0021_A_LCC-SWI-CLEAN AND GAS FREE TANKS VOIDS COFFERDAMS AND SPACES Rev B.docx
DOCX document 53 KB Posted
- Attached to
- USS MTW FY27 MID-TERM AVAILABILITY (MTA)
- Solicitation number
- N6817126RN006
About this file
This is a Statement of Work (SOW) for cleaning, gas-freeing, and maintaining miscellaneous tanks, voids, cofferdams, and spaces aboard the USS MT. WHITNEY (LCC-20) during a mid-term availability. The work is categorized as a "Category A" general services requirement under contract N00000-00-X-0000, with an availability start date of May 16, 2026.
The contractor is responsible for opening, cleaning, and gas-freeing 20 specified tanks including fuel oil service tanks, fuel oil storage tanks, clean seawater ballast tanks, a forepeak tank, and fresh water/technical water tanks with capacities ranging from 4,502 to 85,204 gallons. Key requirements include: establishing a clean storage facility with capacity for approximately 100,000 gallons of fuel oil, 25,000 gallons of JP-5, and 2,000 gallons of lube oil; removing tank contents and temporarily storing reusable fuels and lubricating oils; providing ventilation, lighting, and safety equipment during tank operations; and completing all cleaning and gas-freeing of 20 specified tanks within 14 days of availability start. The contractor must employ a naval architect or structural engineer to plan tank unloading procedures, obtain samples of all liquids prior to transfer and storage, conduct final closeout inspections with the government's Overhaul and Modernization Team (OMT) Representative, repair any coating damage caused by work, and submit weekly progress reports including a detailed tank work matrix tracking opening dates, cleaning completion, gas-free certification receipt, structural surveys, testing completion, and related repair status for each tank or space.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT
This item describes the requirements for the contractor to open, clean, gas-free, maintain, and close miscellaneous tanks, voids, cofferdams, and spaces. Storage of re-usable fuel and lube oils is also required.
REFERENCES/ENCLOSURES
References
1.1.1 MSC Drawing No. 845-4458934 GENERAL ARRANGEMENT DRAWING, USS MT. WHITNEY (LCC)
1.1.2 MSC Drawing No. 845-7490232, USS MT. WHITNEY, Trim & Stability Booklet Enclosures
1.1.3 USS MT. WHITNEY (LCC) List of Applicable Tanks, Voids and Cofferdams to be Opened during Current Availability
2.0 ITEM LOCATION/DESCRIPTION
2.1 Location/Quantity: See Enclosure 2.2.1
3.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None
4.0 NOTES
4.1 The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with all applicable GTR requirements.
4.2 The contractor and all subcontractors, regardless of tier are advised to review other work items under this contract to determine their effect on the work required under this work item.
4.3 The definitions of many terms used in this work item are found in Work Item 001.
4.4 In the event that any tank contents are deemed to be hazardous wastes in accordance with federal, state and local (CONUS) or international (OCONUS) standards, the costs for handling and disposal of those wastes shall be covered under Work Item 023 of this work package.
5.0 QUALITY ASSURANCE REQUIREMENTS
5.1 Tank coating system conditions shall be identified and documented by the contractor during tank surveys. ABS surveyor shall receive a copy of contractor’s reports.
6.0 STATEMENT OF WORK REQUIRED
6.1 It is the contractor’s responsibility to analyze and properly plan tank unloading procedures to ensure that no undue stresses are imposed on the vessel structure. Ship’s force and OMT REP will assist contractor with ship loading documents and software. The contractor shall utilize the services of a naval architect or structural engineer to support this planning. The contractor shall provide their tank unloading plan to the OMT REP at least two business days prior to starting this work to permit review and approval by MSC naval architect.
6.2 Contractor and ship’s force shall on arrival at the contractor’s facility take, record, and verify soundings of all tanks listed in Enclosure 2.2.1, using References 2.1.1 and 2.1.2 as guidance. The Chief Engineer shall review and endorse all soundings taken/recorded. Submit copy of endorsed record to the OMT REP.
