N6264926RL004 A0001 MIGUEL KEITH Continuation Sheet.pdf
PDF 133 KB Posted
- Attached to
- USS MIGUEL KEITH (ESB 5) MTA A0009
- Solicitation number
- N6264926RL004
About this file
This is an amendment to a federal contract job order (N6264926RL004 A0001) for Miguel Keith (ESB 5) under a Military Training Agreement (MTA). The amendment revises the Period of Performance from October 10 – December 10, 2026 to September 26 – December 10, 2026, extending the start date by two weeks. A revised J-3 form has been attached to add missing work items and remove duplicate work item 0506 (CLIN 0001), with Work Item 0801 corrected to Work Item 0890.
The document includes a question and answer section addressing the submission requirements for SRF (Services Requirements Format) Work Items. Category I items (009-001 through 009-126) are general standards applicable to all work under the contract, and their costs must be included in overhead and indirect rates; separate quotations are not required. Category II items (009-011 through 009-032) are optional standards that may be invoked in specific work items, and contractors are required to submit quotations only when these items are explicitly requested in a particular work item, not as standalone submissions.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N6264926RL004 A0001 MIGUEL KEITH (ESB 5) MTA
1. The purpose of this amendment is to revise the Period of Performance dates from 10 October - 10 December 2026 to 26 September to 10 December 2026.
2. Attached is a revised J-3 to add missing work items and to remove duplicate work item 0506 (CLIN 0001). Work Item 0801 corrected to Work Item 0890.
3. See attached updated work items.
4. Clarification.
Question:
Advise whether we are required to submit a quotation for the SRF Work Items listed below:
• CATEGORY I. FY-27 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER
WITHOUT FURTHER REFERENCE.
o 009-001 ~ 009-126
• CATEGORY II. FY-27 STANDARD ITEMS WHICH MAY BE INVOKED IN THE
WORK ITEMS OF THIS JOB ORDER.
o 009-011 ~ 009-032
Answer:
Category I (009-001 ~ 009-126): Costs for these general standards should be included in overhead and indirect rates. Category I Standard Items, such as 'General Criteria; accomplish' (009-001), establish the general requirements and administrative procedures that are applicable to all work performed under the contract. Category I Standard Items are invoked in for all work items and apply to all work being performed.
Category II (009-011 ~ 009-032): Contractor is required to submit a quotation for these items only when they are explicitly invoked in a specific work item.
Contractors are not required to submit a quotation for these items individually. A quote will only be necessary for Category II items if they are specifically requested in a work item.