N6339421R0016_Conformed Copy_Amendment 5.pdf

PDF 2 MB Posted

Attached to
System Module and Standard Module cable set Federal contract opportunity
Solicitation number
N6339421R0016
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This is a solicitation for the fabrication, assembly, testing and delivery of Vertical Launching System module cables. Key details include the requirement for System Module and Standard Module cable sets in accordance with supplied specifications and drawings. Interested offerors may request the technical drawings package and must submit any questions to the Contract Specialist and Contracting Officer by a specified date two weeks prior to the proposal due date. The soliciting agency is the Department of the Navy Naval Sea Systems Command. The incumbent is not specified. Pricing terms and the period of performance are not outlined in this document.

View the file

Other files for this federal contract opportunity

Other files attached to System Module and Standard Module cable set, newest first.
File Type Posted
N6339421R0016_Conformed Copy_Amendment 8.pdf PDF
N6339421R0016_Summary of Changes Amendment 8.pdf PDF
N6339421R0016_Summary of Changes__Amendment 7.pdf PDF
N6339421R0016_Conformed Copy_Amendment 7.pdf PDF
N6339421R0016_Summary of Changes__Amendment 6.pdf PDF
N6339421R0016_Conformed Copy_Amendment 6.pdf PDF
N6339421R0016_Summary of Changes_Amendment 5.pdf PDF
N6339421R0016_Conformed Copy_Amendment 4.pdf PDF
N6339421R0016_Summary of Changes__Amendment 4.pdf PDF
N6339421R0016_Conformed Copy_Amendment 3.pdf PDF
N6339421R0016_Summary of Changes__Amendment 3.pdf PDF
N6339421R0016_Conformed Copy_Amendment 2.pdf PDF
N6339421R0016_Summary of Changes__Amendment 2.pdf PDF
N6339421R0016_J-3_Material Part List_Enclosure.xlsx XLSX spreadsheet
N6339421R0016_Summary of Changes__Amendment 1.pdf PDF
N6339421R0016_Conformed Copy_Amendment 1.pdf PDF
N6339421R0016_J-S-2_Pricing_Spreadsheet.xlsx XLSX spreadsheet
N6339421R0016_J-4_GFP Attachment.xlsx XLSX spreadsheet
N6339421R0016_Exhibit_(A)_CDRLS.pdf PDF
N6339421R0016_VLS MODULE CABLES_SOLICITATION.pdf PDF
N6339421R0016_J-3_Material Part List_Enclosure.pdf PDF
N6339421R0016_J-S-1_Past Performance Questionnaire.doc DOC document
N6339421R0016_J-2_GFI_Attachment.xlsx XLSX spreadsheet
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 05:00 PM local time 13 Dec 2021

X

A

X B

X C X D

EX

X

G

F 114 - 121

122 - 133

X H 134

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA

FAR (48 CFR) 53.214(c)

DX-A3 1 139

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N63394 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 0 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

N/A conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

1 - 7

8 - 52

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

53 - 73

74 - 76

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

77 - 82

83 - 91 X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 92 - 99 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 100 - 101 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIO NS AND INSTRUCTIO NS

PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS

102 - 112

PART II - CO NTRACT CLAUSES

NAVAL SURFACE WARFARE CENTER

4363 MISSILE WAY,

PORT HUENEME CA 93043-4307

(805) 228-8287

805-228-6299FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

09 Sep 2021

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N6339421R0016

Section SF 30 - BLOCK 14 CONTINUATION PAGE

AMENDMENT 2

QUESTIONS & ANSWERS

1. The CLIN 0006/0006AA “Module Cable Set” & CLIN 0011/0011AA “Module Deck & Hatch Cable Set” both have the same 8407428-29 p/n even though each set (37 vs 10) is made up of different p/ns. If not, please advise correct p/n of the kit.

Answer: Review the Material List Enclosure for the kit contents and part numbers listed.

2. Is NSWC-PHD working this solicitation as a WINNER TAKE ALL in terms of all CLINs /SLINS 0001

THRU 0038 as 1 bid for 1 supplier to win? This would be very hard to do otherwise since many of the

“SETS” share common p/ns and common materials with other “SETS”. The “sets” are the 13 different named “sets” in the NSWC files provided. Of course, we will price all 13 “sets” as requested but in the end it is considered an entire packaged bid.

Answer: The Government's intent to award one contract for CLINs/SLINs 0001 - 0038.

3. Regarding progress payments, if a contractor does not have a DCMA/DCAA approved accounting system and is only seeking financial support for purchases of materials only (given the large $$$ amount of material and that cables have to be delivered as kits), can this SOL allow for progress payments of materials at cost w/o any mark ups? A contractor can provide detailed excel files as materials are received monthly and copies of supplier invoices and pictorial evidence of material on site (if DCMA does not do a physical verification). Since this is a small business set aside, the financial commitment to pay for materials so far in advance of delivery necessitates this request.