6.3 Provide a clean storage facility with a capacity of approximately 100,000 gal of fuel oil, 25,000 gal of JP-5 and 2,000 gal of lube oil. Contractor designated storage facility shall be inspected by the OMT REP for cleanliness and acceptability prior to any transferring of fuel oil and lube oil. Prior to off-loading liquids, samples shall be taken by the contractor of each of the tanks to be moved to temporary storage. These samples shall be turned over to the Chief Engineer. Each sample bottle shall be labeled with tank taken from, contents, and date taken. Any visual indications of contamination shall be brought to the attention of the OMT REP immediately. Upon completion of transferring of liquids, the contractor, in conjunction with ship's force, shall validate quantities at the storage facility.
6.3.1 In the event that contamination is suspected, a change order will be issued to the contractor to have a laboratory analysis conducted on the sample.
6.3.2 Provide unit pricing for each facility listed in 7.3.3 Storage facility must be available throughout the duration of the entire availability including any extensions.
6.3.3
| Requirement |
| Unit/Quantity |
| Price |
| Clean Storage Facility for Fuel Oil |
| 1 Lot/ 2,381 Barrels |
| Clean Storage Facility for Lube Oil |
| 1 Lot/ 595 Barrels |
| Clean Storage Facility for JP-5 |
| 1 Lot/ 48 Barrels |
6.4 Removals: The ship will pump down tanks to low suction, either to other tanks onboard or to shore storage facilities. In the event that the tank contents are being moved off the ship, the contractor shall provide support to the vessel, including all hoses and manpower on the shore side to accomplish this removal. Contractor shall be responsible to provide all pumps, hoses, fittings and personnel to safely remove all remaining tank contents as identified in Enclosure 2.2.1. Applicable federal, state, local or international procedures for transferring fuel and lube oils over water shall be followed by the contractor. Contents to be temporarily stored are indicated in the enclosure. All other liquids shall be disposed of in accordance with local, state, federal and/or international regulations. In some states, the presence of oil in the wash water may deem the mixture to be hazardous waste. When pricing this item, the contractor shall assume that oil is present in the tank wash water. The cost for disposal of the mixture shall be included in the price quote regardless of whether or not, due to the presence of oil, the wash water is deemed hazardous waste or non-hazardous waste. If the mixture is determined to be hazardous waste due to some contaminant other than oil, the procedures outlined in Work Item 023 shall be used for the identification, handling and disposal. The costs for removal are still part of this work item (021). All other costs for offload and disposal shall be captured in this work item.
6.5 When directed by the OMT REP, return all fuel oil and lube oil to the vessel. Prior to returning of liquids, the contractor, together with ship's force, shall take samples of all stored liquids. These samples shall be turned over to the Chief Engineer. Each sample bottle shall be labeled with temporary storage tank taken from, contents, and date taken. Any visual indications of contamination shall be brought to the attention of the OMT REP immediately.
6.6 Accomplish the following for each tank/space listed in Enclosure 2.2.1:
6.6.1 Open manholes and erect/maintain safety guards over openings.
6.6.2 Temporarily provide blowers and ventilate tanks and spaces, inclusive of confined areas around manhole covers.
a. Ventilation of the tanks shall be accomplished so as to prevent tank fumes from exhausting in the interior compartments of the ship.
6.6.3 Temporarily provide and maintain, as required, tank lamping/lighting. Lighting shall be explosion proof, safety type lights.
6.7 Clean and Gas Free tanks and spaces listed in Enclosure 2.2.1. Cleaning shall completely remove all traces of dirt, sludge, debris and liquids. All tanks and spaces shall be presented in a clean and dry condition and shall be ready to be certified and maintained safe for men/safe for hot work. The provision of gas free certificates is covered under Work Item 020 of this work package.
6.7.1 Where a battery of tanks is designated for cleaning and gas freeing, all interior spaces in way of same, such as cofferdams, voids, bilges, bilge wells and other spaces, even if not specifically mentioned, shall be considered as being included as spaces to be cleaned and gas freed.
