Amendment N6274225R6503_0004 issued 081625.pdf
PDF 683 KB Posted
- Attached to
- D/B Construct Fixed Ground Stations, Kota Samarahan and Labuan, Malaysia Federal contract opportunity
- Solicitation number
- N6274225R6503
About this file
This document is an Amendment (0004) to a federal solicitation for a Design-Build contract (N6274225R6503) to construct fixed ground stations in Kota Samarahan and Labuan, Malaysia. The amendment changes the proposal due date to August 20, 2025, at 11:00 a.m. Thailand time, and modifies several key contract elements, including changing CLIN 0002 from a base bid item to an option item for constructing a fixed ground station in Labuan. The contract requires the contractor to complete the entire work within 400 calendar days after receiving the Contract Award Document, with specific provisions for project design, construction, electrical systems, site preparation, and associated overhead costs. The amendment also adds clauses related to option evaluation, increased quantity options, and funds availability for fiscal year 2025.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Enclosure 4. BOQ rev- 25R6503_AMD0004.xlsx | XLSX spreadsheet | |
| N6274225R6503_0003 Part 6 Add.jpg | JPG image | |
| Amendment N6274225R6503_0003 issued 073025.pdf | ||
| Enclosure 2. Revised BOQ 25R6503_0003.xlsx | XLSX spreadsheet | |
| Amendment N6274225R6503_0003 issued 073025.pdf | ||
| Amendment N6274225R65030002 issued 072425.pdf | ||
| Amendment N6274225R65030001 issued 062625.pdf | ||
| Solicitation Amendment N6274225R65030001 SF 30.pdf | ||
| Enclosure 4 Blank BoQ - 25R6503.xlsx | XLSX spreadsheet | |
| Enclosure 1. Pre Proposal Inquiry Form.xlsx | XLSX spreadsheet | |
| Solicitation - N6274225R6503 released w Atts 061125.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section 00 00 00 - Procurement and Contracting Requirements
The following changes have been made:
INFORMATION FROM TO
Response Due Date 04 Aug 2025 20 Aug 2025
Miscellaneous text in this section has been added to:
The following changes will be considered part of this solicitation:
A. Proposal due date is hereby changed to August 20, 2025, no later than 11:00 a.m. Thailand time.
B. The following changes are hereby incorporated to the solicitation N6274225R6503.
SUMMARY OF CHANGES
AMENDMENT 0004
1. All references CLIN 0002:
CHANGE: CLIN 0002: BASE BID ITEM 0002 - CONSTRUCT A FIXED GROUND STATION IN LABUAN
TO: CLIN 0002: OPTION ITEM 0001 - CONSTRUCT A FIXED GROUND STATION IN LABUAN
2. ADD: 52.217-5 EVALUATION OF OPTIONS (JULY 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(End of provision)
3. 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives CHANGE "the notice to proceed" TO "Contract Award Document (SF1442)", (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 400 calendar days. The time stated for completion shall include final cleanup of the premises.
(End of clause)
4. ADD: 52.217-7 OPTION FOR INCREASED QUANTITY -- SEPARATELY PRICED LINE ITEM (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option unilaterally by modification to the Contractor within ninety (90) calendar days from contract award for CLIN 0002 Option Item 0001. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of clause)
5. ADD: 52.232-18 Availability of Funds (APR 1984) by reference
6. ADD: 52.232-19 Availability of Funds for the Next Fiscal Year. (Apr 1984)
N6274225R65030004 https://www.acquisition.gov/far/17.206#FAR_17_206
Funds are not presently available for performance under this contract beyond FY25. The Government's obligation for performance of this contract beyond that date is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise for performance under this contract beyond FY25, until funds are made available to the for Contracting Officer performance and until the Contractor receives notice of availability, to be confirmed by the in writing Contracting
.Officer
(End of clause)
C. The following attachment is incorporated into the RFP.
- Enclosure 4 BOQ rev.
All other terms and contract requirements remain in effect and unchanged.
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
The following CLIN(s) / SLIN(s) / ELIN(s) were modified:
Option Line Item 0002
INFORMATION FROM TO CHANGED
BY
Description
Construct a Fixed Ground Station in LabuanBASE BID ITEM 0002 This is a Design- Build project. The contractor shall provide complete design and construction of a fixed ground station in Labuan, Malaysia, in accordance with the Parts 2-6 attached here within.
Construct a Fixed Ground Station in Labuan OPTION ITEM 0001This is a Design-Build project. The contractor shall provide complete design and construction of a fixed ground station in Labuan, Malaysia, in accordance with the Parts 2-6 attached here within.
Option No Yes
Section 00 70 00 - Conditions of the Contract
Additional Information/Notes
The following clauses were modified:
52.211-10Commencement, Prosecution, and Completion of Work.Apr 1984 hereby reads as follows:
Commencement, Prosecution, and Completion of Work (Apr 1984)
The Contractor shall be required to (a) commence work under this contract within calendar days after the date the Contractor receives the Contract 10 Award Document (SF1442), (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than . The 400 calendar days time stated for completion shall include final cleanup of the premises.