Answer: See amendment 1; It is the Government's intent to award with progress payments terms and conditions. Only vendors with approved accounting systems may receive Progress Payments. If the awardee doesn't have an approved accounting system, the awardee can work with DCAA to obtain approval.

4. Given the inflationary period we are in and especially the large fluctuations in raw materials such as copper

(for all the wires), how is NSWC expecting to have FFP bids for the option years which if the 4th year is exercised, can be 45 months from 1/5/2022 plus the time to do the work which could be another year, which could be 5 years from 1/22? Can we provide a possible % increase based on the rise in raw materials?

Answer: It is the vendor's responsibility to price their options CLINs.

5. Can NSWC please reconsider the very short due date extension of 2 weeks for the new date of 10/26? This is a massive RFQ and the time to collect costs, estimate pricing, do the write up of the proposal notes, is substantial. Can this be extended to COB Monday 11/15/21?

Answer: The Government grants a two-week extension for final proposal submission from 26 October

2021 to 09 November 2021.

AMENDMENT 3

1. Continuing delays in receiving quotes from a number of critical sole source and dedicated VLS component suppliers including on the wire due to issues with TE and their QPL status. Also the amount of time to complete the requirements of reports and data for the bid is a large effort. I am sorry but this size of the bid warrants a larger extension / original realistic lead time to submit a compliant and complete proposal given the $ value.

Can this quote be extended until 12/13/21?

Answer: The Government does not concur with the extension.

AMENDMENT 4

1. Will your team reconsider that an extension will be granted to mid December.

Answer: Extension granted until 13 December 2021.

AMENDMENT 5

1. Could the government please provide the VLS Configuration Management Plan, TL130-AD-PLN-010-

VLS for the subject RFP?

Answer: TL130-AD-PLN-010-VLS, Configuration Management Plan document is attached.

2. Since we do not know how long it will take for NSWC to review and present the answers via a MOD P5 to the RFQ, we ask that the current due date of 12/13/21 per Amend P4 be extended further until 01/07/22 given the upcoming holidays. Many of these questions are critical to the costs associated with determining prices to submit to the customer. Once answers are provided then time will be needed to then incorporate the data and the applicable scope of work into our costs.

Answer: Due to upcoming requirement, the Government cannot extend any longer. The solicitation will close on 12/13/2021.

3. For the option CLINs that have ranges of quantities, does NSWC-PHD want 1 single price for the range

(example if 1-4 kits, does NSWC want $1 regardless of qty or can we provide a quote for different prices depending on the qtys withing that range?

Answer: The pricing should be provided base on the range of quantities as indicated for stepladder pricing.

4. For the option CLINs, will each kit be funded/awarded at the same time in each option Year or will the Kits be independently awarded with only some be exercised at all or at different times during the Option Year?

For example, in Option Year 1 would all 9 Sets be awarded? Is PHD’s funding a package where the Option year is the entire group of cable sets for that particular year or is each Set its own customer? We know that the Base Year all Sets listed will be awarded together.

Answer: The Government reserves the right to exercise option CLINs that will satisfy the Government's requirement at the time of option exercising.

5. For the UID requirement for all CDRLs, does PHD want each assembly within the cable set to have its own

UID AND a UID for the entire Kit? How will that work if the Cable set can be over 100 boxes? Does the customer want the pallet to have the cable Set UID on it while each pn box have their own UID per p/n?

Please clarify. If a UID for the cable set, how will that work w/o a part number for the set since all are words as the description? Per SOW 12.1- please confirm that PHD Will assign serial #s rather than the contractor. Which serial #s? Of each cable assembly and or of the Cable Sets? Will each cable set have to be serialized? For example, if the BY, there are 32 of the Module Cable Set, will PHD want each Cable Set to have their own unique serial # and that serial # will in turn be tied to each of cables with the kit and their respective serial #s?

Answer: UID labels are required for cables that have that requirement on the drawing. The UID label is applied directly to the cable IAW the drawing. Kits and boxes do not get UIDs. The Navy will not assign

Serial Numbers.

6. Regarding SOW 4.1 ATE- what is the type of test equipment that PHD will provide? Name of the manufacturer and system name of equipment? How many ATEs will be provided? Will interface test cables be provided to connect the cable assembly under test to the ATE? Will ATE be provided for both the copper wire cables and a different piece of ATE for the fiber optic cables? Can the contractor make a request to NSWC-PHD for which ATE cable tester is purchased? Vendor already makes a large portion of the se p/ns and has a dedicated testers (ATE) and interface test harnesses made. If we are provided the same mfr / system of the ATE we use then we can interchange the test cables and programs rather than having different mfrs of the ATE and possibly different interface connectors.

