SA_82710K_HED_Notional_POAM_from_DDG_101_-_HED_MSProj_19Jan16.pdf

PDF 201 KB Posted

Attached to
USS SAMPSON 8C1 DSRA
Solicitation number
N4523A-18-R-0550
Issued by

View the file

Other files

File Type Posted
N4523A-18-R-0550_Amendment_0019.pdf PDF
N4523A-18-R-0550_Amendment_0018.pdf PDF
N4523A-18-R-0550_Amendment_0017.pdf PDF
N4523A-18-R-0550_Amendment_0016.pdf PDF
BQ_029_-_J-14_Section_B_Note_A_Redacted.pdf PDF
N4523A-18-R-0550_Amendment_0015.pdf PDF
N4523A-18-R-0550_Amendment_0014.pdf PDF
N4523A-18-R-0550_Amendment_0013.pdf PDF
DDG-102_SA_288K_HAZMINCEN_POAM.PDF PDF
USS_Sampson_IMO_IMS_J._Fagnant_2017-12-12.pdf PDF
J-18_Access_and_User_Agreement_rev_003_02122018.pdf PDF
N4523A-18-R-0550_Amendment_0012.pdf PDF
N4523A-18-R-0550_Amendment_0011.pdf PDF
BQ_028_PPT_HED_Informational_Brief_for_DDG_102.pptx PPTX presentation
262-8749116_Rev_A,_HYBRID_ELEC_DRIVE_PIPING_-_OIL_SYS_MODS_&_ML.pdf PDF
235-8749114_Rev_A,_HYBRID_ELEC_DRIVE_CONSOLIDATED_ELEC_MODS_&_ML.pdf PDF
182-8749113_Rev_A,_HYBRID_ELEC_DRIVE_HULL_OUTFIT,_STRUCT_&_FDN_MODS_&_ML.pdf PDF
555-8749121_Rev_A,_HYBRID_ELEC_DRIVE_PIPING_-_FIRE_PROTN_MODS_&_ML.pdf PDF
551-8749120_Rev_A,_HYBRID_ELEC_DRIVE_PIPING_-AIR_SYS_MODS_&_ML.pdf PDF
BQ_028_980-90-007_clarification_Redacted.pdf PDF
N4523A-18-R-0550_Amendment_0010.pdf PDF
N4523A-18-R-0550_Amendment_0009.pdf PDF
DDG_102_DSRA_A-7_4720_Report_dtd_18_DEC_17.pdf PDF
BQ_027_4720_request_Redacted.pdf PDF
N4523A-18-R-0550_Amendment_0008.pdf PDF
N4523A-18-R-0550_J-12_PPI_Q_010_Redacted.pdf PDF
J-1_Work_Package_ERRATA_6.pdf PDF
644-8718346-ARR03_REV-A_SANITARY_ARR_MODS.pdf PDF
BQ_026_Missing_Refs-Answered_Redacted.pdf PDF
BQ_025_Missing_Refs-Answered_Redacted.pdf PDF
505-8718348-PIPE20_REV-A_SANITARY_PIPE_MODS.pdf PDF
512-8718350-VENT52_REV-A_VENTILATION_MANUFACTURING_DETAILS.pdf PDF
512-8718344-VENT10_REV-A_BERTHING_VENT_MODS.pdf PDF
331-8718345-ELEC30_REV-A_BERTHING_ELEC_MODS.pdf PDF
640-8718343-ARR01_REV-A_BERTHING_ARR_MODS.pdf PDF
512-8718347-VENT12_REV-A_SANITARY_VENT_MODS.pdf PDF
331-8718349-ELEC32_REV-A_SANITARY_ELEC_MODS.pdf PDF
BQ_024_Missing_Ref_-_Redacted.pdf PDF
BQ_007_437-012-001_Para_3.2_-_Redacted.pdf PDF
BQ_022_980-90-007_References-Redacted.pdf PDF
BQ_21_123-21-001_-_Redacted.pdf PDF
BQ_005_437-012-001_Missing_Drawings_-_Redacted.pdf PDF
BQ_023_Missing_Refs_-_Redacted.pdf PDF
BQ_018_123-10-001_-_Redacted.pdf PDF
BQ_016_588-21-001_-_Redacted.pdf PDF
BQ_019_123-10-001_-_Redacted.pdf PDF
BQ_009_Clarification_-_Redacted.pdf PDF
BQ_015_588-21-001_-_Redacted.pdf PDF
N4523A-18-R-0550_Amendment_0007.pdf PDF
N4523A-18-R-0550_Amendment_0006.pdf PDF
Show 40 more

