the funding available.

Owner has option to not award a contract for the project without reason.

B. Verbal agreements Supplement: No verbal agreement or conversation with any officer, agent, or employee of Owner, either before, during or after the execution of the Contract, shall affect or modify any of the terms or obligations contained in the Contract Documents, nor shall such verbal agreement or conversation entitle Contractor to any additional payment whatsoever under the terms of the Contract.

25. DIVISION III, SECTION 50 CONTROL OF WORK

A. Authority of the Engineer Supplement: The Engineer may observe, at their own discretion the Contractor’s methods, plant, equipment and appurtenances and may order the work stopped when necessary to prevent its improper execution; may reject any work and materials which in his opinion does not conform to the requirements of the Contract; shall decide all questions which may arise as to the obligation of the Contractor to do any particular work or to furnish any particular materials or as to the reasonable value of any additional work or materials required by the Engineer, or as to the deductions to be made from the Contract price for the work specified herein by reason of any work

3(c): Special Provisions for Airport Construction Page 11 of 16 Issued for Bid May 6, 2025 or materials directed by the Engineer to be omitted. All instructions, rulings and decision of the Engineer shall be made promptly and shall be in writing if so requested by the Contractor, and all such instructions, rulings, and decisions shall be final and binding.

In carrying out any of the above provisions or in exercising any power or authority granted to him by the Contract Documents, there shall be no liability upon the Engineer or his authorized assistants, either personally or as an official of the Owner, it being understood that in such matters the Engineer acts as an agent and representative of the Owner.

Nothing in this section or any other contract documents provision is intended to authorize Engineer to make any decision or give any approval that any applicable law requires be made by the OIAA Commission or other governmental official.

26. DIVISION III, SECTION 60 CONTROL OF MATERIALS

A. Better Material or Process Supplement: In the event the Contractor furnishes a material, pro-cess or an article better than that specified, any difference in cost of such material, process or article so furnished shall be borne by the Contractor.

B. Shop Drawings and Submittals Supplement: The Contractor, at his own expense, shall furnish for the approval of Engineer any and all shop drawings and other submittals required by the Specifi-cations, or that may be requested by the Engineer, for any and all materials the Contractor proposes to use.

Shop drawings and submittals shall be submitted in quadruplicate and shall be marked with the name of the Project and the name of the Contractor.

C. Materials List Supplement: The Contractor shall submit a complete list of all manufactured materials and equipment which he proposes to incorporate into the Project to the Engineer for approval before placing his order for such materials or equipment. If the materials or equipment vary in any way from what was specified or shown on the Plans, specific mention of the variation shall be made in the letter of transmittal.

D. Guarantee of Workmanship and Materials and Date of Acceptance Supplement: Besides guarantees required elsewhere, Contractor shall and does hereby guarantee all workmanship and materials for a period of one year, except as otherwise required in the Contract for a longer period, from and after the date of acceptance of the Work and recordation of Notice of Completion by Owner and shall repair or replace any or all workmanship and materials, together with any other work which may be displaced in so doing, that, in the opinion of the Owner, is or becomes defective during the period of said guarantee without expense whatsoever to Owner.

E. Form of Guarantees Supplement: Guarantees in the form of written warranty shall be supplied on the Contractor's own letterhead as follows:

WARRANTY FOR:

We hereby warrant that the_____________________________ has been installed in accordance with the drawings and Specifications and that the work as installed will fulfill the requirements of the warranty included in the Specifications. We agree to repair or replace any or all of our work together with any other adjacent work which may be displaced by so doing, that may prove to be defective in its workmanship or materials for the period of one year from date of acceptance of the above-mentioned structure by the Owner, ordinary wear and tear, and unusual abuse or neglect excepted.

In the event of our failure to comply with the above-mentioned conditions within seven (7) days after being notified in writing we, collectively or separately, do hereby authorize the Owner to

3(c): Special Provisions for Airport Construction Page 12 of 16 Issued for Bid May 6, 2025 proceed to have said defects repaired and made good at our expense, and we will honor and pay the cost and charges therefore on demand.

Signed:________________________________________________

27. DIVISION III, SECTION 70 LEGAL REGULATIONS AND RESPONSIBILITY TO PUBLIC

A. Safety Supplement: The Engineer has not been retained or compensated to provide design and construction review services relating to the Contractor's safety precautions or to means, methods, techniques, sequences or procedures required for the Contractor to perform his work.

The Contractor will be solely and completely responsible for conditions of the work site, including safety of all persons and property during performance of the work. This requirement will apply continuously and not be limited to normal working hours. Safety provisions shall conform to all applicable state, OIAA, and local laws, ordinances, and codes.

