PAVING IDIQ PPI Log

PPI #

SECTION OF RFP PARAGRAPH

REFERENCE

DRAWING

NUMBER (IF

APPLIC)

QUESTION

ANSWER ATTACHMENT

Yes or No

AMENDMENT #

N/A

The SF 1442 states that this solicitation is 100% set-aside for small business, and yet on page 65 of the RFP, Section 00150 – Instructions to Offerors, it states in the first sentence that the procurement is solicited on an unrestricted basis with full and open competition. Which is correct?

This procurement is a 100% Small Business Set-aside.

No

Also on page 65 of the RFP, Section 00150 – Instructions to Offerors, it states that the proposal due date is 03 June 2014, while the SF 1442 says the bid date is 05 June 2014. Which is correct?

Proposal due date is being extended to 17 June 2014.

SF 1442

Block 3 and Block 13A

Solicitation was just posted on 14 May. However, SF 1442 says date issued is 6 May and bid date is 5 Jun.

Will bid date be extended to make up for the lost 8 days in receipt of the RFP.

Proposal due date is being extended to 17 June 2014.

Page 57 of 68, 3.(a)vi

What constitutes proof of Reps/Certs completed in SAM? A copy of our SAM information?

Per this section offerors must submit: Proof of the Offeror’s filled out Representations and Certifications and Active and Inactive Exclusions from the System for Award Management (SAM).

Page 62 of 68, Factor 4 Safety

Reference Exhibit 3, Safety Data Sheet. Block 7 of Exhibit 3 states That the Safety Narrative cannot exceed 2 pages. Is it correct to assume that the 2 pages is for Block 7 and not the entire Safety Data Sheet?

That is correct Safety Narrative cannot exceed 2 pages in length.

Exhibit 6, ELINS

IDIQ Paving

CLINS

Exhibit 6, ELINS

IDIQ Paving

CLINS

The schedule of indefinite quantity work, Exhibit 6, is locked.

Certain columns need to be unlocked for entry of prices and other.

Only the Unit Pricing Cells will remain unlocked on Exhibit 6.