Latest 50 of 183 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Compartment

Duration Start Finish Frame Longitude P/S Level Equipment Action Celt EQP

1 Hybrid Electric Drive 135 days 9/26/16 3/31/17

136 Avail Start 0 days 9/26/16 9/26/16 1st Plat 0

19 Ripout Vent AFT 4-254-0-E 2 days 10/24/16 10/25/16 281-300 L3-L6 S 1st Plat DRIVE A Ripout T04 2

62 Rework Fuel Oil Piping, Drain, Gas Free, and Clean Gravity Feed Tank

2-298-1-F 2 days 10/26/16 10/27/16 300 L1 S 1st Plat FUEL OIL Install P18 2

77 Ripout Piping AFT 4-254-0-E 10 days 10/26/16 11/8/16 300 L2-L5 S 1st Plat DRIVE A Ripout P18 2

53 Ripout Piping IWO Access Cut 4-254-0-E 3 days 11/9/16 11/11/16 300 Shell S 1st Plat DRIVE A Ripout P18 2

59 Rework CW Supply and Return Piping, Roll Valves 40degs OUTBD

1-254-5-L 2 days 11/9/16 11/10/16 268-276 L12-L13 S 1st Plat CW Install P18 2

78 Ripout Cables and Electrical Equipment 4-254-0-E 2 days 11/9/16 11/10/16 292-300 L3-L12 S 1st Plat DRIVE A Ripout E02 2

22 Ripout Hull Outfit Equipment 4-254-0-E 2 days 11/11/16 11/14/16 292-300 L3-L12 S 1st Plat DRIVE A Ripout T04 2

23 Ripout Foundations and Structure 4-254-0-E 5 days 11/11/16 11/17/16 292-300 L3-L12 S 1st Plat DRIVE A Ripout S40 2

60 Rework FW Piping 1-254-5-L 2 days 11/11/16 11/14/16 268-276 L12-L13 S 1st Plat FW Install P18 2

65 Rework CW Supply Piping 3-370-0-E 2 days 11/11/16 11/14/16 405 L3-L5 S 1st Plat CW Install P18 2

107 Ripout Phone Booth 4-254-0-E 1 day 11/11/16 11/11/16 260 L2-L3 P 1st Plat MOTOR Ripout C02 1

106 Ripout Handrails, T-Bar and Phone booth Founda4-254-0-E 2 days 11/14/16 11/15/16 260 L2-L3 P 1st Plat MOTOR Ripout S40 1

61 Rework PDW Piping 1-268-0-C 2 days 11/15/16 11/16/16 290 L3-L6 S 1st Plat PDW Install P18 2

66 Rework CW Piping 4-370-5-A 2 days 11/15/16 11/16/16 410 L6-L8 S 1st Plat CW Install P18 2

100 Ripout Grating Structure 4-254-0-E 3 days 11/15/16 11/17/16 285-300 L2-L5 S 1st Plat DRIVE A Ripout S40 1

110 Install No Break Power Supply Foundation 4-254-0-E 2 days 11/16/16 11/17/16 262 L1 P 1st Plat MOTOR Install S40 1

63 Rework AFFF Piping 2-300-1-L 2 days 11/17/16 11/18/16 300 L4-L5 S 1st Plat AFFF Install P18 2

67 Rework CW Piping 2-370-2-L 2 days 11/17/16 11/18/16 408 L7-L8 S 1st Plat CW Install P18 2

88 Rig Drive A Foundation to 1st Plat 4-254-0-E 1 day 11/18/16 11/18/16 292 L2-L5 S 1st Plat DRIVE A Loadout S40 2

16 Ripout and Relocate Stanchion IWO Drive Maintenance Envelope

4-254-0-E 6 days 11/21/16 11/28/16 292 L5 S 1st Plat DRIVE A Ripout S40 1

68 Rework CW Piping 2-430-1-Q 2 days 11/21/16 11/22/16 430-442 L7-L9 S 1st Plat CW Install P18 2

69 Rework CW Piping 2-410-0-L 2 days 11/23/16 11/24/16 412-430 L7-L9 S 1st Plat CW Install P18 2

70 Rework CW Piping 2-410-1-L 2 days 11/25/16 11/28/16 410-412 L7-L8 S 1st Plat CW Install P18 2

36 Cut Shell Framing to drop Degaussing to Deck 4-254-0-E 4 days 11/28/16 12/1/16 292-300 Shell S 1st Plat DRIVE A Ripout S40 4