Answer: If the vendor can meet the test requirements IAW the TDP using their test equipment and test cables, they are free to use those assets for ATE.

7. Regarding SOW 4.2 FAI. Will PHD require delivery of the actual FA unit with a AS9102 FA report for approval? If so, will there be any type of fit/electrical tests at PHD? Or will PHD only require delivery of the FA report?

Answer: FAI is a contractor activity, the Government reserves the right to witness any inspection and review the FAI Report.

8. Regarding SOW 7.0 GSI. Does “GSI at the convenience of the government” mean that the contract will have DCMA as the administrator so the entire contract is subject to DCMA source or will NSWC-PHD choose on its own to invoke its right to GSI on a case by case basis? The SOL has section E-246-W007 on page 75- how does this apply if it is not clear if GSI will be required all the time versus “at the convenience of the government”.

Answer: The Government intends to delegate the administration of this contract to DCMA.

9. Regarding SOW 8.0 Environmental Testing. Please clarify how this will be done by the USG for cable assemblies?

Answer: The vendor shall follow the requirements as specified by the TDP, if applicable.

10. Regarding SOW 12.3 for Substitute sources of supply. Please clarify if a drawing is “Suggested sources” only, the contractor must get permission from PHD to use another suggested source.

Answer: Yes, qualification plan must be submitted to the US Navy, Approved by the US Navy and the results of the qualification must meet the requirements. When all requirements are met, the US Navy will add that source as a suggested source of supply.

11. Regarding SOW 16.1 PRR. The CLINs 0034 ,0035,0036, 0037 & 0038 are or a quantity of 1 but this 16.1 section of the SOW states PRRs will be done quarterly. Is this per each Base year and Option? Is the “1” to cover all PRRs on a quarterly basis per BY and option Year?

Answer: The CLINs covers BY and each option year. PRR will occur quarterly until the delivery is completed.

12. A) With regards to progress payments, where is the SOL is this identified? We only see it discussed in

Amendment 0001:

Answer: It is the Government's intent to award with progress payments terms and conditions. Therefore, the solicitation includes progress payment clauses: 52.232-16 (Dev) Progress Payments (DEVIATION 2020-

O0010) JUN 2020, 252.232-7004 (Dev) DoD Progress Payment Rates (DEVIATION 2020-O0010) MAR

2020, and 252.232-7016. Only vendors with approved accounting systems may receive Progress Payments.

B) If a contractor obtains DCAA approval for a cost accounting system AFTER being issued the contract for this solicitation, can the contractor be able to request progress payments for the contract for work already performed as well as for the duration of the contract?

Answer: The contract will be modified to add Progress Payment after DCAA approval. DCMA will administer the Progress Payment.

13. Where / When did NSWC provide these 3 documents? We do not see them in the CD sent to us with all the drawings? Can these 3 documents please be sent? 1) TL130-AD-PLN-010-VLS--Configuration

Management Program Plan for the MK 41 VLS, Volume 1, Equipment (Hardware) Configuration

Management. 2) MK 41 VLS Standing Instruction 94-1F, Attachment 6-- Marking for Technical Data, 3)

TL130-AD-PLN-030-VLS-- Firmware Configuration Management.

Answer: TL130-AD-PLN-010, TL130-AD-PLN-030, and MK41 VLS Standing Instructions 94-1F are attached.

14. Please confirm that someone from NSWC fills out this J-S-1 Past Performance Questionnaire since it states

“FROM ASSESSOR INFO”. How do we have responsibility to have this submitted when the bid is due if we are not the ones to fill it out? Where are the instructions for where / to whom we send this to?

Answer: It is the responsibility of the vendor to send the request to whoever the vendor would like to provide the assessment.

15. As we are working on the Proposal content, question concerning Section 2.3 for "Disposition of Technician

Data Package (TDP) and Technical Drawings. This is a complicated request since vendor already has the vast majority of the TDP from previous contracts and data provided by NSWC and the USG. We cannot destroy what we already had prior to this RFQ so destroying the CD provided would only cover this TDP yet we already have most of the documents since we have been many of these p/ns before and have all the component drawings, PLs, NORs on file. Please advise how we are to “destroy” a duplicate copy of what we have already been provided and the requested certification statement. I am not sure if this would be taking an exception to this RFP flow down. Please provide direction.

Answer: The vendor can send the CD back to the Government for disposal. The vendor is under no obligation as a result of this solicitation to delete data/drawings that it already has in its possession.

