Final Pre-Proposal Conference - 26APR2011 Rev 3.ppt

PPT presentation 3 MB Posted

Attached to
NAWCTSD Training Data Products Contract (TDPC) Federal contract opportunity
Solicitation number
N61340-11-R-0010
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

About this file

Slide presentations from the TDPC pre-proposal conference on 26 April 2011 in Orlando FL.

View the file

Other files for this federal contract opportunity

Other files attached to NAWCTSD Training Data Products Contract (TDPC), newest first.
File Type Posted
TDPC Info Only Memo.doc DOC document
Amendment 4 to TDPC RFP N61340-11-R-0010.doc DOC document
Q-Rs_Amendment_4_Attch_Round_4.pdf PDF
Attachment —
Attachment_(12)_Oral Presentation Planning Sheet.xls XLS spreadsheet
Conformed TDPC RFP N61340-11-R-0010 Amendment 3.docx DOCX document
Q-Rs_Amendment_3_Attch_Round_3.pdf PDF
Attachment —
Attachment —
Attachment —
Attachment —
Q-Rs_Amendment_2_Attch_Round_2.pdf PDF
Amendment 2 to TDPC RFP N61340-11-R-0010.doc DOC document
Conformed TDPC RFP N61340-11-R-0010 Amendment 2.doc DOC document
Attachment —
Attachment —
Conformed TDPC RFP N61340-11-R-0010 Amendment 1.docx DOCX document
Amendment 1 to TDPC RFP N61340-11-R-0010.docx DOCX document
Q-Rs_Amendment_1_Attach_Roiund_1 —
Attachment —
Pre-Proposal_Conference_Attendee_List_4-26-11.xlsx XLSX spreadsheet
Attachment —
Attachment —
Attachment —
Attachment —
N61340-11-R-0010_TDPC_RFP_11Apr11.docx DOCX document
Attachment —
Attachment —
Attachment —
Attachment —
Round 5 QAs.docx DOCX document
TDPC Schedule Change Notice 03-24-11.doc DOC document
TDPC DRAFT_SOW_Feb11.docx DOCX document
TDPC Schedule Change Notice 01-20-11.doc DOC document
Round_4_Q As_TDPC.doc DOC document
TDPC Schedule Change Notice 12-16-10.doc DOC document
TDPC Change-Update Notice.doc DOC document
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE: *

Pre-Proposal Conference

Training Data Products Multiple Award Contract (TDPC)

Welcome Aboard/General Overview Ms. Aida Matta Training Data Products Contract

(TDPC)

Program Manager

Introductions

Leadership in Attendance
Government TDPC Integrated Project Team (IPT)
CDR Francisco Silebi, Program Director
Ms. Aida Matta, Program Manager
Mr. Thomas Courtney, Contracting Officer
Ms. Lari Manning, Instructional Systems Specialist
Mr. Ralph Soberal, Contract Specialist
Ms. Argentina Thompson, Small Business
Geoffrey Chun, Legal Counsel

Agenda

0800-0830 Welcome Aboard/General Overview – Aida Matta

0830-0900 Administrative/Terms and Conditions - Ralph Soberal

0900-0930 Source Selection Overview– Tom Courtney

0930-1000 Past Performance and Experience– Lari Manning

1000-1015 Break

1015-1045 Technical – Lari Manning

1045-1115 Price – Ralph Soberal

1115-1130 Open Discussion

1130 Adjourn

Please silence all cell phones, BlackBerry’s, etc.

No recording devices

Restroom locations

Today’s attendees’ list will be posted on the NAWCTSD and FedBizOpps websites

Welcome to the Naval Air Warfare Center Training Data Products Contract Pre-Proposal presentation

Mission NAWCTSD is the principal Navy center for research, development, test and evaluation, acquisition and product support of training systems;

We provide Interservice coordination and training systems support for the Army and Air Force, and we perform such other functions and tasks as directed by higher authority.

(OPNAVNOTE 5450 - 8 Sep 93)

Naval Aviation

Non-Aviation

Non Navy

NAVY

TDPC

TDPC Strategy Functional Area I Analysis, Design, and Evaluation Functional Area 2 Development, Production, and Implementation Functional Area 3 Sustainment Small Businesses Revenue standard - $27 Million.

LOT I - UNRESTRICTED

Functional Area I Analysis, Design, and Evaluation Functional Area 2 Development, Production, and Implementation Functional Area 3 Sustainment

LOT II - RESTRICTED

No size or revenue standard .

Scope of TDPC TDPC will procure both products and services Training products will be 80 - 90% of the contract The end-goal of the TDPC is to deliver current training systems including, but not limited to:

Traditional
Stand-Alone, NIPRNet, SIPRNet, and Web-Based
Virtual World (self-paced or instructor facilitated)
PC Simulation
PDA, Wearable Computers, Notebooks, etc.
Blended Systems
New and emerging products adaptable for training

Procurement Milestone Schedule

Sheet1

Milestone Completion Date

Release RFP 11-Apr-2011

Pre-Proposal Conference 26-Apr-2011

Solicitation Questions 6-May-2011

Proposals Due 26-May-2011

Oral Presentations Start 1-Jun-2011

Final Proposal Revision (FPR) Due 21-Nov-2011

Contract Award 23-Feb-2012

Sheet2

Sheet3

QUESTIONS?