6.7.2 For all tanks and spaces indicated in enclosure 2.2.1, air vents, sounding tubes, filling and suction lines and other appurtenances shall be included for cleaning and gas freeing. Secondary manhole covers for each tank shall also be opened.
6.7.3 Post original gas free certification at each tank/space location. Certificate shall be mounted directly at the tank/space manhole entrance.
6.7.4 Post copy of gas free certificates at the designated gangway access to the vessel. Certifications posted at gangway shall be in a protective weather/waterproof enclosure that is accessible and visible.
6.8 Surveys and testing requirements for these tanks shall be addressed in other work items in this work package.
6.9 At the conclusion of all required work, conduct a final closeout inspection for each tank/space listed in enclosure 2.2.1 with the OMT REP. No tank shall be closed until a final inspection is accomplished with the OMT REP in attendance.
6.9.1 Contractor is responsible for repairing all tank coating damage caused by work in this solicitation work package. During close out inspection, if coatings are found damaged by contractor’s work, contractor shall repair damaged areas prior to final close out of tank/space, at contractor’s expense. Damaged coatings shall be repaired in accordance with MSC paint system and the paint representative’s recommendations.
6.9.2 Ensure all blowers, lighting, staging, tools, and miscellaneous equipment are removed prior to the final inspection. Any staging necessary for OMT REP close out inspection shall be removed just prior to final acceptance close out of tank/space.
6.9.3 Present tank in final clean condition. No dirt, dust, debris or liquids shall be allowed. Any tank or space failing the close out inspection, shall be re-cleaned until passing OMT REP inspection (repeated cleanings and inspections will be at contractor expense, and may become subject to issuance of a QDR).
6.10 Upon acceptance of final closeout inspection and by direction of the OMT REP, reinstall manhole covers using new gaskets, grommets, and wicking. Submit a condition found report for any missing or damaged fasteners or hardware.
6.11 The following tanks and spaces, included in Enclosure 2.2.1, shall be opened, cleaned and prepared for gas free certification within 14 days of the shipyard availability start:
6.11.1 Tank 9-FP-0-W Forepeak Tank
6.11.2 Tank 9-40-1-W Clean SW Ballast Tank
6.11.3 Tank 9-40-2-W Clean SW Ballast Tank
6.11.4 Tank 9-52-0-W Clean SW Ballast Tank
6.11.5 Tank 9-52-1-W Clean SW Ballast Tank
6.11.6 Tank 9-52-2-W Clean SW Ballast Tank
6.11.7 Tank 9-64-1-W Clean SW Ballast Tank
6.11.8 Tank 9-64-2-W Clean SW Ballast Tank
6.11.9 Tank 9-98-1-W Clean SW Ballast Tank
6.11.10 Tank 9-98-2-W Clean SW Ballast Tank
6.11.11 Tank 9-86-5-W FW Ballast Tank
6.11.12 Tank 8-86-6-W FW Ballast Tank
6.11.13 9-104—1-W Technical Water Tank
6.11.14 9-104-2-W Technical Water Tank
6.11.15 Tank 7-82-1-F Fuel Oil Service Tank
6.11.16 Tank 9-86-1-F Fuel Oil Storage Tank
6.11.17 Tank 9-86-2-F Fuel Oil Storage Tank
6.11.18 Tank 9-104-1-J JP-5 Storage Tank
6.11.19 Tank 9-104-4-J JP-5 Storage Tank
7.11.20 Tank 9-104-2-J JP-5 Service Tank
NOTE: FUEL OIL SERVIE AND STORAGE TANKS WILL BE PUMPED DOWN
6.12 Required deliverable report: Contractor shall create, maintain, update, and submit weekly during the progress meeting, a tank/space work matrix. This matrix shall contain the following information:
6.12.1 Tank/Space Name
6.12.2 Tank/Space Location Designation
6.12.3 Date Tank/Space Opened
6.12.4 Date Gas Free Cleaning Started
6.12.5 Date Gas Free Cleaning Completed
6.12.6 Date Gas Free Certificate Received
6.12.7 Date ABS Initial Structural Survey Complete
6.12.8 Date Air Test/Hydro Test Completed
6.12.9 Date Final Tank/Space Cleaning Started
6.12.10 Date Final Tank/Space Cleaning Completed
6.12.11 Date Tank/Space Final Close
6.12.12 Tank/Space Related Repair Status: List major job sequence within a tank/space followed by date start and date completed (such as below):
a. Access Cuts -> date removed/date installed
b. Blasting -> date start/date complete
c. Painting -> date start/date complete
d. Related work items internal repairs (pipe, valve, structure, etc.)