108 Install New Grating Sturcture, Grating Panels, Handrails and Firehose Reel Fdn

4-254-0-E 7 days 11/29/16 12/7/16 285-300 L2-L7 S 1st Plat DRIVE A Install S40 2

123 Install Drive A Foundation 4-254-0-E 3 days 12/5/16 12/7/16 292 L2-L5 S 1st Plat DRIVE A Loadout S40 2

35 Remove Ladder to MER2 and Close off Access to STBD Side

4-254-0-E 1 day 12/8/16 12/8/16 292 L8 S 1st Plat DRIVE A Ripout T04 2

48 Install New Cable Way on 300 BKHD for Drive A and B run to SWBD

4-254-0-E 4 days 12/8/16 12/13/16 300 L5 S 1st Plat DRIVE A Install E02 2

101 Install Piping and Penetrations 4-254-0-E 5 days 12/8/16 12/14/16 300 L2-L5 S 1st Plat DRIVE A Install P18 3

102 Install M/M Foundations and Electrical Equipment 4-254-0-E 4 days 12/15/16 12/20/16 300 L2-L5 S 1st Plat DRIVE A Install E02 2

103 Install Wireways 4-254-0-E 5 days 12/21/16 12/27/16 300 L2-L5 S 1st Plat DRIVE A Install E02 2

104 Pull T400 Cables from Drive A to Motor and to SWBD and Hookup

4-254-0-E 10 days 12/28/16 1/10/17 292-300 L2-L5 S 1st Plat DRIVE A Pull T400 Cables

E02 8

129 Repair Disturbed Painted and Insulated surfaces A4-254-0-E 8 days 12/28/16 1/6/17 288-300 L1-L12 S 1st Plat DRIVE A Install P10 4

121 Pull Local Cables, Cut in and Hook-up 4-254-0-E 5 days 1/11/17 1/17/17 292-300 L3-L12 S 1st Plat DRIVE A Pull T40 E02 2

39 Cut 1st Plat Shell Access to MER2, Protect Degaussing prior to Loadout of Eqpt

4-254-0-E 5 days 1/12/17 1/18/17 292-300 Shell S 1st Plat ACCESS

CUT

Ripout S40 4

41 Loadout Drive A - Rig and Set on Foundation 4-254-0-E 1 day 1/19/17 1/19/17 292 L2-L5 S 1st Plat DRIVE A Loadout S40 2

42 Close 1st Plat Shell Access Cut to MER 2 and Reinstall STBD side Ladder

4-254-0-E 10 days 1/20/17 2/2/17 300 Shell S 1st Plat ACCESS

CUT

Install S40 4

109 Install/Rig Drive A and Install Upper Foundations 4-254-0-E 4 days 1/20/17 1/25/17 290 L2-L5 S 1st Plat DRIVE A Install S40 2