Administrative/Terms and Conditions Mr. Ralph Soberal TDPC Contract Specialist

Communications Classification: UNCLASSIFIED

FAR 15.201, “Exchanges with industry before receipt of proposals”

Presolicitation Conferences constitute an Informal Exchange of Information Insight into Government plans No Guarantee as to Government’s final course of action To improve the understanding of Government requirements and industry capabilities, thereby allowing potential offerors to judge whether or how they can satisfy the Government’s requirements, and enhancing the Government’s ability to obtain quality services, at reasonable prices, and increase efficiency in proposal preparation, proposal evaluation, negotiation, and contract award.

Formal RFP is the only contract action to allow industry to formally respond with a proposal

Rules of Engagement All information released during this conference is to be considered for informational purposes only

Internal source selection plans and procedures will not be discussed

Unless an amendment is issued, no communication today between industry attendees and individual Government personnel either modifies or changes the solicitation

Guidelines & Information Please save your questions until the end of each section in the presentation. A “Question” slide will prompt you

The Government reserves the right to request any question be submitted in writing

Due to time constraints, not all questions may be answered today

Questions not answered today will be reviewed and may be answered and posted on the website or otherwise incorporated into the solicitation documents

All documents will be issued on the web at http://nawctsd.navair.navy.mil under Business Opportunities and https://www.fbo.gov under Federal Business Opportunities

Follow-on Communications

All follow-on communications shall be coordinated via the Contracting Officer, with the primary POC being the Contract Specialist below

Contracting Officer: Mr. Thomas Courtney (AIR 2.5.3.2.1)

- Telephone No: (407) 380-4108

- Email: thomas.courtney@navy.mil

Contract Specialist: Mr. Ralph Soberal (AIR 2.5.3.5.2)

- Telephone No: (407) 380-4077

- Email: rafael.soberal@navy.mil

Disclaimer Today’s remarks by Government officials involved in the TDPC Multiple Award Contract solicitation shall not be considered a guarantee of the Government’s course of action in proceeding with this or any other solicitation

The information shared today reflects current Government intentions and is subject to change based on a variety of circumstances, including internal and external comments and reviews

The formal Request for Proposals is the only document that shall be relied upon in determining the Government’s requirements

Page * Solicitation (Standard form 33) Return completed signed copy (Volume 4 - Other) Block 12 - Minimum 270 days In Accordance With (IAW) Section L, paragraph A3.5 Minimum Offer Acceptance Period Block 14 (Acknowledgement of Amendments; include signed copies of SF 30s) Block 15A – 18 (Offeror Information and Endorsement)

Page * Section B Highlights – Supplies or Services and Prices No pricing provided at the MAC Level CLIN structure will be reflective of MAC basic award

1st Digit (LOT) : 1 = LOT I; 2 = LOT II
2nd Digit (Ordering Period): 0 = Base Ordering Period; 1, 2, or 3 for each successive option
3rd Digit (Contract Type): 1 = Firm-fixed-price (FFP); 2 = Fixed-price-incentive (FPI); 3 = Cost-plus-fixed-fee (CPFF); 4 = Cost-plus-incentive-fee (CPIF)
4th Digit (Functional Area): 1, 2, or 3 for the applicable Functional Area.

Example: 2011 = Lot II; Base Ordering Period; FFP contract; for Functional Area 1. Will also result in 2111, 2211, and 2311 optional ordering periods.

MAC ceilings:

$780M – Combined Unrestricted (LOT I) and Restricted (LOT II) MACs $1K - Guaranteed minimum (Regardless of number of awards)

Page * Section C Highlights – Descriptions and Specifications

C2. DESCRIPTION OF LOT I AND LOT II

LOT I – Materialized Requirements of Greater Complexity LOT II – Materialized Requirements of Lesser Complexity Opportunity to participate in DO/TO procurements Determination of requirements to LOT I or LOT II at DO/TO level Small Business would be competitive in terms of Market Prices, Quality, and Delivery For cross Functional Area (FA) requirements must have ticket for all FAs Table indentifies qualified Functional Area(s) of award

Page * Section D – Packaging and Marking Section E – Inspection and Acceptance

Section D – Packaging and Marking

Basic MAC does not require delivery of any product or service; instructions for proposal packaging and marking provided in Section L Specific instructions for requirements will be provided at the DO/TO level

Section E – Inspection and Acceptance

Basic MAC does not require inspection and acceptance of any product or service; proposal acceptance is provided in Section L Specific instructions for inspection and acceptance will be provided at the DO/TO level

