This document is Standard Form 30 (SF 30), Amendment 0004 to solicitation N6817126RN006, issued by NAVSUP FLC Sigonella Naples Office on 13 July 2026. The amendment responds to six Pre-Proposal Inquiries (PPIs) regarding maintenance and preservation work items for naval facilities.
The amendment clarifies several technical requirements: Work Items 110 and 115 previously referenced non-existent Work Item 134, which contractors should disregard; Enclosure 2.2.1 containing the List of GPETE Equipment is attached to support pricing for WI 492 calibration work; Johnson Controls is the recommended OEM for WI 801 AC Plant Servicing, though local European OEM representatives are acceptable; IAF (Installing Activity Furnished) materials identified in work items are the contractor's responsibility to provide; and WI 168 painting requirements regarding weather conditions and tenting are at contractor discretion for compliance. The amendment maintains all other existing terms and conditions unchanged. Offerors must acknowledge receipt of this amendment prior to the solicitation deadline using one of three specified methods: completing items 8 and 15 and returning copies, acknowledging receipt on each offer copy, or submitting separate written communication referencing the solicitation and amendment numbers.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
Created On:
13 Jul 2026, 12:40 PM Greenwich Mean Time
J 1 2
2. AMENDMENT/MODIFICATION NUMBER
0004 13 Jul 2026 See Continuation Sheet N68171
NAVSUP FLC SIGONELLA NAPLES OFFICE
NAVAL REGIONAL CONTRACTING CEN DET, PSC 817 BOX 50
FPO, AE 09622-0050
UNITED STATES
Anna Guarino, Email: anna.guarino4.ln@us.navy.mil Telephone: 0815683573 SCD: PAS:
N6817126RN006
18 Jun 2026
See Section G - Contract Administration Data
See Schedule
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Block 14 (Description of Amendment/Modification): The purpose of this amendment is to respond to six (6) additional Pre-Proposal Inquiries (PPIs):
PPI#8: Work Item (WI) 110 para 5.5. is referring to WI 134. WI 134 is not included in received J-2 MTA work package - please advise will we receive WI 134.
Response: There is no WI 0134. Disregard Paragraph 5.5 of WI 0110 " Weather Deck Preservation".
PPI # 9: Work Item (WI) 0115 para 5.5. is referring to WI 134. WI 134 is not included in received J-2 MTA work package - please advise will we receive WI 134.
Response: There is no WI 0134. Disregard paragraph 5.5 of the WI 0115 "Trunk 4-143-1 T Preservation".
PPI #10: WI 492 para 3.1.2. Quantity to be calibrated is referring to enclosure 2.2.1. This enclosure is blank without any indication of how many devices and from which manufacturer they are. Please provide info how to price this Work Item .
Response: Enclosure 2.2.1 List of GPETE Equipment, is attached to this amendment.
PPI#11: WI 801 is it possible to have local OEM from Europe and not from JOHNSON CONTROLS NAVY SYSTEMS US ?
Response: As per 7.1 of WI 0801 " Contractor to provide an OEM authorized technical representative to Groom A/C Plants listed in Paragraph
3.1.3. Johnson Controls is the recommended OEM for performance of WI 0801 AC Plant Servicing.
PPI#12: We have noticed that numerous drawings which are received as part of listed reference in various work items are containing acronym IAF.
Expression IAF is related to various equipment and material. In received WI 0001 under definitions there is no any explanation what does this mean therefore please provide answer and guidance what to do with it and who is responsible to procure this equipment and material?
Response: IAF stands for Installing Activity Furnished. Contractor is responsible for providing material identified as IAF.
PPI#13: WI 168 para 7.13.10. stated weather conditions are not easy to achieve on open spaces during period of performance in this part of the year. MSC sometimes requested tenting or better to say encapsulation of entire area so that the proper painting conditions would be timely obtained and maintained through entire painting process. What is the MSC's position now on whether a tent is needed for these painting activities having in mind that as stated in WI overcoating intervals are critical to the application of non-skid ?
Response: The requirements of 7.13.10 are clear. It is at the contractor discretion on how to meet the requirement.
All other terms and conditions remain unchanged.