127 Install Vent AFT 4-254-0-E 5 days 1/26/17 2/1/17 288-300 L7-L11 P 1st Plat DRIVE A Install T04 2

132 Connect CW Piping to Drive A 4-254-0-E 5 days 1/26/17 2/1/17 300 L2-L5 S 1st Plat DRIVE A Install P18 3

9/26

S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Deadline

Hybrid Electric Drive

Project: HED MSProj 19Jan16 Date: 1/21/16

Duration Start Finish Frame Longitude P/S Level Equipment Action Celt EQP

105 Remove Coffer Dam (Only for Waterbourne Installations)

4-254-0-E 3 days 2/3/17 2/7/17 300 Shell S 1st Plat ACCESS

CUT

Ripout S40 4

4 Tent off area to Forward end of MRG 4-254-0-E 2 days 10/3/16 10/4/16 260 L3 P 2nd Plat MOTOR Install P10 2

5 Install Spool Piece and bolt on cover for Care and protection

4-254-0-E 8 days 10/5/16 10/14/16 260 L3 P 2nd Plat MOTOR Install O04 2

2 Open, gas free fuel tank 4-220-4-F 10 days 10/17/16 10/28/16 254 2nd Plat TANK Gas FreeP10 6

3 Ripout Vidmars IWO 254 Bulkhead Access Cut 3-220-01-A 4 days 10/17/16 10/20/16 254 L5 P 2nd Plat MOTOR Ripout C02 4

47 Open, gas free fuel tank 4-300-1-F 10 days 10/17/16 10/28/16 300 2nd Plat TANK Gas FreeP10 6

49 Ripout Vent FWD 4-254-0-E 2 days 10/17/16 10/18/16 260 L3-L5 P 2nd Plat MOTOR Ripout T04 2

83 Ripout Cables IWO Access Cut 254 BKHD 4-254-0-E 2 days 10/17/16 10/18/16 254 L1-L5 P 2nd Plat MOTOR Ripout E02 1

6 Ripout Lube Oil Piping and Hard Flange to protect4-254-0-E 2 days 10/19/16 10/20/16 254 L2-L5 P 2nd Plat MOTOR Ripout P18 2

11 Ripout Vent AFT 4-254-0-E 2 days 10/19/16 10/20/16 281-300 L3-L9 S 2nd Plat DRIVE B Ripout T04 2

50 Ripout Cables and Electrical Equipment, ISO Motor Install (LO Heater Controller, TB & Lights)

4-254-0-E 5 days 10/19/16 10/25/16 254 L1-L5 P 2nd Plat MOTOR Ripout E02 1

84 Ripout Electrical Eqpt and M/M Fdn IWO Access C4-254-0-E 2 days 10/19/16 10/20/16 254 L1-L5 P 2nd Plat MOTOR Ripout E02 1

13 Ripout Piping AFT 4-254-0-E 4 days 10/21/16 10/26/16 292-300 L3-L12 S 2nd Plat DRIVE B Ripout P18 4

27 Ripout Piping to Lube Oil Heater 4-254-0-E 3 days 10/21/16 10/25/16 260 L1-L5 P 2nd Plat MOTOR Ripout P18 1

29 Cut Access to SD Store Room 1 thru 254 BKHD and Install temporary staging to allow Eqress into space

3-220-01-A 8 days 10/26/16 11/4/16 254 L1-L5 P 2nd Plat ACCESS

CUT

Ripout S40 2

14 Ripout Hull Outfit Equipment 4-254-0-E 3 days 10/27/16 10/31/16 292-300 L3-L12 S 2nd Plat DRIVE B Ripout T04 2

21 Ripout Piping (Including pipe to Air Tank) 4-254-0-E 3 days 10/27/16 10/31/16 292-300 L3-L12 S 2nd Plat SWBD Ripout P18 4

28 Ripout Handrails and grating IWO of HED EPS Motor Fdn and Eqpt Installation

4-254-0-E 4 days 10/28/16 11/2/16 254 L1-L5 P 2nd Plat MOTOR Ripout S40 2

30 Install Coffer Dams PORT and STBD for Increased Stability (Only for Waterbourne Installations)

3-220-01-A 15 days 10/31/16 11/18/16 240 Shell P 2nd Plat ACCESS

CUT

Install O04 4

17 Ripout Grating and Rails IWO Drive B Foundation Installation

4-254-0-E 1 day 11/1/16 11/1/16 292-300 L3-L6 S 2nd Plat DRIVE B Ripout S40 1

20 Ripout Cables and Electrical Equipment (Including T300 from ABT)

4-254-0-E 4 days 11/1/16 11/4/16 292-300 L3-L12 S 2nd Plat DRIVE A Ripout E02 6

117 Ripout and Stow Air Tank - will install after T400's are pulled

4-254-0-E 2 days 11/1/16 11/2/16 292-300 L3-L7 S 2nd Plat SWBD Ripout P18 4

18 Install New Grating Structure and BUS for Drive B4-254-0-E 8 days 11/2/16 11/11/16 292-300 L3-L6 S 2nd Plat DRIVE B Install S40 1