Page * Section F Highlights–Deliveries or Performance Period of Performance

MAC Commences on date of award and may be extended in accordance with option provision POP on DO/TO may extend beyond ordering period; in no case will DO/TO performance date exceed 11 years from date of MAC basic award

Ordering Periods

Base Ordering Period – 60 Months Options – 12 Months (3 Options)

Page * Section G Highlights–Contract Administration Data

NAVAIR Clause 5252.201-9502 - Provide in Volume 4 – Other

Contractor Authorized Contract Coordinator
Technical Representative

Page * Section H Highlights- Special Contract Requirements 5252.216-9508 Minimum Guarantee Small Businesses obtaining award in both LOTs any Functional Areas will only receive one Minimum Guarantee ($1,000)

H.3 Award of DO/TO on LOT II Set-Aside Basis Provide maximum practical opportunities to small businesses Small business goals published on NAWCTSD Business Opportunities Website Partial Set-Aside; Determined after market research Failure of small business to respond to market research inquiry may result in assignment to LOT I No set-aside within LOT I LOT II awardees will be required to satisfy at least 50% of the requirement IAW 52.219-14 Limitations on Subcontracting on a DO/TO basis

Page * Section H Highlights- Continued H.4 Prime Contractor Subcontracting Restriction of subcontracting applies to the requirement ticket holders only (LOT and FA) Not applicable to LOT I requirements for LOT II only ticket holders Not applicable to LOT II requirements for LOT I only ticket holders Commercial items or support may be purchased from another ticket holder Not applicable to DO/TO issued pursuant to “Exception to Fair Opportunities”

H.7 Security Requirements FAR 52.204-2 comply with DoD Manual 5220.22M Anticipated up to the Level of TOP SECRET DD254 issued at DO/TO level

Page * Section H Highlights- Continued H.8 (b) All DO/TO are subject to the basic terms and conditions with limited exceptions Clauses relevant to specific contract types not included in DO/TO FAR 52.222-46 Evaluation of Compensation for Professional Employees FAR 52.216-16 Progress Payments FAR 52.232-32 Performance Based Payments

H.10 Clause Modifications Reserve the right to add, delete, and/or modify clauses on individual DO/TO

Page * Section H Highlights- Continued H.11 Addition of Contractors During Life of ID/IQ Contract Maintain presence of both large and small businesses contractor base Periodically determine whether to add LOT I or LOT II, by Functional Area or any combination thereof Small businesses merging or being acquired (FAR 51.219-28 re-representation) Unable to re-represent as small business (FAR 52.219-28) TDPC prime contractor performance history Experienced levels of DO/TO competition Emergence of capable firms Any other consideration in Government’s best interest

Failure to re-represent will render awardee ineligible for additional LOT II awards (N/A to LOT I)

Page * Section H Highlights- Continued H.12 Small Business Subcontracting Plan Large Businesses Only Approved by PCO All elements of plan with the exception of goals and companies Not part of the tradeoff Communications regarding subcontracting plan not considered discussions 2 part frame work (complete 2nd part at DO/TO level) Do not confuse with small business participation (referred to as small business utilization strategy in Sections L & M) H.14 Maximum Profit /Fee Rate Table outlines maximum for DO/TO and Modification by Contract Type Maximum pass through on Subcontracts Travel on Cost Reimbursable basis is 0.0% Applicable to all DO/TO requirements (including competitive)

Page * Section I Highlights – Contract Clauses

FAR 52.203-2 Cert of Independent Price Determination FAR 52.204-7 Central Contractor Registration (must be registered to include NAICS Code 541330) FAR 52.219-4 Notice of Price Evaluation Preference for HubZone Small Business Concerns under LOT I (10% increase LOT I large businesses) FAR 52.219-14 Limitation on Subcontracting (LOT II 50% rule)

Section I Highlights – Continued

FAR 52.219-28 Post Award Small Business Program Rerepresentation Applies (long term contract over 5 years) 30 days from novation agreement 30 days after merger or acquisition 60-120 days prior to end of fifth year 60-120 days prior to exercise of options Fill in information for clauses incorporated by reference under Section I is included at the end of Section I under “Section I Clause Details”

Page * Section J – List of Documents, Exhibits and Other Attachments Section K – Representations, Certifications and Other Statements of Offerors

Section J - Attachment(s) 3, 4, and 5 to be provided before oral presentation(s)
Section K – Representations, Certifications and Other Statements of Offerors to be provided in Volume 4 – Other section

Page * Section L Highlights – Instructions, Conditions, and Notices to Bidders

A1.0 General:

A1.1 Proposal Format

8.5 X 11; Arial 12 Pt Font; 1 inch margins

Each volume separate binder Page number by Functional Area (FA) FA 1, Page 1 – 1-1 Original and 4 copies paper 4 CD-ROMs (Separate Price Master and Back-up)

A1.3 Microsoft (MS) 2007 Applications MS Office and MS Visio

A1.4 Hyperlinks No hyperlinks Volumes 2, 3, and 4. Hyperlinks allowed in Volume 1 for ease of movement No marketing information

Page * Section L Highlights – Continued

A1.0 General (continued):

A1.5 Virus Free Electronic Submissions A1.6 Multimedia No sound graphics or video embedded A3.0 Proposal Submission:

Clearly mark packages with solicitation number and submit no later than date on block 9 of SF 33.