e. Related work items external repairs (welding, UT’s, zincs, other structural related; etc.)
f. Fluids added/removed from tank/space (pot water chlorination; Undocking stability; fuels/oils; etc.)
Paint all disturbed surfaces to match surroundings USS Mt Whitney
( LCC-20 )
| GENERAL SERVICES AND REQUIREMENTS |
| CONTRACT NO. N00000-00-X-0000 |
| ITEM NO. 0021 |
| CATEGORY "A" |
| 2026-05-16 |
| LCC-SWI-CLEAN AND GAS FREE TANKS VOIDS COFFERDAMS AND SPACES |
| Simpson, Eric H. |
GENERAL REQUIREMENTS: None additional 0021 - 20 Enclosure 2.2.1 - USNS MT. WHITNEY (LCC) List of Applicable Tanks, Voids and Cofferdams to be Opened during Current Availability
(DFM) Fuel Oil Service Tanks
| Description Tank Number |
| Tank Frame Location |
| 95% Capacity |
(gals) Area (sqft) Arrival Condition (Ltons)
| 7-82-1-F |
| 82-86 |
| 8,445 |
MT
| 9-104-2-J |
| 109-111 |
| 4,502 |
MT
| 9-104-1-J |
| 109-121 |
| 35,524 |
MT
| 9-104-4-J |
| 109-121 |
| 29,471 |
MT
(DFM) Fuel Oil Storage Tanks
| Description Tank Number |
| Tank Frame Location |
| 95% Capacity |
(gals) Area (sqft) Arrival Condition (Ltons)
| 9-86-1-F |
| 86-98 |
| 41,340 |
MT
| 9-86-2-F |
| 86-98 |
| 40,458 |
MT
(SW) Clean Ballast Tank
| Description Tank Number |
| Tank Frame Location |
| 100% Capacity |
(gals) Area (sqft) Arrival Condition (Ltons)
| 9-40-1W |
| 40-52 |
| 27,156 |
MT
| 9-40-2W |
| 40-52 |
| 27,156 |
| 9-52-0W |
| 52-56 |
| 44,043 |
MT
| 9-52-1W |
| 52-64 |
| 65,782 |
| 9-52-2W |
| 52-64 |
| 65,782 |
| 9-64-1W |
| 64-76 |
| 85,204 |
| 9-64-2W |
| 64-76 |
| 85,204 |
| 9-98-1W |
| 98-104 |
| 37,942 |
MT
| 9-98-2W |
| 98-109 |
| 75,833 |
MT
(SW) Forepeak Tank
| Description Tank Number |
| Tank Frame Location |
| 100% Capacity |
(gals) Area (sqft) Arrival Condition (Ltons)
| 9-FP-0W |
| FP-8 |
| 56,412 |
(PW) Fresh Water Ballast Tanks
| Description Tank Number |
| Tank Frame Location |
| 100% Capacity |
(gals) Area (sqft) Arrival Condition (Ltons)
| 9-86-5W |
| 86-98 |
| 32,307 |
| 9-86-6W |
| 86-98 |
| 32,307 |
| 9-104-1 |
| 104-109 |
| 37,564 (Technical Water Tank) |
| 9-104-2 |
| 104-109 |
| 37,564 (Technical Water Tank) |