16. N6339421R0016 AMD 4, Page 122 of 136, Section L, Section 2.3, Disposition of TDP and Technical

Drawings states that Offerors should not transfer the data by any means to a third party. In this case, can an

Offeror provide access to the TDP to its subcontractor’s with whom it is seeking quotes? And if that is not possible, does this mean every subcontractor of every Prime Offeror has to request a TDP CD from PHD?

Answer: Due to the distribution statement on the TDP, contractor can share the drawings with vendors who has JCP.

AMENDMENT 1

1. Question: We are asking if this public file “N6339421R0016 J-3 Material Part List Enclosure” that we downloaded, be sent as an excel file and not a PDF?

Answer: Material Part List Enclosure excel file will be provided.

2. Question: Our question is in regards to past performance. The Solicitation states the following “In addition to references for the prime, the Offeror shall also submit one Past Performance Reference for each proposed subcontract valued at 10% or more of their total proposed price.” What if our company does not have contracts of equal value to the proposed requirement? However, we have performed the same requirements but in a much lower scale.

Answer: The relevancy evaluation considers many factors or elements. The dollar value or size of previous contracts is only one factor.

3. Question: Expected Award date for BASE YEAR contract once the bid closes on 10/12/21?

Answer: See Page 83 of 132. For proposal purposes the estimated date of task order award is 05 January

2022.

4. Question: What does “AOE” for Delivery Info section starting on page 76 of SOL?

Answer: After Option Exercised (AOE). Used in Line Item Detail to define a delivery date for an option line item.

5. Question: Does the SOL allow for upfront $ at time of contract award and or performance based payments for material receipts by a supplier on a monthly basis? If not, can it, given that this is for small businesses and the $ value will be very large and that the cables are to be delivered in kits, which makes for longer time to collect payment.

Answer: It is the Government's intent to award with progress payments terms and conditions. Therefore, the solicitation includes progress payment clauses: 52.232-16 (Dev) Progress Payments (DEVIATION 2020-

O0010) JUN 2020, 252.232-7004 (Dev) DoD Progress Payment Rates (DEVIATION 2020-O0010) MAR

2020, and 252.232-7016. Only vendors with approved accounting systems may receive Progress Payments.

6. Question: Can the due date be extended given how little time is being offered to review so much data?

Answer: The Government grants a two-week extension for final proposal submission from 12 October

2021 to 26 October 2021.

7. Question: Per earlier request for an extension for the submittal date, is this being considered? 4 weeks is not enough time for the scope of work for costing, quoting plus the time for the substantial write ups for proposal notes.

Answer: The Government grants a two-week extension for final proposal submission from 12 October

2021 to 26 October 2021.

Section B - Supplies or Services and Prices

NOTE A,B,C

NOTE A

Stepladder Pricing. Stepladder pricing is utilized in this solicitation to provide Offerors an opportunity to propose different pricing for separate quantity ranges within applicable Contract Line Items (CLINs). Price evaluation of step ladder CLINs will utilize a randomly selected quantity. Notwithstanding the option to propose different unit pricing for different quantities, the Offeror may propose the same unit price for all quantities.

For all option CLINs with stepladder pricing, the Government may unilaterally exercise a given line item more than once. Option CLINs with stepladder pricing may be exercised until the total quantity purchased equals the maximum quantity listed for that option CLIN in Section B.

(End of Text)

NOTE B

The following table provides the approximate timeframes that the CLINs and associated SLINs, where applicable, will be awarded or exercised. This information is provided for planning purposes only and is subject to change depending on need and funding availability.

CLINS and Award/Option Exercise Timeframe

Deliverable At Award/

Year 1

Year 1 Year 2 Year 3 Year 4

System Module Cable

Set

CLIN 0001 CLIN 0002 CLIN 0003 CLIN 0004 CLIN 0005

Module Cable Set CLIN 0006 CLIN 0007 CLIN 0008 CLIN 0009 CLIN 0010

Module Deck &

Hatch Cable Set

CLIN 0011 CLIN 0012 CLIN 0013 CLIN 0014 CLIN 0015

Ancillary Cables Sets CLIN 0016 CLIN 0017 CLIN 0018 CLIN 0019 CLIN 0020

Extender Cable Set CLIN 0021 CLIN 0022 CLIN 0023 CLIN 0024 CLIN 0025

B/L VII DDG AMOD

Cable Set

CLIN 0026 CLIN 0027 CLIN 0028 CLIN 0029 CLIN 0030

Inco/Depot W21

Cable Assembly Set

CLIN 0031 CLIN 0032 CLIN 0033

Production Readiness

Review

CLIN 0034 CLIN 0035 CLIN 0036 CLIN 0037 CLIN 0038

Physical

Configuration Audit

CLIN 0039

Data

Deliverables/CDRLs

CLIN 0040

*CLINs 0001, 0006, 0011, 0016, 0021, 0026, 0031, and 0034 will be funded at award.

