This is a Task Group Instruction (TGI) for installing and removing scaffolding at various locations aboard the USS MILIUS (DDG-69) to support Ship's Force maintenance work. The document details scaffolding requirements at multiple locations including weather decks, yardarm, and pole mast positions between frames 125-202, spanning multiple deck levels. The work will enable preservation of bulkheads and maintenance of various antenna systems including antenna numbers 6-4, 3-30B, 3-12, 3-4, 3-3, and 4-1.

The contractor work period is scheduled from May 12, 2025 through July 4, 2025. The work will be performed in 10 separate lots of scaffolding assemblies, each supporting specific maintenance tasks to be completed by Ship's Force. SRF-JRMC will provide crane and rigging services, safety inspections, and QA inspections under TGI No. 38KA186501S02. The work requires compliance with NAVSEA Standard Items, Local Standard Items, and scaffolding regulations under 29 CFR PART 1915.71. No government furnished materials are provided for this task.

View the file

Other files

File Type Posted
Attachment II Price Proposal Form N6264925RA019.xlsx XLSX spreadsheet
38KA186502A01_c0v0TGI.pdf PDF
N6264925RA019-0001.pdf PDF
Attachment IV Contract Data Sheet 25RA019.pdf PDF
38KA112301A01_c0v0TGI.pdf PDF
Attachment II Price Proposal Form N6264925RA019.xlsx XLSX spreadsheet
38KA116802A01_c0v0TGI.pdf PDF
38KA163401A01_c0v0TGI.pdf PDF
38KA175301A01_c0v0TGI.pdf PDF
N6264925RA019.pdf PDF
38KA112302A01_c0v0TGI.pdf PDF
38KA165402A01_c0v0TGI.pdf PDF
38KA165403A01_c1v1TGI.pdf PDF
Attachment III Request for Information Form.doc DOC document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

17-OCT-2024 1315

20.14.15.2.9020 (September 2024) ICN: 38KA186501 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SF TST A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-69 USS MILIUS KA1 86512

CU PHASE TITLE: *F/O - INSTALL AND REMOVE SCAFFOLDING TO/FROM VARIOUS LOCATION FOR S/F WORK

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 4

ES01L150

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

TAKEISHI, TAKAYUKI 231B 3152436704 12-OCT-2024

APPROVED BY: CODE: PHONE: DATE:

NAMEGAYA, MASAHARU 231B 3152434489 12-OCT-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ES01-L150

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE VARIOUS U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

865A1201

1. SCOPE/PURPOSE:

1.1 Title: Scaffolding for Ship’s Force Work; install and remove

1.2 Location of work:

1.2.1 Between 04 Level and 05 Level Weather, Frames between 125 and 135, Port and Starboard (Stbd)

1.2.2 01 Level Weather, Frames between 142 and 150, Port and Stbd

1.2.3 01 Level Weather, Frames between 197 and 202, Port and Stbd

1.2.4 04 Level Weather, Frames between 160 and 170, Port and Stbd

1.2.5 Lower yardarm, Frames between 170 and 175, Port and Stbd

1.2.6 Pole Mast, Frame 181, Ship’s Center Line

TGI Short Form

17-OCT-2024 1315

20.14.15.2.9020 (September 2024) (Continued) ICN: 38KA186501 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SF TST A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-69 USS MILIUS KA1 86512

CU PHASE TITLE: *F/O - INSTALL AND REMOVE SCAFFOLDING TO/FROM VARIOUS LOCATION FOR S/F WORK

FOUO Pg 2 of 4

CU PHASE DESCRIPTION (Cont.)

1.3 Identification:

1.3.1 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.1 Remarks: Preservation work of bulkhead and antenna pedestal will be accomplished by Ship's Force.

1.3.2 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.2 Remarks: Maintenance work of antenna number 6-4(P6) will be accomplished by Ship's Force.

1.3.3 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.2 Remarks: Maintenance work of antenna number 6-4(S5) will be accomplished by Ship's Force.

1.3.4 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.3 Remarks: Maintenance work of antenna number 6-4(P8) will be accomplished by Ship's Force.

1.3.5 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.3 Remarks: Maintenance work of antenna number 6-4(S7) will be accomplished by Ship's Force.

1.3.6 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.4 Remarks: Preservation work of antenna number 3-30B platform will be accomplished by Ship's Force.

1.3.7 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.4 Remarks: Preservation work of antenna number 3-12 platform will be accomplished by Ship's Force.

1.3.8 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.5 Remarks: Maintenance work of antenna number 3-4 will be accomplished by Ship's Force.

1.3.9 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.5 Remarks: Maintenance work of antenna number 3-3 will be accomplished by Ship's Force.

1.3.10 Quantity (One Lot), Scaffolding Assembly

17-OCT-2024 1315

20.14.15.2.9020 (September 2024) (Continued) ICN: 38KA186501 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SF TST A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-69 USS MILIUS KA1 86512

CU PHASE TITLE: *F/O - INSTALL AND REMOVE SCAFFOLDING TO/FROM VARIOUS LOCATION FOR S/F WORK

FOUO Pg 3 of 4

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

Location: 1.2.6 Remarks: Maintenance work of antenna number 4-1 will be accomplished by Ship's Force.

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date: 12 May 2025

1.7 Contractor work completion date: 04 Jul 2025

2. PROCEDURE:

2.1 Erect/hang scaffolding listed in 1.3.1 through 1.3.10 in accordance with Ref. No. 3.

2.2 Remove scaffolding listed in 1.3.1 through 1.3.10 upon completion of the work in accordance with Ref. No. 3 when requested by Ship’s Force via Code 333.

2.3 Notes:

2.3.1 Planner: Code 231B T. Takeishi, 243-6704

2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.3.3 JCN ES01-L150 is related to this TGI.

2.4 Government Furnished Material (GFM): None.

2.5 SRF-JRMC will provide the following service work: (TGI No. 38KA186501S02)

2.5.1 [C740] Crane and crane rigging service.

2.5.2 [C106.1] Safety inspection for SRF-JRMC employees.

2.5.3 [C133] QA inspection for (G) symbol(s).

17-OCT-2024 1315

20.14.15.2.9020 (September 2024) (Continued) ICN: 38KA186501 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: TEMPORARY STAGING SF TST A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-69 USS MILIUS KA1 86512

CU PHASE TITLE: *F/O - INSTALL AND REMOVE SCAFFOLDING TO/FROM VARIOUS LOCATION FOR S/F WORK

FOUO Pg 4 of 4

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - 1 N 2 LI FY-25 Local Standard Items - ORG N

3 TM 29 CFR PART

1915.71 Scaffolding or Staging - N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38KA186501 KEY OP: A01