Am5.pdf
PDF 290 KB Posted
- Solicitation number
- N62478-19-R-1518
About this file
This solicitation is for a design-build project to construct a new Undersea Operations Training Center at Joint Base Pearl Harbor-Hickam in Hawaii. The project includes construction of a new approximately 54,380 gross square foot facility in two stories to support operator and diver training functions. The facility will house classrooms, laboratories, computer labs, operator lockers and cages, diver support spaces, and a high bay area containing a combat training tank. Supporting site work and utilities are also required.
The solicitation will be issued on October 16, 2019 and proposals will be due by December 16, 2019. The estimated cost of the project is between $25-100 million. The contract will be awarded using a lowest price technically acceptable source selection evaluating experience, safety, and past performance as non-cost factors. Large businesses must submit a subcontracting plan. The Naval Facilities Engineering Command is the contracting agency. The solicitation and drawings can be accessed on the Federal Business Opportunities website.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Am7.pdf | ||
| Am6.pdf | ||
| Am4.pdf | ||
| Am3.pdf | ||
| Am2.pdf | ||
| Am1.pdf | ||
| P-463_JA_19-06.pdf | ||
| P-463_JA_170727.pdf | ||
| RFP_Part_1.pdf | ||
| P-463_JA_19-09.pdf | ||
| FedBizOps_Notice_1_use.pdf | ||
| P-463_JA_19-10.pdf | ||
| P-463_JA_19-11.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT J 1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
Am-0005 12/10/19
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
NAVFAC Hawaii Construction Acquisition Division (OPHA2) 400 Marshall Road See Item 6 JBPHH, Hawaii 96860-3139
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
N62478-19-R-1518
X 9B. DATED (SEE ITEM 11)
16 Oct 19
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[ X ]The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ ] is extended, [x ] is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning ____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required) NA
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: FAR CLAUSE 52.243-4, CHANGES
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor [ ] is not, [ ] is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N62478-19-R-1518, FY20 MILCON P-463 SOF Undersea Operational Training Facility, Pearl City Peniunsula, Joint Base Pearl Harbor-Hickam (JBPHH), Hawaii
See page 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION UNUSABLE
30-105 STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Am-0005 Standard Form 30 Item No. 14 (Continued) Page 2 of 2
1. CHANGES TO THE SOLICITATION. Attached hereto are revised pages to the solicitation. The revision mark “(Am-0005)” is shown on each page.
a. REVISED SECTIONS/PROVISIONS/CLAUSES/PAGES/PARAGRAPHS/ITEMS. The following are revised pages to the solicitation. Changes are indicated in bold print. Although the entire documents are being re-issued under Am-0005, only the following pages/paragraphs/items changed in the following document.
Document 00010
SF 1442, Item No. 13D
Document 00700
52.232-18, Availability of Funds (Apr 1984)
2. The proposal due date of December 16, 2019, 2:00 P.M., Hawaiian Standard Time, remains unchanged.
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATIED (RFP)
3. DATE ISSUED
10/16/19
PAGE OF
PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO 6. PROJECT NO.
7. ISSUED BY CODE N62478 8. ADDRESS OFFER TO
NAVFAC Hawaii Construction Acquisition Division (OPHA2) 400 Marshall Road
JBPHH, HI 96860-3139
Mail: See Block 7 or
Hand carry proposals to:
NAVFAC Hawaii 400 Marshall Road, Building A13
JBPHH, HI 96860-3139
Depository hours between 7:30 AM and 2:00 PM, Monday Through Friday except Holidays. Please call 471-0318 or 474-3783 or 471-9197 for access to A13.
9. FOR INFORMATION
CALL:
A. NAME
Jody Muraoka
B. TELEPHONE NO. (Include area code) (NO COLLECT
CALLS)
(808)471-0318, FAX: (808)474-1543
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder”.
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
Request for Proposals No. N62478-19-R-1518, FY20 MILCON P-463 SOF Undersea Operational Training Facility Pearl City Peninsula, Joint Base Pearl Harbor-Hickam (JBPHH), Hawaii.
This procurement is solicited on an unrestricted basis.
SYSTEM FOR AWARD MANAGEMENT (SAM): Offerors shall comply with FAR 52.204-7, System for Award Management (Oct 2018) to receive an award. Lack of registration in the SAM database will make an Offeror ineligible for award
11. The Contractor shall begin performance within 15 calendar days and complete it within * calendar days after receiving *See Document 00700, Clause 52.211-10 award, notice to proceed. This performance period is X mandatory, negotiable. (See Section 00700 FAR 52.211-10) 12.a THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES”, indicate within how many calendar days after award in Item 12B.)
YES NO
12.B CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and (See Document 00100) copy to perform the work required are due at the place specified in Item 8 by 2:00 PM HST, 12/16/19 (or as amended via SF30). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 197 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212
1442-102 (Am-0005) STANDARD FORM 1442 (REV. 4-85) Prescribed by GSA
FAR (48 CFR) 53.236-1(d)
OFFER (Must be fully completed by offeror) N62478-19-R-1518
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO./FACSIMILE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
DUNS NO. CAGE CODE
TIN NO.
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within ____ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
SEE ATTACHED PROPOSAL SCHEDULE
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZATION TO SIGN OFFER
(Type or print )
20B. SIGNATURE 20C. OFFER
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified) (See Section 00700 252.232-7006).
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) ( ) 41 U.S.C.253(c) ( )
26. ADMINISTERED BY CODE N62478 27. PAYMENT WILL BE MADE BY N68732
NAVFAC HAWAII
NAVFAC HI FEAD PRJ22
90 G St., Bldg 1200
JBPHH, HI 96853-5230
Defense Finance & Accounting Service - Cleveland Norfolk Accounts Payable
PO BOX 998022
Cleveland OH 44199
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT Contractor is required to sign this document and return copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form an any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE 30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD
GPO : 1995 O - 469-79
STANDARD FORM 1442 BACK
(REV. 4-8)
(Am-0005)
Document 00700
Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-13 Contractor Code of Business Ethics and Conduct OCT 2015 52.203-19 Prohibition on Requiring Certain Internal Confidentiality
Agreements or Statements
JAN 2017
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2018
52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-21 Basic Safeguarding of Covered Contractor Information Systems
JUN 2016
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities.
OCT 2019
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
AUG 2019
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
OCT 2018
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.210-1 Market Research APR 2011 52.211-13 Time Extensions SEP 2000 52.211-15 Defense Priority And Allocation Requirements APR 2008 52.215-2 Audit and Records--Negotiation OCT 2010 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data--
Modifications
AUG 2011
52.215-13 Subcontractor Certified Cost or Pricing Data--Modifications OCT 2010 52.215-17 Waiver of Facilities Capital Cost of Money OCT 1997 52.215-21 Requirements for Certified Cost or Pricing Data and Data
Other Than Certified Cost or Pricing Data -- Modifications
OCT 2010
52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Deviation 2019-O0003)
APR 2019
(Am-0005)
52.219-8 Utilization of Small Business Concerns OCT 2018 52.219-9 Small Business Subcontracting Plan AUG 2018 52.219-16 Liquidated Damages-Subcontracting Plan JAN 1999 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards - Overtime
Compensation
MAY 2018
52.222-6 Construction Wage Rate Requirements AUG 2019 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records AUG 2018 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-30 Construction Wage Rate Requirements--Price Adjustment (None or Separately Specified Method)
AUG 2018
52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans FEB 2016 52.222-40 Notification of Employee Rights Under the National Labor
Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons JAN 2019 52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-15 Energy Efficiency in Energy-Consuming Products DEC 2007 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
AUG 2018
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.223-21 Foams JUN 2016 52.225-1 Buy American—Supplies (Applies to FF&E portion of the project)
MAY 2014
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets AUG 2018 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds--Construction OCT 2010
(Am-0005)
52.229-3 Federal, State And Local Taxes FEB 2013 52.232-17 Interest MAY 2014 52.232-18 Availability of Funds APR 1984 52.232-23 Alt I Assignment of Claims (May 2014) - Alternate I APR 1984 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-23 Responsibility of the Architect-Engineer Contractor APR 1984 52.236-25 Requirements for Registration of Designers JUN 2003 52.236-26 Preconstruction Conference FEB 1995 52.242-5 Payments to Small Business Subcontractors JAN 2017 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Items JAN 2019 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984 52.251-1 Government Supply Sources APR 2012 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General AUG 2019 252.203-7004 Display of Hotline Posters MAY 2019 252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992
(Am-0005)
252.204-7004 Antiterrorism Awareness Training for Contractors. FEB 2019 252.204-7006 Billing Instructions OCT 2005 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
OCT 2016
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Country that is a State Sponsor of Terrorism
MAY 2019
252.211-7003 Item Unique Identification and Valuation MAR 2016 252.219-7003 Small Business Subcontracting Plan (DOD Contracts) MAY 2019 252.223-7001 Hazard Warning Labels DEC 1991 252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.225-7048 Export-Controlled Items JUN 2013 252.226-7001 Utilization of Indian Organizations and Indian-Owned
Economic Enterprises, and Native Hawaiian Small Business Concerns
APR 2019
252.227-7022 Government Rights (Unlimited) MAR 1979 252.227-7033 Rights in Shop Drawings APR 1966 252.231-7000 Supplemental Cost Principles DEC 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.232-7011 Payments in Support of Emergencies and Contingency
Operations
MAY 2013
252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7013 Requirement for Competition Opportunity for American Steel
Producers, Fabricators, and Manufacturers
JUN 2013
252.242-7006 Accounting System Administration FEB 2012 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for
Military Operations
OCT 2010
252.247-7023 Transportation of Supplies by Sea FEB 2019 252.251-7000 Ordering from Government Supply Sources AUG 2012
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
(Also see Document 00800, Part III, Paragraph 3.4.)
The Contractor shall be required to (a) commence work under this contract within fifteen (15) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than seven hundred (700) calendar days after the date the Contractor receives the notice to proceed. (See also Document 00800, Paragraph 3.5 for Phased Construction Schedule). The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(See also Document 00700, Clause 52.211-10, Commencement, Prosecution, and Completion of Work ( (Apr 1984) and Document 00800, Paragraph 3.4, Notice to proceed and Paragraph 3.5, Phased Construction Schedule)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government for each calendar day of delay until the work is completed or accepted as follows:
PHASE 1: $280.00/day
PHASE 2: $8,522.00/day
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JULY 2013)
(a) Definitions. As used in this clause--
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is ``not dominant in its field of operation'' when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts--
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it ( ) is, ( ) is not a small business concern under NAICS Code 236220 assigned to contract number .
(Contractor to sign and date and insert authorized signer's name and title).
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (JAN 1997)
(a) "Hazardous material", as used in this clause, includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).
(b) The offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. This information shall also be included on the Material Safety Data Sheet submitted under this contract.
Material Identification No.
(If none, insert "None")
(Am-0005)
(c) This list must be updated during performance of the contract whenever the Contractor determines that any other material to be delivered under this contract is hazardous.
(d) The apparently successful offeror agrees to submit, for each item as required prior to award, a Material Safety Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items.
Failure to submit the Material Safety Data Sheet prior to award may result in the apparently successful offeror being considered nonresponsible and ineligible for award.
(e) If, after award, there is a change in the composition of the item(s) or a revision to Federal Standard No. 313, which renders incomplete or inaccurate the data submitted under paragraph (d) of this clause, the Contractor shall promptly notify the Contracting Officer and resubmit the data.
(f) Neither the requirements of this clause nor any act or failure to act by the Government shall relieve the Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.
(g) Nothing contained in this clause shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.
(h) The Government's rights in data furnished under this contract with respect to hazardous material are as follows:
(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to--
(i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials;
(ii) Obtain medical treatment for those affected by the material; and
(iii) Have others use, duplicate, and disclose the data for the Government for these purposes.
(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this clause, in precedence over any other clause of this contract providing for rights in data.
(3) The Government is not precluded from using similar or identical data acquired from other sources.
52.225-11 BUY AMERICAN-CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT 2019)
(a) Definitions. As used in this clause-
“Caribbean Basin country construction material” means a construction material that–
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(Am-0005)
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
“Commercially available off-the-shelf (COTS) item”-
(1) Means any item of supply (including construction material) that is-
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C.40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Designated country” means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(Am-0005)
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St.
Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
“Designated country construction material” means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
“Domestic construction material” means-
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if-
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“Free Trade Agreement country construction material” means a construction material that-
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
“Least developed country construction material” means a construction material that-
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
“United States” means the 50 States, the District of Columbia, and outlying areas.
“WTO GPA country construction material” means a construction material that-
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(Am-0005)
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) This clause implements 41 U.S.C.chapter 83, by providing a preference for domestic construction material. In accordance with 41 U.S.C.1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.
(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs(b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
None
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(Am-0005)
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction MaterialDescription Unit of Measure Quantity Price (Dollars)*
Item1:
Foreign construction material _______ _______ _______
Domestic construction material _______ _______ _______
Item2:
Foreign construction material _______ _______ _______
Domestic construction material _______ _______ _______
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
(Am-0005)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
(1) The Contractor's request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer.
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if--
(i) Consideration is specifically authorized by this contract; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that--
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
(Name)
(Title)
(Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall--
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until--
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as--
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after--
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of 1940 (31 U.S.C. 3727 and 41 U.S.C. 6305).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR Subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C. 3903(c)(1), the amount payable under subparagraph (d)(2) of this clause shall be--
(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and
(2) Deducted from the next available payment to the Contractor.
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least twenty (20) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
52.236-4 PHYSICAL DATA (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by borings, test pits, sample taking and testing.
(b) Weather conditions: Moderate tropical climate. Warm throughout the year with an average annual temperature of 80 degrees F. Rainy season from July to November. Average annual rainfall approximately 80 inches. Small scale storms can occur at any time, with little notice. Tropical storms or typhoons may occur during any month of the year, but are most likely from July through September.
(c) Transportation facilities: No public transportation to site. Transportation to new building site is via Privately Owned Vehicles (POV) on paved road that runs adjacent to new parking site. Main vehicular access to facility is off Victor Wharf Access Road.
(End of clause)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browsefar
(Am-0005) https://www.acq.osd.mil/dpap/dars/dfarspgi/current/ https://www.secnav.navy.mil/rda/Pages/NMCARS.aspx
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
252.222-7000 RESTRICTIONS ON EMPLOYMENT OF PERSONNEL (MAR 2000)
(a) The Contractor shall employ, for the purpose of performing that portion of the contract work in the State of Hawaii, individuals who are residents thereof and who, in the case of any craft or trade, possess or would be able to acquire promptly the necessary skills to perform the…