NOTE C

MAXIMUM QUANTITY MULTIPLE OPTION QUANTITY CLINS

CLINs, SLINs or other provisions in this contract set forth option quantities associated with option exercise periods.

Offerors should use those estimated quantities for planning purposes and in the preparation of its proposals including its price proposal. After award of the contract the Government may need to move quantity between these option CLINs. The contract resulting from this solicitation will have a maximum dollar value or a maximum number of units that may be purchased. The Government, may, through contract modification, move quantities of items labor or estimated costs between the option CLINs as long as the contract maximum is not exceeded.

If pricing varies by option exercise period the pricing applicable is the pricing applicable when the option is exercised. For example, items moved from option year four to option year one will be payable at the rates applicable to option year one.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

System Module Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of System Module

Cables Set IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

NET AMT

0001AA 6 Set System Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

PSC CD: 5999

OPTION System Module Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of System Module

0002AA Set OPTION System Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

STEPLADDER PRICING

STEPLADDER NAME ITEM NO FROM QUANTITY TO QUANTITY UNIT PRICE

System Module Cable SLIN

0002AA, MAX 14

0002AA 2.00 3.00

4.00 8.00

9.00 14.00

OPTION System Module Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of System Module

0003AA Set OPTION System Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

System Module Cable Set, SLIN 0003AA, MAX 14

0003AA 2.00 3.00

4.00 8.00

9.00 14.00

OPTION System Module Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of System Module

0004AA Set OPTION System Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

System Module Cables Set

SLIN 0004AA, MAX 11

0004AA 2.00 3.00

4.00 7.00

8.00 11.00

OPTION System Module Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of System Module

0005AA Set OPTION System Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

System Module Cable Set

SLIN 0005AA, MAX 15

0005AA 2.00 4.00

5.00 9.00

10.00 15.00

Module Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of Module Cables Set

IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

0006AA 32 Set Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION Module Cable Set

FFP

0007AA Set OPTION Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

Module Cable Set SLIN

0007AA, MAX 56

0007AA 12.00 23.00

24.00 41.00

42.00 56.00

OPTION Module Cable Set

FFP

0008AA Set OPTION Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0008AA, MAX 68

0008AA 12.00 23.00

24.00 53.00

54.00 68.00

OPTION Module Cable Set

FFP

0009AA Set OPTION Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0009AA, MAX 60

0009AA 12.00 23.00

42.00 60.00

OPTION Module Cable Set

FFP

0010AA Set OPTION Module Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0010AA, MAX 84

0010AA 12.00 35.00

36.00 59.00

60.00 84.00

Module Deck and Hatch Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of Module Deck and

Hatch Cable Set IAW the SOW and TDP. Refer to CDRLs for item and data

0011AA 32 Set Module Deck and Hatch Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION Module Deck and Hatch Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of Module Deck and

0012AA Set OPTION Module Deck and Hatch Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

Module Deck and Hatch Set

SLIN 0012AA, MAX 56

0012AA 12.00 23.00

42.00 56.00

OPTION Module Deck and Hatch Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of Module Deck and

0013AA Set OPTION Module Deck and Hatch Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

Module Deck and Hatch Cable

Set SLIN 0013AA, MAX 68

0013AA 12.00 23.00

24.00 53.00

54.00 68.00

OPTION Module Deck and Hatch Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of Module Deck and

0014AA Set OPTION Module Deck and Hatch Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

Set SLIN 0014AA, MAX 60

0014AA 12.00 23.00

42.00 60.00

OPTION Module Deck and Hatch Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of Module Deck and

0015AA Set OPTION Module Deck and Hatch Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

Set SLIN 0015AA, MAX 84

0015AA 12.00 35.00

36.00 59.00

60.00 84.00

Ancillary Cables Sets

FFP

Production Phase: Manufacture, assembly, test and delivery of MK 41 MOD 36

Ancillary Cable Set,Germany Ancillary Cable Set,4-Module Ancillary Cable Set and 2-Module Ancillary Cable Set IAW the SOW and TDP. Refer to CDRLs for item and data requirements.