28. DIVISION III, SECTION 90 MEASUREMENT AND PAYMENT

A. Acceptance and Final Payment Supplement: OIAA may withhold funds or, because of subsequently discovered facts, nullify the whole or any part of any certificate for payment, to such extent as may be necessary to protect the OIAA from loss, due to causes including but not limited to the following:

1) Defective work not remedied;

2) Claims filed or information reasonably indicating probable filing of claims;

3) Failure of Contractor to make payment due for materials and/or labor;

4) Information causing reasonable doubt that the contract can be completed for any unpaid balance;

5) Damages to another Contractor;

6) Liquidated Damages.

When any and all of such causes are removed, certificates shall be issued for amount withheld.

B. Direct Costs Supplement:

1) Labor

a. Cost of labor shall include any employer payments to or on behalf of workers for health, welfare, pension, vacation, and similar purposes. Labor rates will not be recognized when in excess of those prevailing in the locality at the time the work is being performed. No labor charges will be accepted for supervision. The costs for all superintendents and fore-persons are included in the markups established by the Contract Documents. The only exception to this will be working forepersons who perform actual manual labor or the extra work. No labor charges will be accepted for engineering or proposal preparation. These costs are included in the markups established by the Contract Documents.

b. Overtime and premium time pricing will only be allowed for labor which is performed after normal working hours at the Engineer’s direction and written approval. If the Contractor chooses to work overtime without the Engineer’s written approval, then overtime rates and premiums shall not apply.

2) Material

a. The actual cost to the Contractor for the materials directly required for the performance of the force account work. Such costs of materials may include the cost of transportation. No delivery charge will be allowed unless the delivery is specifically for the changed work.

3(c): Special Provisions for Airport Construction Page 13 of 16

b. If a trade discount by an actual supplier is available to the Contractor, it shall be credited to the OIAA. If the materials are obtained from a supplier or source owned wholly by or in part by the Contractor, payment thereof will not exceed the current wholesale price for the materials. The term "trade discount" includes the concept of cash discounting.

c. If, in the opinion of the Engineer, the cost of the materials is excessive or if the Contractor fails to furnish satisfactory evidence of a cost to the Contractor from the actual supplier thereof, then, in either case, the cost of materials shall be deemed to be the lowest current wholesale price at which similar materials are available in the quantities required. The OIAA reserves the right to furnish such materials as it deems advisable and the Contractor shall have no claims for cost or profits on materials furnished by the OIAA.

3) Equipment

a. The actual cost to the Contractor for the use of equipment directly required in the per-formance of the force account work. In computing the hourly rental of equipment any time less than thirty (30) minutes shall be considered one-half hour. No payment will be made for time while equipment is inoperative due to breakdown or for non-working days. In addition, the rental time shall omit the time required to move the equipment to the work, for rental of such equipment, and to return it to the source. No mobilization or demobilization will be allowed for equipment already on site. If such equipment is not moved by its own power, then loading and transportation costs will be paid in lieu of rental time thereof. How-ever, neither moving time nor loading and transportation costs will be paid if the equipment is used on the Project in any way other than upon the changed work.

b. Individual pieces of equipment having a replacement value of $1,000 or less shall be considered to be small tools or small equipment and no payment will be made thereof unless it is a direct expense for the changed work and is used for no other purpose.

c. The rental rate for equipment will not exceed that as recommended by the lower of the rental rates established by Caltrans or as contained in the Association of Equipment Distributors (AED) book.

d. The amount to be paid to the Contractor for the use of equipment as set forth above shall constitute full compensation to the Contractor for all costs incidental to the use of the equipment.

C. Cost Markups Supplement:

1) For work performed by the Contractor, a 15 percent markup for overhead and profit will be added to the direct costs (as defined in Section 90-5) of the force account work.

2) For work performed by a Subcontractor a 20 percent markup for overhead and profit will be added to the direct costs (as defined in Section 90-5) of the force account work. (Suggested breakdown: 15 percent to the Subcontractor, 5 percent to the Contractor.)

3) For work performed by a Sub-subcontractor (any tier) a 25 percent markup for overhead and profit will be added to the direct costs (as defined in Section 90-5) of the force account work.

(Suggested breakdown: 15 percent to the Sub-subcontractor, 5 percent to the Subcontractor and 5 percent to the Contractor.)

4) In no case will the total markups be greater than 25 percent of the direct cost notwithstanding the number of Contract tier actually existing.

3(c): Special Provisions for Airport Construction Page 14 of 16 Issued for Bid May 6, 2025

5) On proposals covering both increases and decreases in the amount of the Contract sum, over-head, profit and commission shall be allowed on the net increase only as determined above.

Where the difference is a deletion, no percentage for overhead, profit or commission shall be allowed.

6) The markup percentage shall be full compensation for profit, small tools, cleanup, engineering, supervision, warranties, job site overhead and home office overhead. No markup will be allowed on taxes, insurance and bonds.

END OF SPECIAL PROVISIONS FOR AIRPORT CONSTRUCTION