12 Ripout No Break Power Supply, ABT 3-290-1, and Power Supply 3-292-1

4-254-0-E 2 days 11/7/16 11/8/16 292-300 L3-L12 S 2nd Plat DRIVE B Ripout E02 4

15 Ripout Foundations 4-254-0-E 5 days 11/9/16 11/15/16 292-300 L3-L12 S 2nd Plat DRIVE B Ripout E02 2

31 Cut Shell Access to SD Store Room 1 3-220-01-A 5 days 11/9/16 11/15/16 240 Shell P 2nd Plat ACCESS CUTRipout S40 4

114 Ripout Electrical Equipment - Lights, Phone, Horn, TB, etc

4-254-0-E 2 days 11/9/16 11/10/16 292-300 L3-L7 S 2nd Plat DRIVE B Ripout E02 4

34 Ripout Halon Bottle Rack Foundation for Lube Oil Heater Relocation

4-254-0-E 4 days 11/14/16 11/17/16 256 L1 S 2nd Plat LUBE OIL

HEATER

Ripout S40 2

32 Load Out HED EPS Motor & Fdn, Drive A, B and SWBD Fdns and Tangle Box

3-220-01-A 3 days 11/16/16 11/18/16 240 Shell P 2nd Plat MOTOR Loadout E02 4

37 Rig Drive A, B and SWBD Foundations to MER 2

- Install prior to Loadout of Equipment

4-254-0-E 1 day 11/16/16 11/16/16 295-300 L3-L7 S 2nd Plat SWBD Loadout E02 4

38 Install New Foundations for Drive B and SWBD - Weld & Paint

4-254-0-E 15 days 11/17/16 12/7/16 292-300 L3-L7 S 2nd Plat DRIVE B Install S40 2

122 Install Structural Foundations - ABT, Pwr Pnl, Air Receiver Tank, Phone Booth etc

4-254-0-E 10 days 11/17/16 11/30/16 292-300 L3-L12 S 2nd Plat DRIVE B Install S40 2

26 Install Structure and Foundation for Lube Oil Heat4-254-0-E 6 days 11/18/16 11/25/16 256 L3 S 2nd Plat LUBE OIL HEInstall S40 1

113 Install Piping 4-254-0-E 8 days 11/18/16 11/29/16 292-300 L3-L7 S 2nd Plat DRIVE B Install P18 3

87 Close Shell Access Cut (Port) 3-220-01-A 10 days 11/21/16 12/2/16 240 Shell P 2nd Plat ACCESS CUTInstall S40 4

S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Deadline

Hybrid Electric Drive

Duration Start Finish Frame Longitude P/S Level Equipment Action Celt EQP

51 Cut Lube Oil Heater Foundation and Relocate to Fr 256 L3 (S)

4-254-0-E 3 days 11/28/16 11/30/16 260 L1-L5 P 2nd Plat LUBE OIL

HEATER

Install S40 2

85 Pull New Cables to Lube Oil Controller, Pull Back T150 Cables to new Location

4-254-0-E 4 days 12/1/16 12/6/16 254 L1-L5 P 2nd Plat MOTOR Pull Cables

E02 4

115 Install M/M Foundations, and Install Electrical Equ4-254-0-E 5 days 12/1/16 12/7/16 292-300 L3-L7 S 2nd Plat DRIVE B Install E02 4

120 Install Hull Outfit Equipment 4-254-0-E 3 days 12/1/16 12/5/16 292-300 L3-L12 S 2nd Plat DRIVE B Install T04 2

124 Install Piping to Relocated Lube Oil Heater 4-254-0-E 3 days 12/1/16 12/5/16 260 L3 S 2nd Plat LUBE OIL HEInstall P18 2

116 Pull Local Cables, Cut in and Hook-up (Not T400's4-254-0-E 8 days 12/8/16 12/19/16 292-300 L3-L7 S 2nd Plat DRIVE B Pull CabE02 2

71 Install HED EPS Foundation, Weld and Machine S4-254-0-E 4 days 12/9/16 12/14/16 260 L1-L5 P 2nd Plat MOTOR Install S40 2

72 Install HED EPS Motor and Connect to MRG -

NO PRODUCTION WORK IN AREA WHILE

MRG IS OPEN

4-254-0-E 15 days 12/15/16 1/4/17 260 L1-L5 P 2nd Plat MOTOR Install O04 4

52 Cut 2nd Plat Shell Access to MER2 4-254-0-E 5 days 12/20/16 12/26/16 292-300 Shell S 2nd Plat ACCESS CUTRipout S40 4

54 Loadout Drive B - Rig and Set on Foundation 4-254-0-E 1 day 12/27/16 12/27/16 292 L2-L5 S 2nd Plat DRIVE B Loadout S40 2