0016AA 2 Set MK 41 MOD 36 Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0016AB 1 Set Germany Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0016AC 2 Set 4-Module Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0016AD 5 Set 2-Module Ancillary Cable MK 6 Update Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0016AE 3 Set 4-Module Ancillary Cable MK 6 Update Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION Ancillary Cables Sets

FFP

Production Phase: Manufacture, assembly, test and delivery of MK 41 MOD 36

Ancillary Cable Set,Germany Ancillary Cable Set,4-Module Ancillary Cable Set

0017AA 1 Set OPTION MK 41 MOD 47 Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0017AB 2 Set OPTION MK 41 MOD 47 Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0017AC Set OPTION 4-Module Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

4-Module Ancillary Cable Set

SLIN 0017AC, MAX 4

0017AC 1.00 2.00

3.00 4.00

0017AD 4 Set OPTION 2-Module Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION MK 41 MOD 47 Ancillary Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of MK 41 MOD 36

Ancillary Cable Set,Germany Ancillary Cable Set,4-Module Ancillary Cable Set

0018AA Set OPTION MK 41 MOD 47 Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

MK 41 MOD 47 Ancillary

Cable Set SLIN 0018AA, MAX 4

0018AA 1.00 2.00

0018AB Set OPTION 4-Module Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

4-Module Ancillary Cable Set

SLIN 0018AB, MAX 5

0018AB 1.00 2.00

3.00 5.00

OPTION MK 41 MOD 47 Ancillary Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of MK 41 MOD 36

Ancillary Cable Set,Germany Ancillary Cable Set,4-Module Ancillary Cable Set and 2-Module Ancillary Cable Set IAW the SOW and TDP.

0019AA Set OPTION MK 41 MOD 47 Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

Cable Set SLIN 0019AA, MAX 4

0019AA 1.00 2.00

0019AB Set OPTION 4-Module Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

4- Module Ancillary Cable Set

SLIN 0019AB, MAX 4

0019AB 1.00 2.00

OPTION MK 41 MOD 47 Ancillary Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of MK 41 MOD 36

Ancillary Cable Set,Germany Ancillary Cable Set,4-Module Ancillary Cable Set and 2-Module Ancillary Cable Set IAW the SOW and TDP.

0020AA Set OPTION MK 41 MOD 47 Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

Cable Set SLIN 0020AA, MAX 4

0020AA 1.00 2.00

0020AB Set OPTION 4-Module Ancillary Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

4- Module Ancillary Cable Set

SLIN 0020AB, MAX 4

0020AB 1.00 2.00

Extender Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of Extender Cable Set

0021AA 12 Set Extender Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION Extender Cable Set

FFP

0022AA Set OPTION Extender Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

Extender Cable Set SLIN

0022AA, MAX 10

0022AA 1.00 2.00

3.00 6.00

7.00 10.00

OPTION Extender Cable Set

FFP

0023AA Set OPTION Extender Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0023AA, MAX 10

0023AA 1.00 2.00

3.00 6.00

7.00 10.00

OPTION Extender Cable Set

FFP

0024AA Set OPTION Extender Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0024AA, MAX 7

0024AA 1.00 2.00

3.00 5.00

6.00 7.00

OPTION Extender Cable Set

FFP

0025AA Set OPTION Extender Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0025AA, MAX 12

0025AA 1.00 4.00

5.00 8.00

9.00 12.00

B/L VII DDG AMOD Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of B/L VII DDG

AMOD Cable Set IAW the SOW and TDP. Refer to CDRLs for item and data

0026AA 4 Set B/L VII DDG AMOD Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION B/L VII DDG AMOD Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of B/L VII DDG

0027AA 4 Set OPTION B/L VII DDG AMOD Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION B/L VII DDG AMOD Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of B/L VII DDG

0028AA 4 Set OPTION B/L VII DDG AMOD Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION B/L VII DDG AMOD Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of B/L VII DDG

0029AA 4 Set OPTION B/L VII DDG AMOD Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION B/L VII DDG AMOD Cable Set

FFP

Production Phase: Manufacture, assembly, test and delivery of B/L VII DDG

0030AA 2 Set OPTION B/L VII DDG AMOD Cable Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

Inco/Depot W21 Cable Assembly

FFP

Production Phase: Manufacture, assembly, test and delivery of Inco/Depot W21

Cable Assembly set IAW the SOW and TDP. Refer to CDRLs for item and data

0031AA 11 Set Inco/Depot W21 Cable Assembly

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION Inco/Depot W21 Cable Assembly Set

FFP

Production Phase: Manufacture, assembly, test and delivery of Inco/Depot W21

0032AA 2 Set OPTION Inco/Depot W21 Cable Assembly Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

OPTION Inco/Depot W21 Cable Assembly Set

FFP

Production Phase: Manufacture, assembly, test and delivery of Inco/Depot W21

0033AA 2 Set OPTION Inco/Depot W21 Cable Assembly Set

FFP

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0034 1 Each Production Readiness Review

FFP

Note: The contractor shall comply with section 16.0 in accordance with the SOW and TDP.

