About this file

N6247018R4007_Amendment_0004.pdf

View the file

Other files

File Type Posted
SPEC_01_14_00_-_Amendment_0004.pdf PDF
N6247018R4007_Amendment_0003.pdf PDF
N6247018R4007_Amendment_0002.pdf PDF
N6247018R4007_Site_Visit_Sign-In_Sheet.pdf PDF
N6247018R4007_Site_Visit_Presentation.pdf PDF
18R4007_Amendment_0001.pdf PDF
Att_A_Const_Exp_Data_Sheet.docx DOCX document
Att_E_Schedule_B.docx DOCX document
Att_F_P911_4of7.pdf PDF
Att_(B)_PPQ.docx DOCX document
Att_(C)_Visitor_Pass.xls XLS spreadsheet
Att_(D)_PPI_Log.xlsx XLSX spreadsheet
N6247018R4007_Solicitation.pdf PDF
N6247018R4007_N6247018R4007_Pre-Solicitation_Notice.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0004 is being issued for the follow ing reasons:

1.To provide the below technical revisions and associated attachment.

2.To respond to pre-proposal inquiry.

3.To add clause 52.204-2 Security Requirements (Aug. 1996), Alt II (Apr 1984).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Aug-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247018R4007

X 9B. DATED (SEE ITEM 11)

18-Jun-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Aug-2018

CODE

COMMANDER NAVFAC ATLANTIC

6506 HAMPTON BLVD

NORFOLK VA 23508-1278

N62470 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6247018R4007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0004

Amendment 0004 is being issued for the following reasons:

1. To provide the below technical revisions and associated attachment.

2. To respond to pre-proposal inquiry.

3. To add clause 52.204-2 Security Requirements (Aug. 1996), Alt II (Apr 1984).

1. To provide the following technical revisions.

Project Titles: P-119 Construct Hydrant System, P-911 Aircraft Parking Apron NSA Souda Bay, Greece Date: 08/02/18 Drawing Revisions On NAVFAC Drawing No. 14061355 (C-505, P-119), DETAIL D1 DELETE the text “…5100 LONG…” and replace with the text “…500 LONG…”.

Specification Revisions

DIVISION 01 – GENERAL REQUIREMENTS

SECTION 01 14 00 WORK RESTRICTIONS

DELETE the entire section.

ADD the attached Revised Section 01 14 00.

2. To respond to pre-proposal inquiries.

PPI

REFERENCE QUESTION

RESPONSE Page Section Para.

27 Drawing

C-505 Dowel is referred to as 5100 mm.

Should this be 510 mm?

Dowel should be 500 mm. Please see drawing revision above.

SECTION 01 00 00 - GENERAL REQUIREMENTS

The following have been added by reference:

52.204-2 Alt II

(End of Summary of Changes)