55 Loadout SWBD - Rig and Set on Foundation 4-254-0-E 1 day 12/28/16 12/28/16 292 L2-L5 S 2nd Plat SWBD Loadout S40 2

112 Install Upper Foundation for Drive B 4-254-0-E 8 days 12/28/16 1/6/17 292-300 L3-L7 S 2nd Plat DRIVE B Install S40 4

126 Install Vent AFT 4-254-0-E 5 days 12/28/16 1/3/17 288-300 L7-L11 P 2nd Plat DRIVE B Install T04 2

25 Install Hinged Grating Platform 4-254-0-E 3 days 12/29/16 1/2/17 300 L10 S 2nd Plat SWBD Install S40 3

99 Close 2nd Plat Shell Access Cut to MER 2 4-254-0-E 10 days 12/29/16 1/11/17 300 Shell S 2nd Plat ACCESS CUTInstall S40 4

118 Install Upper Foundations for HED SWBD - after Access Patch is Installed

4-254-0-E 4 days 12/29/16 1/3/17 292-300 L3-L7 S 2nd Plat SWBD Install S40 4

133 Connect CW Piping to Drive B 4-254-0-E 8 days 12/29/16 1/9/17 292-300 L3-L7 S 2nd Plat DRIVE B Install P18 3

128 Repair Disturbed Painted and Insulated surfaces A4-254-0-E 8 days 1/4/17 1/13/17 288-300 L1-L12 S 2nd Plat DRIVE B Install P10 4

73 Install Piping to Lube Oil Sump 4-254-0-E 4 days 1/5/17 1/10/17 260 L1-L5 P 2nd Plat MOTOR Install P18 2

111 Install HED EPS Motor Piping Connections 4-254-0-E 10 days 1/5/17 1/18/17 260 L1-L5 P 2nd Plat MOTOR Install P18 4

131 Start Hydro Testing and Flushing of New and Distrubed Piping Systems

4-254-0-E 33 days 1/11/17 2/24/17 254-300 2nd Plat Install P18 4

43 Install Cable Ladders and Cable Ways in Preparation for 2SA and 3SA SWBD De-energinze

4-254-0-E 5 days 1/19/17 1/25/17 284 L9-L11 S 2nd Plat SWBD Install E02 2

46 Install New Cable Way from Drive B to HED EPS Motor (Staging Required)

4-254-0-E 12 days 1/19/17 2/3/17 254-300 L5 S 2nd Plat DRIVE B Install E02 2

74 Install Electrical Equipment, Cut In and Hook up C4-254-0-E 8 days 1/19/17 1/30/17 254 L1-L5 P 2nd Plat MOTOR Install E02 2

75 Install Cable Ladder and Cable ways 4-254-0-E 5 days 1/19/17 1/25/17 260 L1-L2 P 2nd Plat MOTOR Install E02 2

44 Cut and Pull back 12 T400 Cables from 2SA SWBD and Pull to Tangle Box

4-254-0-E 10 days 1/26/17 2/8/17 260-284 L9 S 2nd Plat SWBD Pull T400 Cables

E02 8

79 Close 254 Access to SD Storeroom #1 4-254-0-E 5 days 1/26/17 2/1/17 254 L1-L5 P 2nd Plat ACCESS CUTInstall S40 4

81 Install Grating Structure, Rails and Grating Panels4-254-0-E 5 days 2/2/17 2/8/17 254 L1-L5 P 2nd Plat MOTOR Install S40 2

86 Reinstall Vidmar Cabinets 3-220-01-A 5 days 2/2/17 2/8/17 240 L5 P 2nd Plat MOTOR Install C02 4

76 Pull T400 Cables from Drive B to Motor and to SWBD and Hookup

4-254-0-E 8 days 2/6/17 2/15/17 260-300 L1-L2 P 2nd Plat MOTOR Pull T400 Cables

E02 4

125 Remove Coffer Dam (Only for Waterbourne Installations)

3-220-01-A 3 days 2/8/17 2/10/17 240 Shell p 2nd Plat ACCESS

CUT

Ripout S40 4

45 Pull 12 New T400 Cables from 2SA SWBD to New HED SWBD and Hookup

4-254-0-E 8 days 2/9/17 2/20/17 292 L9 S 2nd Plat SWBD Pull T400 Cables

E02 8

82 Install Vent FWD 4-254-0-E 5 days 2/9/17 2/15/17 260 L3-L5 P 2nd Plat MOTOR Install T04 2

80 Repair Disturbed Painted and Insulated surfaces F4-254-0-E 8 days 2/16/17 2/27/17 254-260 L1-L5 P 2nd Plat MOTOR Install P10 4

