This Task Group Instruction (TGI) details crane and rigging services required for the USS MILIUS (DDG-69) FY25 Surface Incremental Availability (SIA) at Yokosuka Naval Base, Japan. The work involves providing crane services with a 1,500 lb weight limitation and rigging services consisting of four riggers and one supervisor, to be performed over 18 days (Wednesdays and Saturdays across 9 weeks) between 08:00-17:00. The period of performance runs from May 14, 2025 to July 12, 2025.
The TGI is part of a larger solicitation (N6264925RA019) managed by NAVSUP Fleet Logistics Center Yokosuka for SRF-JRMC. Work will be conducted throughout the ship and pier side, with no government furnished materials required. The document identifies key personnel including planner M. Namegaya (Code 231B) and Work Integration Manager T. Yaginuma (Code 333). Proposals for the overall solicitation are due February 12, 2024, at 10:00 AM, and must be submitted to specified Navy personnel via email.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment II Price Proposal Form N6264925RA019.xlsx | XLSX spreadsheet | |
| N6264925RA019-0001.pdf | ||
| Attachment IV Contract Data Sheet 25RA019.pdf | ||
| 38KA112301A01_c0v0TGI.pdf | ||
| Attachment II Price Proposal Form N6264925RA019.xlsx | XLSX spreadsheet | |
| 38KA116802A01_c0v0TGI.pdf | ||
| 38KA186501A01_c0v0TGI.pdf | ||
| 38KA163401A01_c0v0TGI.pdf | ||
| 38KA175301A01_c0v0TGI.pdf | ||
| N6264925RA019.pdf | ||
| 38KA112302A01_c0v0TGI.pdf | ||
| 38KA165402A01_c0v0TGI.pdf | ||
| 38KA165403A01_c1v1TGI.pdf | ||
| Attachment III Request for Information Form.doc | DOC document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
18-JAN-2025 1614
20.14.15.2.9020 (September 2024) ICN: 38KA186502 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: F/O CRANE & RIG SVCE AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-69 USS MILIUS KA1
CU PHASE TITLE: F/O - PROVIDE FY25 SIA CRANE, CRANE RGNG, AND RGNG SERVICE FOR SHIP’S FORCE WORK
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 3
EXSYL082
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
NAMEGAYA, MASAHARU 231B 3152434489 18-JAN-2025
APPROVED BY: CODE: PHONE: DATE:
TAKAGI, RYOUTA 231B 3152434502 18-JAN-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EXSY-L082
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
865A3102
1. SCOPE/PURPOSE:
1.1 Title: FY25 SIA Crane, Crane Rigging, and Rigging Service for Ship’s Force Work; provide
1.2 Location of Work:
1.2.1 Throughout the Ship
1.2.2 Pier Side
1.3 Identification:
1.3.1 Quantity (One Lot), Crane and Crane Rigging Service for Ship’s Force Work
Remarks: Weight Limitation; No greater than 1,500 LBs Work Time Performance Period; 18 Days (Wednesday and Saturday in 9 Weeks) Work Time; From 08:00 to 17:00
TGI Short Form
18-JAN-2025 1614
20.14.15.2.9020 (September 2024) (Continued) ICN: 38KA186502 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: F/O CRANE & RIG SVCE AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-69 USS MILIUS KA1
CU PHASE TITLE: F/O - PROVIDE FY25 SIA CRANE, CRANE RGNG, AND RGNG SERVICE FOR SHIP’S FORCE WORK
FOUO Pg 2 of 3
CU PHASE DESCRIPTION (Cont.)
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
1.3.2 Quantity (One Lot), Rigging Service for Ship’s Force Work
Remarks: Weight Limitation; No greater than 1,500 LBs Work Time Performance Period; 18 Days (Wednesday and Saturday in 9 Weeks) Work Time; From 08:00 to 17:00 Rigging team must consist of Four (4) riggers and One (1) supervisor proficient.
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date: 14 May 2025
1.7 Contractor work completion date: 12 July 2025
2. PROCEDURE:
2.1 Provide crane, crane rigging, and rigging service listed in 1.3.1 and 1.3.2 during throughout FY25 SIA (KA1) period as per Ship’s Force request.
2.2 Notes:
2.2.1 Planner: Code 231B M. Namegaya, 243-4489
2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.2.3 JCN EXSY-L082 is related to this TGI.
2.3 Government Furnished Material (GFM): None.
2.4 SRF-JRMC service work: None.
18-JAN-2025 1614
20.14.15.2.9020 (September 2024) (Continued) ICN: 38KA186502 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: F/O CRANE & RIG SVCE AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-69 USS MILIUS KA1
CU PHASE TITLE: F/O - PROVIDE FY25 SIA CRANE, CRANE RGNG, AND RGNG SERVICE FOR SHIP’S FORCE WORK
FOUO Pg 3 of 3
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 38KA186502 KEY OP: A01
File details come from the government source that posted it. Updated .