(End of clause)
N6274225R65030004
N6274225R65030004
N6274225R6503_0004
Enclousre 4. BOQ rev.
ACTIVITY AND LOCATION: CONSTRUCTION CONTRACT NO. ID NO.
ESTIMATED BY CATEGORY CODE
PROJECT TITLE: NO
JOB ORDER NO.
Construct Fixed Ground Station Kota Samarahan NUMBER UNIT UNIT COST TOTAL ($) UNIT COST TOTAL ($) UNIT COST TOTAL ($)
B10 SUPERSTRUCTURE
Anchor bolts bolt
Base plates unit
Steel structural members including platform kg
Connections kg
Steel plate cover unit
B20 EXTERIOR ENCLOSURE
B201009 Exterior Painting and Coating
Antirust paint Liter
D50 ELECTRICAL
D5010 Electrical Service and Distribution ls
D5020 Lighting and Branch Wiring ls
D502002 Aviation obstruction lighting pcs
D503001 Conduit for fiber optic cables m
D509004 Lightning protection system ls
F10 SPECIAL CONSTRUCTION
Project plaque ls
X OFFICE OVERHEAD & PROFIT
X20 Office Overhead
X30 Profit
Total
Table 2: SITEWORK
Construct Fixed Ground Station Kota Samarahan NUMBER UNIT UNIT COST TOTAL ($) UNIT COST TOTAL ($) UNIT COST TOTAL ($)
G10 SITE PREPARATION
G1010 Site Clearing ls
G1030 Mobilization ls
De-mobilization ls
Design and drawing ls
Construction of temporary facilities ls
G30 SITE CIVIL/ MECHANICAL UTILITIES
Electricity connection
X FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT
X20 Office Overhead
X30 Profit
Total
Construct Fixed Ground Station in Labuan NUMBER UNIT UNIT COST TOTAL ($) UNIT COST TOTAL ($) UNIT COST TOTAL ($)
B10 SUPERSTRUCTURE
Anchor bolts bolt
Base plates unit
Steel structural members including platform kg
Connections kg
B20 EXTERIOR ENCLOSURE
B201009 Exterior Painting and Coating
Antirust paint Liter
D50 ELECTRICAL
D5010 Electrical Service and Distribution ls
D5020 Lighting and Branch Wiring ls
D502002 Aviation obstruction lighting pcs
D503001 Conduit for ethernet cables m
D509004 Lightning protection system ls
F10 SPECIAL CONSTRUCTION
Project plaque ls
X OFFICE OVERHEAD & PROFIT
X20 Office Overhead
X30 Profit
Total
Table 2: SITEWORK
Construct Fixed Ground Station in Labuan NUMBER UNIT UNIT COST TOTAL ($) UNIT COST TOTAL ($) UNIT COST TOTAL ($)
G10 SITE PREPARATION
G1010 Site Clearing ls
G1030 Mobilization ls
De-mobilization ls
ENGINEERING ESTIMATECLIN 002: Option Bid Item 0001 QUANTITY MATERIAL COST LABOR COST
CLIN 002: Option Bid Item 0001 QUANTITY MATERIAL COST LABOR COST ENGINEERING ESTIMATE
Total CLIN 001
D/B Construct Fixed Ground Stations STATUS OF DESIGN
CLIN 0001: Base Bid Item 0001
CLIN 0001: Base Bid Item 0001
QUANTITY MATERIAL COST LABOR COST ENGINEERING ESTIMATE
QUANTITY MATERIAL COST LABOR COST ENGINEERING ESTIMATE
BILL OF QUANTITIES
DATE PREPARED
Kota Samarahan and Labuan, Malaysia N6274225R6503
#SBU - CONTRACTING AND ACQUISITIONS
N6274225R6503_0004
Enclousre 4. BOQ rev.
Design and drawing ls
Construction of temporary facilities ls
G30 SITE CIVIL/ MECHANICAL UTILITIES
Electricity connection
X FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT
X20 Office Overhead
X30 Profit
Total
Total CLIN 002
TOTAL CLIN 001 and CLIN 002
#SBU - CONTRACTING AND ACQUISITIONS
| BoQ - Fixed Ground Stations_AMD0004.pdf |
| Sheet1 |
| IDCode: J |
| Page: 1 |
| Pages: 4 |
| AmendNo: 0004 |
| EffDate: 16 Aug 2025 |
| ReqNo: See Continuation Sheet |
| ProjNo: N6274225R6503 |
| IssCode: N62742 |
| AdmCode: |
| IssuedBy: NAVFACSYSCOM PACIFIC |
258 MAKALAPA DR STE 100, JBPHH HI 96860-3134
JBPHH, HI 96860-3134
UNITED STATES
ARTITAR UDIT, Email: artitar.udit.ln@us.navy.mil Telephone: 6622871036 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: N6274225R6503 |
| SolDate: 11 Jun 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: 1 |
| OffrNoEx: Off |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: N6274225R6503 D/B Construct Fixed Ground Stations, Kota Samarahan and Labuan, Malaysia |
Detail of Amendment 0004 begins on the following page.
| ContNameTitle: |
| CoNameTitle: Rondel Williams |
| ContDate: |
| CODate: 15 Aug 2025 |