No Fax or electronic submission Mailed or hand carried Hand carried need visit request submitted no later then two business days prior Contact myself or alternate Mr. Thomas Courtney (must be hand delivered) Give yourself plenty of time for gate entry and processing

Page * Section L Highlights – Continued

A3.0 Proposal Submission (continued):

A3.1 Proposal packaging In cartons or equivalent in most efficient manner Packing slip Marked “For Official Use Only” “Source Selection Information – See FAR 2.101 and 3.104” A3.2 All proposals must be UNCLASSIFIED A3.3 Solicitation changes (see notification website) A3.4 Solicitation questions submitted via email utilizing Attachment (2). Last date for submission is May 6, 2011 Government reserves the right not to respond to late question submissions A3.5 Minimum offer acceptance period (input in Block 12 SF33 minimum 270 days) If longer specify in clause and include in Volume 4 – Other Pre-proposal conference slides and attendee list will be posted to solicitation notice following conference

Page * Section L Volume 4 Other B5.2.1 Terms and conditions, assumptions, Exceptions, Deviations, or Waivers Certification – to terms and conditions, exceptions, or deviations If proposed, may cause to be deficient Exception – will not comply with requirement Deviation – will not comply with requirement but proposes alternative to meet intent Waiver – request authorization to depart from specific requirement but would be considered suitable Provide detail description if proposed if none state so.

B5.2.2 Adequacy of Accounting System Provide a statement defining the most recent of determination Identify the verifying Government agency If not, may be ineligible to receive cost reimbursement type DO/TO and progress payment arrangements under fixed-price contracts until obtained

Page * Section L Volume 4 Other (Continued) Other Data Signed SF33 basic and each amendment Signed representations, certifications, and acknowledgements or ORCA reference Completed Clause from Section L, A3.5 Minimum Offer Acceptance Period, if SF33 block 12 is longer than 270 days Information to populate Section G 5252.201-9502 (Contractor POC) Small Business only - Selection of Lot I and/or Lot II Large Business only - Small Business Master Sub Subcontracting Plan

Source Selection Overview Mr. Thomas Courtney TDPC Contracting Officer

Source Selection Objectives Choose the contractors who provide the best value to the Government, all factors considered.

Obtain through use of a comprehensive evaluation process, a high quality, fair and consistent evaluation of proposals.

Generic Source Selection Process

Req’ts Developed Plan the Approach Acquisition

Strategy/Plan

SSP

Market Research & Early Exchanges w/Industry

SOW
P-Spec

Draft RFPs

One-on-ones

Industry Days

Tech. Library

Receive Proposals Compare Proposals Discussions w/ Offerors (ENs) Complete Discussions (PCO) Evaluate Proposals Set Competitive Range

(PCO)

(or SSA Selects Source) Evaluate FPRs Request Final Proposal Revision (FPRs) Debrief Contract

SSAC

The Source Selection Process

SSA

SSAC

SSA

SSAC

SSA

SSA

SSAC

DECISION

Formal

RFP

Technical Exp Past Perf Price

Page * Sections L and M Understanding and following Sections L&M are the keys to developing a good proposal; a mutually beneficial goal for award

Proposal Instructions – Section L of the RFP:

Tells Offerors what to put in the proposal

Evaluation Criteria – Section M of the RFP:

Identifies what will be evaluated

Page * Proposals

(a) There are 3 distinct Functional Areas within the TDPC statement of work for which an offeror may propose:
(1) Analysis, Design and Evaluation
(2) Development, Production and Implementation
(3) Sustainment
An offeror may propose to one or more Functional Areas. For each Functional Area to which an offeror is interested in proposing, the offeror is required to submit a distinct proposal addressing all 4 evaluation factors for that Functional Area.
No alternate proposals allowed

Page * Structure of this Evaluation Independent source selections x 6 Lot 1 x 3 Functional Areas Lot 2 x 3 Functional Areas

Independent best value / trade off decisions

Anticipate multiple awards per “pool” #s To allow robust competition at the order level

Page * Intent on Discussions… The Government reserves the right to conduct discussions; however, award may be based upon initial offers.

Don't assume you can improve your position during discussions, there may not be discussions.

Page * If Discussions…

Competitive Range Set (most highly rated; can limit based on efficiency) Evaluation Notices (ENs) sent (to offerors in the CR) As a minimum, notification of deficiencies and significant weaknesses Ask for additional information FPRs

Note WRT Technical: If discussions are held, a second Oral Presentation will not be conducted; instead, offerors will be given an opportunity to present (in writing) their mitigation for any weaknesses or deficiencies assigned based upon the oral presentation. However, this mitigation information may not be weighted as much as the information originally provided during the Oral Presentation.