0035 1 Each OPTION Production Readiness Review

FFP

Note: The contractor shall comply with section 16.0 in accordance with the SOW and TDP.

0036 1 Each OPTION Production Readiness Review

FFP

Note: The contractor shall comply with section 16.0 in accordance with the SOW and TDP.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0037 1 Each OPTION Production Readiness Review

FFP

Note: The contractor shall comply with section 16.0 in accordance with the SOW and TDP.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0038 1 Each OPTION Production Readiness Review

FFP

Note: The contractor shall comply with section 16.0 in accordance with the SOW and TDP.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0039 1 Each Physical Configuration Audit

FFP

Note: The contractor shall comply with section 6.0 in accordance with the SOW and TDP.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and

Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

0040 1 Lot CDRLS - Not Separately Priced (NSP)

FFP

Prepare, maintain and deliver data IAW CDRLs A001 through A007 and Data Item

Delivery (DID) schedule requirements. The Government shall have unlimited rights to all data generated under this effort IAW DFARS 252.227-7013 unless an assertion is provided and accepted by the Government with the offer IAW DFARS

252.227-7017.The price for all data generated by the contractor directly or indirectly in its performance of this procurement effort is included in the price paid by the Government under the other CLINs in the contract.

CLAUSES INCORPORATED BY FULL TEXT

B-215-H002 REFUNDS (SPARES AND SUPPORT EQUIPMENT) (NAVSEA) (OCT 2018)

(a) In the event that the price of a spare part or item of support equipment delivered under this contract significantly exceeds its intrinsic value, the Contractor agrees to refund the difference. Refunds will not be made to recoup the amount of cost decreases that occur over time due to productivity gains (excluding economic purchase quantity considerations) or changes in market conditions.

(b) For purposes of this requirement, the intrinsic value of an item is defined as follows:

(1) If the item is one which is sold or is substantially similar or functionally equivalent to one that is sold in substantial quantities to the general public, intrinsic value is the established catalog or market price, plus the value of any unique requirements, including delivery terms, inspection, packaging, or labeling.

(2) If there is no comparable item sold in substantial quantities to the general public, intrinsic value is defined as the price an individual would expect to pay for the item based upon an economic purchase quantity as defined in FAR

52.207-4, plus the value of any unique requirements, including delivery terms, inspection, packaging or labeling.

(c) At any time up to two years after delivery of a spare part or item of support equipment, the Contracting Officer may notify the Contractor that based on all information available at the time of the notice, the price of the part or item apparently exceeds its intrinsic value.

(d) If notified in accordance with paragraph (c) above, the Contractor agrees to enter into good faith negotiations with the Government to determine if, and in what amount, the Government is entitled to a refund.

(e) If agreement pursuant to paragraph (d) above cannot be reached, and the Navy's return of the new or unused item to the Contractor is practical, the Navy, subject to the Contractor's agreement, may elect to return the item to the Contractor.

Upon return of the item to its original point of Government acceptance, the Contractor shall refund in full the price paid.

If no agreement pursuant to paragraph (d) above is reached, and return of the item by the Navy is impractical, the

Contracting Officer may, with the approval of the Head of the Contracting Activity, issue a Contracting Officer's final decision on the matter, subject to Contractor appeal as provided in the "Disputes" clause (FAR 52.233-1).

(f) The Contractor shall make refunds, as required under this requirement, in accordance with instructions from the

Contracting Officer.

(g) The Contractor shall not be liable for a refund if the Contractor advised the Contracting Officer in a timely manner that the price it would propose for a spare part or item of support equipment exceeded its intrinsic value, and with such advice, specified the estimated proposed price, the estimated intrinsic value and known alternative sources or item, if any, that can meet the requirement.

(h) This requirement does not apply to any spare parts or items of support equipment whose price is determined through adequate price competition. This requirement also does not apply to any spare part or item of support equipment if the

Contractor submitted, and certified the currency, accuracy and completeness of, cost or pricing data applicable to the item.

(End of text)

Section C - Descriptions and Specifications

STATEMENT OF WORK

STATEMENT OF WORK

VERTICAL LAUNCHING SYSTEM

MODULE CABLES N63394-21-R-0016

1.0 SCOPE

The Contractor shall be responsible for the satisfactory and timely performance of all tasks defined in the Statement of Work (SOW). This SOW, with its supporting attachments and referenced documentation, describes the total requirement for the manufacture, assembly, test and delivery of Vertical Launching System (VLS) System Module

Cable Set, Module Cable set, Module Deck and Hatch Cable set, MK 41 Mod 36 Ancillary Cable kit, MK 41 Mod

47 Ancillary Cable kit, Germany Ancillary Cable set, 4-Module Ancillary Cable kit, and 2-Module Ancillary Cable kit.

2.0 PROGRAM AUTHORITY

Naval Surface Warfare Center, Port Hueneme Division (NSWC PHD) is the program authority for this contract.

