This is a Bid Form for the Ontario International Airport Authority (OIAA) for the Ground Power Unit (GPU) Lifecycle Replacement project. The bid document outlines a project requiring contractors to furnish labor, materials, equipment, and supervision to complete the work. The project timeline includes 170 days for mobilization, either 70 or 110 days for installation (depending on base or alternate bid), and 20 days for close-out. The bid remains valid for 180 calendar days after the bid opening, with the expectation that the contractor will execute the required contract and bonds within 15 days of award.
The bid form emphasizes that quantities in the Schedule of Work and Prices are approximate and used for bid comparison purposes. The lowest Base Bid will determine the lowest responsible bidder for contract award. Bidders must submit a price for each item in the attached schedule, with understanding that any discrepancies in unit prices or total costs will be corrected according to the specified governing rules. The contractor must hold a valid contractor's license, and all work must conform to the Contract Documents, with any conflicts resolved by the order of precedence established in those documents.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid and Schedule of Work and Prices
BID
BIDDER NAME:
DATE: , 2025
TO THE CHIEF EXECUTIVE OFFICER OF THE OIAA:
The undersigned has carefully examined the plans and specifications for the Ground Power Unit (GPU) Lifecycle Replacement project, and has personally visited the site of the work, and has become familiar with the conditions. The undersigned hereby proposes to furnish all the labor, materials, equipment, supervision, and incidentals to perform all work required and to complete the Work strictly in accordance with the Contract Documents, including any addenda, within Mobilization 170 Days Installation base bid 70 Days Close-Out 20 Days for base bid or Mobilization 170 Days Installation base bid 110 Days Close-Out 20 Days thats for all add alt bids from the date of the Notice to Proceed for the sums and unit prices stated in the Schedule of Work and Prices.
The undersigned has submitted a price on each item in the attached Schedule of Work and Prices, and has checked carefully all figures inserted in the Schedule and understands that the OIAA will not be responsible for any errors or omissions by the undersigned in this bid.
The undersigned understands that the quantities indicated in the Schedule of Work and Prices are approximate only and not guaranteed to be correct. It is understood that they are the quantities, however, which will be used for the purpose of comparing bids. It is also understood that in the case the amount listed in the Unit Price Total is not the correct sum of the Unit Price multiplied by the Quantity, the Unit Price amount shall govern and the Unit Price Total shall be corrected along with the Total Cost amount accordingly. It is understood that if the Total Cost amount listed is not the correct sum of the Unit Prices Totals, the Unit Price Totals shall govern and the Total Cost shall be corrected accordingly. It is understood that the lowest Base Bid shall be the basis to determine the lowest responsible bidder for award of the Contract.
The undersigned has also attached hereto
This Bid shall remain valid for one hundred eighty (180) calendar days after the bid opening. The undersigned agrees that in case of default in executing the required contract and necessary bonds within fifteen (15) days after award is made, the proceeds of the check or bond accompanying this bid shall become the property of the OIAA.
All work done and materials furnished shall conform to the Contract Documents. In the event of any conflict, the order of precedence established in the Contract Documents shall prevail.
Bid and Schedule of Work and Prices
BID
Contractor's License No.
Expiration Date of Contractor's License
The representations of this Contractor's License are made under penalty of perjury.
Name of Individual, Firm or Corporation
Address
(Sign here if individual) Signature
(Sign here if partnership) Signature
Members of Firm: Name (or Corporation)
Address
Name
Address
Name
Address
(Sign here if Corporation) Signature