If a competitive range is established, the Government may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

Page *

EXPERIENCE

(Performance Risk)

TECHNICAL

(Rating & Proposal Risk)

The Government shall place significantly greater emphasis on the offeror’s Technical Capability over its Small Business Utilization Strategy.

Evaluation Criteria

PAST

PERFORMANCE

(Performance Risk) Price ($$$) And, “All evaluation Factors other than Price, when combined, are significantly more important than Price.”

Page * Proposal Volumes

No page limits, however…
Subcontracting Plan (Annex A) – Lot 1, and only large businesses

In presenting material in the proposal, the offeror is advised that quality of information is more important than quantity. Clarity, brevity, and logical organization should be emphasized during proposal preparation and presentation.

Volume

Volume Title

CD ROM*

Written Copies Required

Technical

1 Master/1 Backup

1 Original/4 Copies

Experience

1 Master/1 Backup

1 Original/4 Copies

Past Performance

1 Master/1 Backup

1 Original/4 Copies

Price/Other

1 Master/1 Backup

1 Original/2 Copies

Volume 4 Annex A

Master Subcontracting Plan

1 Master/1 Backup

1 Original/2 Copies

Page *

B1.2 SMALL BUSINESS UTILIZATION STRATEGY (LOT I OFFERORS ONLY)

For each Functional Area proposed, the LOT I offerors shall describe their Small Business Utilization Strategy for implementation of the following elements for the individual DO/TO:
(1) The process that will be used to determine the complexity and variety of the work small firms are to perform; and
(2) The process that will be used to ensure maximum practicable utilization of small firms for each DO/TO.

Who submits this? Answer: Lot 1 only, and from both large and small businesses

Note: Identification of specific small business utilization and goals will be proposed & evaluated at the DO/TO level as requirements materialize.

Page * Summary The Source Selection process will assure that your proposal will receive a fair and consistent evaluation and consideration for award

L&M is intended to help you provide us with your best value solution and instruct you in preparing a proposal that will facilitate our evaluation

Keys to Developing a Good Proposal Understand the RFP requirements Understanding the Evaluation Criteria will help you know where to place emphasis in your proposal Follow the Proposal Instructions – Provide material where requested

Ensure that your proposal Helps the evaluator evaluate - don’t make us have to guess or search for answers Provides substantiation for what you propose – give us a reason to believe you

TDPC Past Performance, Experience & Technical Proposal Requirements Lari Manning Instructional Systems Specialist

TDPC – SCOPE OF WORK

Functional Area 1 Scope of Work NOTE: This is not a complete list of processes.

Analysis, Design and Evaluation

Analysis
Front End Analysis
Mission / Job / Task Analysis
Cognitive Task Analysis
Top Down Functional Analysis
Use Case Scenarios
Gap Analysis
Root Cause Analysis
Analysis of Alternatives
Problem Analysis
Baseline Comparison System
Technology Assessments
Design
TSRA
Training Task Analysis
Learning Analysis
Learning Objectives Design
Curriculum Outline Design
Scenario Design
Media Selection
Cost and Trade-off Analysis
Training Systems Functional Description
Evaluation
Evaluation Plans
Formative/Summative
Operational
Training Effectiveness Evaluation

Functional Area 2 Scope of Work NOTE: This is not a complete list of processes.

Development, Production and Implementation

Production/Work Plan
Implementation Plan
Test Plan
Prototypes
Scripts/Storyboards
Group and Self-Paced Training
Learner Assessments
Job Aids
Electronic Performance Support Systems
Hardware Delivery Systems
Electronic Classrooms
Learning Resource Centers
PDAs
Other

Functional Area 3 Scope of Work

Identify, analyze, design, cost, develop, produce and implement training system modifications, upgrades or enhancements due to:
Engineering Change Proposals (ECP)
Training Change Requests (TCR)
Rapid Engineering Maintenance Engineering Change (RAMEC)
Modernization Program
Service Life Extension Program (SLEP)
New & Emerging Technology
Software Upgrades
Policy, Guidance, Standard Operating Procedures, or Doctrine/ Tactics
Training Location, Manpower, Personnel, Facilities, Equipment or Resource Changes

Sustainment NOTE: This is not a complete list of processes.

SOW Changes - Systems Engineering Technical Review Process (SETR)

SETR - required by NAVAIR Instruction 4355.19D
TSD currently mapping processes to employ SETR reviews for all products, including ISD
SETR is currently not an evaluation factor
Will be applied at the Delivery/Task Order Level

TDPC DEFINITIONS -WORK COMPLEXITY

What is “Work Complexity”?