3.0 APPLICABLE DOCUMENTS

The following documents, of the issue indicated, form a part of this SOW, including all applicable terms, conditions, clauses, attachments and exhibits. The exact revisions of the documents are not cited in the text of this SOW. The

Contractor shall apply the latest version of the documents in effect at the time of award of the contract. In the event of a conflict between the documents referenced herein and the contents of this SOW, the SOW shall be considered the superseding requirement.

3.1 Government Documents

Document Number Document Title

MIL-STD-109C Quality Assurance Terms and Definitions

MIL-STD-1686C Electrostatic Discharge Control Program for Protection of

Electrical and Electronic Parts, I Assemblies and Equipment

(Excluding

Electrically Initiated Explosive Devices)

WS 20130 Production Environmental Test Requirements for VLS

TL130-AD-PLN-010-VLS Configuration Management Program Plan for the MK 41 VLS, Volume 1, Equipment (Hardware) Configuration Management

MK 41 VLS Standing Instruction 94-1F, Attachment 6

Marking for technical data

TL130-AD-PLN-030-VLS, Firmware Configuration Management

NAVSEA Drawing Standard Module Cable

NAVSEA Drawing System Module Cable set

Module Cable set

Module Deck and Hatch Cable set

MK 41 Mod 36 Ancillary Cable kit

MK 41 Mod 47 Ancillary Cable kit

Germany Ancillary Cable set

4-Module Ancillary Cable kit

2-Module Ancillary Cable kit

3.2 Industry Documents

Document Number Document Title

ANSI/ISO/ASQC Q9001 Quality Systems - Model for Quality Assurance in Design, Development, Production, Installation and Servicing

ANSI/EIA-649 2011 National Consensus Standard for Configuration Management

ANSI/ASQC Q9004 Quality System Elements

ISO 9001 Quality Program Requirements

SAE Aerospace Standard

AS9102 Rev A

Aerospace First Article Inspection

ISO 14000 Environmental Management Systems Standards

SAE AS5553 & AS6174 Counterfeit Prevention Plan

4.0 REQUIREMENTS

The Government requires manufacturing of VLS System Module Cable set, Module Cable set, Module Deck and

Hatch Cable set, MK 41 Mod 36 Ancillary Cable kit, MK 41 Mod 47 Ancillary Cable kit, Germany Ancillary Cable set, 4-Module Ancillary Cable kit and 2-Module Ancillary Cable kit in accordance with the documents specified in

SOW and the technical data package (TDP). All cables shall meet all requirements in accordance with the TDP and associated specifications.

4.1 Automatic Test Equipment

The Government will provide all necessary test equipment to test cables.

The Government has certified the test equipment, along with test program sets for use.

The Contractor shall be responsible for maintaining and calibrating the necessary test capability including ATE, associated interface cables, test tools and calibration tools.

Changes to certified ATE shall be submitted to the Government for approval and certification.

4.2 First Article Inspection

The Contractor shall perform First Article Inspection (FAI) of all assemblies, subassemblies, components and detail parts including castings and forgings in accordance with SAE Aerospace Standard AS9102 Rev A. The purpose of

FAI is to provide objective evidence that all TDP and specification requirements are correctly understood, accounted for, verified, and recorded. An FAI is not required for standard catalog items, commercial-off-the-shelf items, raw materials or items procured in accordance with source control drawings.

The Contractor shall submit all FAI requirement waivers to the NSWC PHD for approval. The waiver shall identify, at a minimum, the part description, part number, manufacturer, date last built, location last built, FAI report summary (if applicable), FAI discrepancies and corrective actions (if applicable), and waiver justification.

The Government reserves the right to witness all FAI activities. The Contractor shall submit a comprehensive schedule of FAI events prior to the first event in accordance with CDRL A001. The schedule shall include date, time, expected duration and location.

The Contractor shall generate FAI reports in accordance with AS9102 Rev A. The Contractor shall retain the FAI reports for at least seven (7) years. The Government reserves the right to examine all FAI reports. The Contractor shall submit a report copy via digital means in accordance with CDRL A002.

All deficiencies discovered during the FAIs shall be corrected at Contractor’s expense prior to unit delivery to the

Government.

5.0 TECHNICAL DATA REVIEWS, QUALITY AUDITS

During the performance of the contract, the Government shall have the right to perform technical data reviews and quality audits consisting of evaluation of records, processes and products to verify the Contractor's compliance with the respective quality programs.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .