This amendment modifies a solicitation for two 120-ton overhead bridge cranes at Explosive Handling Wharf Building No. 1 at Kings Bay, Georgia. The amendment extends the proposal due date from May 6, 2020 to May 13, 2020 at 5:00 PM Eastern Time in response to inquiries. Offerors must submit proposals electronically via DoD Safe in separate parts for price and non-price factors by the amended due date. Joint ventures must include teaming agreements and letters of commitment with proposals. The Navy seeks these cranes to handle ordnance at the specified wharf building.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Extend Proposal Due Date
Amendment 0006 is issued to:
1) Revise SECTION A - SOLICITATION/CONTRACT FORM to extend the proposal due date
2) Revise SECTION L2 - PROPOSAL SUBMISSION INSTRUCTIONS
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-May-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247020R1001
X 9B. DATED (SEE ITEM 11)
20-Feb-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
05-May-2020
CODE
COMMANDER NAVFAC ATLANTIC
NAVY CRANE CENTER
NORFOLK NAVAL SHIPYARD
BLDG 491
PORTSMOUTH VA 23709-5000
N62470 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6247020R1001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 06-May-2020 05:00 PM to 13-May-2020 05:00 PM.
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
L1 INQUIRIES OR QUESTIONS
Inquiries and questions on this Request for Proposals shall be submitted in writing electronically to the Contracting Officer, Lisa Sumpter at lisa.sumpter@navy.mil and Mikel Outen at mikel.outen@navy.mil. See solicitation Section J, Attachment D, for the pre-proposal inquiry form.
All inquiries or questions must state the solicitation number and clearly state the question and solicitation/spec reference.
The deadline for submitting pre-proposal inquiries is 14 calendar days prior to proposal due date.
L2 PROPOSAL SUBMISSION INSTRUCTIONS
1. Time and Date for Receipt of Proposals
A. Technical and price proposals shall be submitted no later than the date and time provided in Block 9 of the Standard Form 33 “Solicitation, Offer, and Award.” Proposals not received on or before the hour and date set forth will be handled in accordance with FAR provision 52.215-1 “Instructions to Offerors – Competitive Acquisition.”
B. Proposals shall be submitted to the following address:
If sent by mail or private courier:
Director, Navy Crane Center Attention: Ms. Mikel Outen Naval Facilities Engineering Command Building 491 Portsmouth, Virginia 23709-1044
You are required to submit both price and non-price final proposal revision in electronic format. The Contract Specialist will send you a “Request for Drop-off” from the DoD SAFE application. Please send an email to mikel.outen@navy.mil and lisa.sumpter@navy.mil and advise of the email address that will be used. Following receipt of the email address, a request for drop off will be sent, and the Government will confirm that it has been received. Please submit your full proposal via the DoD SAFE application. The DoD SAFE application has a 25 file limit for upload and 8GB file size limit. Please plan accordingly. No hard copy submissions will be accepted.
B. Proposals shall be submitted electronically, in two readily severable parts (Part I Price and Part II Non-Price), via a single DoD Safe transmission using the following instructions:
1) Offerors shall notify the Government of their intent to submit a proposal via email to Ms. Mikel Outen (mikel.outen@navy.mil) with cc: to Ms. Lisa Sumpter (lisa.sumpter@navy.mil) no later than 5 PM Eastern Time, April 29, 2020 7 May 2020. As part of this email, Offerors shall provide a name and email address for the Request for Documents. Notifications of intent to submit a proposal that are received after the date established in this paragraph shall not be considered.
2) A Request for Documents will be initiated by Ms. Outen and sent via DoD Safe to Offerors that provided notice of their intent to propose. The Government will confirm with Offerors that the Request for Documents was received. The Request for Documents is an email from DoD Safe to Offerors with a link that shall be used to transmit proposal documents via DoD Safe (the link will be active for 14 days, but Offerors must transmit their proposals by the proposal due date and time, see below).
3) Offerors shall use the link provided in the DoD Safe Request for Documents email to transmit their proposal. Please note: Offerors may be required to copy and paste the link in their browser if selecting the link in the email does not work. Offerors shall transmit their proposals, using these instructions, by the date and time provided in Block 9 of the Standard Form 33 “Solicitation, Offer, and Award,” as amended (see Amendment 0003). Offerors must allow adequate transmission time to ensure timely receipt of proposals.
4) The DoD SAFE application has a 25 file limit for upload and 8GB file size limit. Please plan accordingly. No hard copy submissions will be accepted.
2. Proposal Format Offerors must submit required information for non-price (technical and past performance) and price proposals as follows:
The Non-Price (technical and past performance) and Price Proposals shall be submitted in separate binders, tabbed appropriately, and must include a cover page with the name of the prime contractor, addresses, phone and fax numbers, e-mail addresses, solicitation number, DUNS number, and point of contact. Should there be a discrepancy between paper and electronic information provided, the paper copies shall govern. Offerors are requested to number the pages consecutively for each factor.
Each volume of the proposal shall be submitted in accordance with the solicitation submittal requirements presented under Price and Non-Price Factors. Proposals are to be neat, legible and orderly. Content is more important than quantity. A concise and comprehensive proposal is desired. Organization, clarity, accuracy of information, relevance, and completeness are of prime importance. Statements such as “will comply”, or “noted and understood”, without supporting narrative to define compliance are not acceptable. Cursory responses or responses which merely reiterate or reformulate solicitation language will not be considered as satisfying the requirement of the RFP or as demonstrating the ability to perform. Elaborate brochures or other presentations beyond that sufficient to present a complete and effective proposal are not desired. Elaborate artwork and expensive visual or other presentation aids are not necessary.
Do not include exceptions or conditions to the terms and conditions of the solicitation in either the non-price or price proposal. Should the offeror include any standard commercial or company terms and conditions that conflict with the terms and conditions of the solicitation the offeror may be determined “unacceptable” and thus ineligible for award. Should the offeror have any questions related to specific terms and conditions of the solicitation, these should be resolved prior to submission of offers, via the pre-proposal inquiry process.
Details concerning how the proposal will be evaluated are covered in Section M of the RFP.
3. Joint Venture and Team Arrangements—FAR Subpart 9.6 defines contractor team arrangements. Contractor team arrangements mean (1) two or more companies form a partnership or joint venture to act as a potential prime contractor; or (2) a potential prime contractor agrees with one or more other companies to have them act as its subcontractor under a specified Government contract or acquisition program.
All offerors proposing team members, a joint venture, key “team” subcontractor(s) (a key “team” subcontractor is defined as a subcontractor who in a “team” approach will perform significant/critical aspects of work under the proposed contract on a consistent basis, or on a consistent overflow basis), other subcontractors, and/or other entities
(subsidiary/affiliate/parent/LLC/LTD member companies whose names are not exactly as stated on the SF33) upon whose resources the offeror relies on in response to a factor or subfactor requirement of this proposal, experience provided under Factor 1 (Corporate Experience), shall submit the following information in the front of both the technical and price proposals:
1. Provide a listing of the team members’ corporate name (no abbreviations), address, point of contact, phone number, DUNS Number, and CAGE Code. Provide this information in technical and price proposal.
2. Submit a copy of the joint venture agreement, other teaming arrangement agreement, or signed binding letter of commitment from each team member. For subcontractors, the offeror shall also provide an explanation of the meaningful involvement that the subcontractor will have in performance of this contract.
All joint ventures, teaming agreements, and letters of commitment shall: (1) clearly identify the expected relationship, role and responsibility between the firms or of the subcontractor or other entity (type and proportion of work to be performed); and (2) shall be signed by the appropriate individual(s) of each firm.
Copies of joint venture agreements, teaming agreements, and letters of commitment shall not be applied against the overall 75 page limit under the technical proposal.
(End of Summary of Changes)