Standardized process to define program risks during acquisition planning
Used in concert with Marketing Research (FAR Part 10) output data
Helps establish the work as being in scope of either Restricted or Unrestricted MAC
Standardized job aid providing cues to IPT for Functional Area cost, schedule and performance risks
Supports the team in defining potential impact of technical requirements, manpower, personnel, data, resource, budget, schedule and other risks on the program

Work Complexity Guidelines Functional Area 1: Analysis, Design and Evaluation Complex

Analyses for weapon system acquisition (pre-MS A to MS C)
Human engineering analyses
Efforts where Subject Matter Experts (SMEs) do not exist
Large scale - manpower intensive with short schedules
More than one job or training site
One job with multiple positions, multiple jobs with one position each, or multiple jobs with multiple positions
Jobs and positions having multiple qualifications, certifications, or licenses (QCL)
Multiple missions and/or courses of instruction
Medium to high technical, cost and schedule risks

Non-Complex

Jobs that currently exist and are defined in the field
One job, with one position
One job, having one training site
One level of QCL
Single mission or single course of instruction
Readily available SMEs in the field
Small manpower requirements, with long lead times
Low technical, cost and schedule risk

Work Complexity Guidelines Functional Area 2: Development, Production and Implementation Complex

Weapon system acquisition (pre-MS A to MS C)
Development more than 80 hours of content
Development more than 40 hours of content having medium to high technical, cost, or schedule risk
Proprietary or specialized software requiring special training
Limited availability of personnel
Large scale, manpower intensive tasks having short schedules
Data immature and not available
Production of high levels of learning for knowledge (problem solving), skill (readiness, mechanism, adaptation and origination), and attitudes (receiving, responding, valuing, competence and innovation)
Medium to high degree of physical and functional fidelity
Simulation and simulation gaming as a strategy
New development of IETMs, technical publications, and integrated training and technical documentation/publications (performance support systems)

Non-Complex

New development for already implemented training systems (DODI 5000.02 model post-MS C, Operation and Support Acquisition Phase)
Development of less than 80 hours of content having low schedule risk
Use of two-dimensional and three-dimensional (2D and 3D) animations and graphics only. Has no simulation or simulation gaming requirements
Simulation with low degree of physical and functional fidelity
Requires production of only lower levels of learning to include knowledge (fact, rule and discrimination) and skill (perception, gross motor skills, and continuous movement)
Commercial Item software and hardware
Data available and mature
Manpower requirements small with long lead times
Low technical, cost and schedule risks
Development of stand-alone job aid, checklist or decision aid

Work Complexity Guidelines Functional Area 3: Sustainment Complex

Unknown, ill defined, or ever changing requirements
Unknown changes greater than known changes
Medium to high performance/technical risk
Medium to high cost risk
Medium to high schedule risk
Tasks requiring an Earned Value Management System
Technical data is immature and not readily available
SMEs may not be readily available
Rapid tactics changes
Requires large amounts of technical data
Sustaining training at multiple sites
Sustaining multiple courses of instruction across a training continuum
Upgrading hardware and software delivery systems to meet new policy, guidance or standards
Support deployable training systems or training conducted at forward deployed/ embarked locations
Update of existing IETMs, technical publications and performance support systems to meet Engineering Change Proposals (ECPs), technical directives, policy or standard operating procedure changes

Non-Complex

Documented list of required changes (known requirements)
Production requirements fixed based on known list of changes
Workforce fixed based on known list of changes
Low performance/technical risks due to Government defined changes
Low cost and schedule risks due to Government defined changes
Technical data readily available
SMEs readily available
Requires defined changes to training at one site
Required defined changes for one course of instruction or part of one course

What IS Relevant?

Previous federal, state or local Government contracts and private/commercial contracts similar to this solicitation and no older than five years from the TDPC proposal due date
Information older than 5 years will not be considered relevant
Contracts beginning before the five year period but ending during the five year period will be considered in whole.
Recent contracts will be considered more relevant than older contracts.
Should be related to similar programs in the same division, or price centers in which the offeror proposes to perform this effort
Past performance and Experience must be gained through contracted work vice the experience of its personnel
Past Performance and Experience submittals should be the same contracts

What IS Relevant?

Work may be from a previous contract as a prime, subcontractor or joint venture
The offeror shall not describe project work performed by other team members, subcontractors, or by individual employee’s experience from previous employment
Work must be performed by the company proposing on the TDPC

What IS Relevant?

A logical connection with the matter under consideration to include:
ISD Phases
Work processes and sub-processes within a Phase
Training products being delivered
Work assigned between prime and subcontractors
Relevant projects must require the delivery of products specifically geared to training
Training is defined as the events and activities designed to facilitate the learning and development of new and existing skills for the purpose of improving job performance

What is NOT Relevant?

Does not include:
Development of training devices or simulators
Teaching or Facilitating
Contractor Support Services (CSS)
Schoolhouse management, administration or staff work
Education
Work augmenting a team
Body shops
Summary of employees’ career experiences while working outside the company

What IS Relevant in Functional Area 1?

Relevant

Identify the need or gap and the subsequent processes to design a training intervention or performance support system
Design of training alternatives and training delivery methods, media, strategies, fidelity levels, and interactivity requirements to fill a performance gap, solve a performance deficiency or provide the training /support required to ensure employees can perform work in the intended environment, to the required proficiency
Evaluation of training

Not Relevant

Pass through of work that does not require the offeror to perform Functional Area 1 processes and sub-processes including Program Management, Front End Analysis, Training Systems Requirements Analysis, Evaluation, Configuration Management and Quality Control of the intermediate products
Development, Production, and Implementation of Direct and Indirect training solutions

What IS Relevant in Functional Area 2?

Relevant

Development, Production and Implementation of new training solutions
Management of multiple production teams working concurrently to produce, deliver and install a fully operational training system that will deliver, track, report, schedule, and manage learning as well as the training system
Production of training solutions requiring integration with a Learning, Training or Content Management System

Not Relevant

Pass through of work that did not require the offeror to perform Program Management, production of group and self-paced training solutions, and development, installation and test of the integrated training system
Purchase of training system HW and SW
Previous contracts supporting realignment of an organization, modification of organization mission/vision/goal statements, or the modification of operating procedures, policy or doctrine

Relevant A previous contract that required the full ISD model to be applied to identify, design, develop, implement and evaluate change or an approach that required only production and implementation of customer identified changes are both considered relevant work

Not Relevant Pass through of work that does not require the offeror to perform Functional Area 3 processes and sub-processes including Program Management, analysis, design, production, integration and evaluation of an existing training system is not relevant

All work must be for the sole purpose of maintaining currency of the total training system through the application of the ISD model

What IS Relevant in Functional Area 3?

TDPC – EXPERIENCE REQUIREMENTS

Experience Section L Requirements

For each Functional Area proposing to, provide information on Attachment 6 – Experience Input Form
Submit only contracts meeting definition of relevancy for each Functional Area
Identify project experience as Prime, Subcontractor or Joint Venture Member
Do not claim work performed by other team members
Do not claim work performed by employees while employed by other companies or organizations
Government will contact other team members and government representatives to verify work assignments
Contracts crossing Functional Areas should complete separate Experience Input Form for each Functional Area being proposed to

Experience Section M

Government will evaluate relevant experience on basis of breadth, depth and similarity of work required on TDPC
A balance between types, numbers of processes demonstrated along with complexity of contract will form the basis for overall performance risk rating
Complexity determination will apply definitions of complexity found in SOW
Lack of relevant experience may be considered a weakness and may not result in an adverse rating

Experience Section M

A small business may elect to compete for both the Restricted and the Unrestricted MACs
Due to the definitions of complexity, a low risk performance rating on LOT II (Set-Aside) contract does not necessarily mean offeror will have the same rating for LOT I (Non Set-Aside)

Experience Section M

Functional Area 1
Greater emphasis will be placed on Analysis and Design, than on Evaluation
Functional Area 2
Greater Emphasis will be placed on Development and Production, than on Implementation
Functional Area 3
Greater emphasis will be placed on Analysis, Design, Development, Production and Evaluation, than on Implementation

TDPC – PAST PERFORMANCE REQUIREMENTS

Past Performance Section L

Submit the following for each Functional Area being proposed to:
Attachment 7 Past Performance contract List
List Past performance contracts along with summary information to include contact information for any past Performance and CPARs update Questionnaires sent out
Provide information on show cause notices, cure notices, or termination for default on any contract that has occurred in the last 5 years
If none, state there are none

Past Performance Section L For each Functional Area proposing to, provide evidence of your organization’s ability to perform relevant work List a minimum of 5 of the most relevant contracts performed within 5 years of the proposal submission

List from most relevant to least relevant
JV should submit 5. If 5 are not available from the JV, each JV member can individually submit up to 5, in addition to JV submittal

Past Performance Section L

Attachment (8) Past Performance Individual Contract Information
Provide past performance information by individual contract to include areas to include:
Contract data
Relevancy description and rationale
Past performance
Systemic Improvements
Attachment (9) CPARS Update Questionnaire
Submit to customers for past performance information for contracts with CPARS 6 months old; completion dates more than 6 months before the due ate for this Past Performance Volume

Past Performance Section L

Attachment (10) Past Performance Questionnaire
Submit Attachment 10 to customers for contracts that have no CPARS information
Submit to PCO, Administering Contracting Officer, Program Manager and Technical Lead for completion and return to government

Past Performance Section L

Government may also use information from other sources other than those identified by the offeror
Past performance Information Reporting Systems and Past Performance Questionnaires will be primary means to evaluate performance risk
The government will not search for mitigations to problems found in offeror’s submitted information
The burden is on the offeror to be thorough and complete

Break

TDPC – TECHNICAL REQUIREMENTS

The government intends on identifying the offerors most susceptible of performing Human Performance, Instructional Systems Development and Systems Engineering processes to analyze, design, develop, produce, install, test, implement and, evaluate direct and indirect training solutions

Section L Technical Capability

Section L Technical Capability

The offeror will deliver their repeatable processes for each Functional Area being proposed to as required by Section L
Visio Flow Diagrams are to be a common representation of the offeror’s processes
Instructions for symbols are in Section L B1.1.1(c)
If ISO 9000 certified your existing process flow and symbology will be accepted
Provide an explanation of your symbology if different than Section L B1.1.1(c)

Section L Technical

Demonstrate your ability to solve typical training and performance problems using your repeatable processes
The scenarios [Attachments (3), (4) and (5)] will be provided the day of each offeror’s oral presentation
Five paper copies of each Functional Area scenario will be given to your team in an envelope
You will have 30 minutes to organize and 1 hour to present
At the end of each Functional Area oral, the government may ask probing questions, not to exceed 30 minutes
All questions will be during the probing period
Your proposed Visio flow diagrams will be loaded on the computer and will be ready for projection

Section L Technical

The oral presentations will allow the offeror to demonstrate that it can apply its processes and sub-processes to allow it to manage technical, cost and schedule risks, while solving job performance and or training problems
Price cost or fee information shall not be discussed in the oral presentation

Section L Technical

All oral presentations and the probing period will be captured on digital media
If proposing to more than one Functional Area, there will be a 15 minute break before receipt of the next Functional Area scenario (envelope)
The process repeats itself until all Functional Areas being propose d to are completed
All Functional Areas for an offeror, will be completed in the same day

Section M Technical

LOT I technical evaluation of:
Technical capability
Small business utilization strategy
LOT II technical evaluation of:
Technical capability
Evaluation will be on Visio Flow Diagrams and Oral Presentation
Ability to implement repeatable processes within A functional Area
Proposed approach for the scenario

Section M Technical Will evaluate the offeror’s ability to solve human performance and training requirements for the following Level 1 processes:

Functional Area 1

Analysis
Design
Evaluation
Management
Administration
Support
Quality Improvement
Delivery

Functional Area 2

Development
Production
Implementation
Management
Administration
Support
Quality Improvement
Delivery

Functional Area 3

Analysis
Design
Development
Production
Implementation
Management
Administration
Support
Quality Improvement
Delivery

NOTE: Each Level 1 process should be mapped to the lowest level to best describe the offeror’s work activities.

Section M Technical

The degree to which the offeror met the requirements effectively and efficiently will be determined through an analysis of the offeror’s selection of the:
Processes and Sub-processes
Labor categories
Input/output products for the scenario requirements
There will be one scenario per Functional Area

Sample Scenario Functional Area 3: Mr. Wilson, the Operations Officer, from the XYZ Organization, provides initial and certification training to certify over 75 Instructors a year. The XYZ Organization has defined a new requirement to transition their entire Instructor-Under-Training syllabus to a technology-based-solution to reduce travel and manpower costs. Mr. Wilson wants to compete a contract to immediately change the media from traditional, instructor led, to a virtual world environment. The winning offeror will upgrade the delivery method and media only. All lectures, demonstrations, practice and assessment will take place in a virtual world, with geographical dispersed student instructors. Existing Instructor and Trainee Guides as well as assessment content will be reused. Only the media/delivery method will be modified.

TDPC Price Requirements Mr. Ralph Soberal TDPC Contract Specialist

Page * Price Section L Requirements Two Sections Pricing Other Content Pricing section shall contain:

All price information requested (Labor category cross-walk, rate, and build-up) Paper copy does not need labor descriptions (electronic as is)

Provide all rates, basis, and formulas used to build labor rates Spreadsheets shall not be protected by offerors

Provide sufficient information to support price Include explanation of all ground rules and assumptions that affect the price estimates.

Submit Forward Pricing Rate Agreements if applicable Provide rationale for labor rates Provide DCMA POC

Page * Sheets are protected offerors will provide data in yellow blocks.

Offeror’s Labor Category is the category description the offeror uses

Explain differences (wrap text, ensure printed copy is legible)

Labor Category Cross-Walk

Page *

List Labor Category from Cross-Walk
Show your work (formulas, descriptions, and basis)

Labor Rate Build-up

Page *

List Burdened Labor Rates from labor rate build-up
Show your work (formulas, descriptions, and basis)
Adjust Escalation if desired

Burdened Labor Rates

Check Totals

Other Price Proposal Information – DCMA POC

Check Totals

Page * Price Section M Requirements Price Factor

Each Functional Area Complete Reasonable Complete Provide information in Section L, Volume 4 Reasonable Likelihood of competitive price in the future Total evaluated price when compared amongst all offerors Verifiable and supportable (rates and factors) No profit rates Not cost or Pricing data No profit rates Not considered certified current cost or pricing data Government may use DCMA or DCAA information HubZone preference (10%)

Page *

TYPICAL PRICE PROPOSAL SHORTFALLS

Arithmetic and/or spreadsheet formulas are incorrect

Not relating contractor labor categories to cross-walk

Not providing adequate labor rate support information

Not completing all RFP sections (e.g., Section G Contract Administration information, Section K Reps/Certs etc.)

OPEN DISCUSSION