119 Install Air Tank and Pipe up 4-254-0-E 4 days 2/21/17 2/24/17 292-300 L3-L7 S 2nd Plat SWBD Install P18 4

64 Drain, Gas Free and Clean Lube Oil Sump prior to Pipe Mods

5-254-5-F 2 days 10/17/16 10/18/16 S Hold LO SUMP Install P18 2

89 Ripout Vent AFT 4-254-0-E 2 days 10/21/16 10/24/16 288-300 L7-L11 S Hold TANGLE BOXRipout T04 2

8 Ripout Piping and Resilient Hanger IWO Tangle Box Installation

4-254-0-E 2 days 10/25/16 10/26/16 288-300 L7-L11 S Hold TANGLE

BOX

Ripout P18 2

S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Deadline

Hybrid Electric Drive

Duration Start Finish Frame Longitude P/S Level Equipment Action Celt EQP

7 Ripout Cables, Equipment, and M/M Fdns IWO Tangle Box Installation

4-254-0-E 3 days 10/27/16 10/31/16 288-300 L7-L11 S Hold TANGLE

BOX

Ripout E02 2

9 Patch Penetrations and cut new Penetrations for New Tangle Box Installation

4-254-0-E 10 days 10/27/16 11/9/16 288-300 L7-L11 S Hold TANGLE

BOX

Install S40 2

24 Ripout and Relocate Fdn for Power Panel 4-295-1, Shaft Seal Stowage, and Install BUS

4-254-0-E 6 days 11/1/16 11/8/16 295 L12 S Hold TANGLE

BOX

Ripout S40 1

95 Ripout Resilient Hanger Structure 4-254-0-E 1 day 11/1/16 11/1/16 288-300 L7-L11 S Hold TANGLE BOXRipout S40 1

96 Install Structure for Resilient Hanger 4-254-0-E 2 days 11/2/16 11/3/16 288-300 L7-L11 S Hold TANGLE BOXInstall S40 1

94 Relocate Gage boards 4-254-0-E 7 days 11/4/16 11/14/16 288-300 L7-L11 S Hold TANGLE BOXInstall O04 2

33 Relocate Electrial Equipment- PP, Lights, Speaker, Smoke Det. etc. IWO Tangle Box Installation

4-254-0-E 4 days 11/10/16 11/15/16 288-300 L7-L11 S Hold TANGLE

BOX

Install E02 1

40 Install Piping and Resilient Hanger to MDI Hose A4-254-0-E 3 days 11/10/16 11/14/16 288-300 L7-L11 S Hold TANGLE BOXInstall P18 2

92 Install M/M Fdns 4-254-0-E 3 days 11/10/16 11/14/16 288-300 L7-L11 S Hold TANGLE BOXInstall E02 1

98 Layout and Cut Cable Ladder and Cable way Penetrations

4-254-0-E 4 days 11/10/16 11/15/16 288-300 L7-L11 S Hold TANGLE

BOX

Install E02 2

90 Install Cable Way inside Tangle Box Location 4-254-0-E 4 days 11/17/16 11/22/16 288-300 L7-L11 S Hold TANGLE BOXInstall E02 2

97 Pull Local Cables, Cut in and Hook up (Not T400'4-254-0-E 6 days 11/17/16 11/24/16 288-300 L7-L11 S Hold TANGLE BOXPull CabE02 2

10 Install Tangle Box and Weld 4-254-0-E 7 days 11/23/16 12/1/16 288-300 L7-L11 S Hold TANGLE BOXInstall S40 2

56 Rotate Valve IWO HED Motor Foundation Installa 4-254-0-E 3 days 11/24/16 11/28/16 254 L2-L4 P Hold MOTOR Install P18 1

58 Rework SW and Lube Oil Piping to Lube Oil Coole4-254-0-E 10 days 11/24/16 12/7/16 260 L2-L5 P Hold MOTOR Install P18 2

57 Install Remote Operator (ROG) on Rotated Valve 4-254-0-E 5 days 11/29/16 12/5/16 254 L2 P Hold MOTOR Install O04 1

130 Repair Disturbed Painted and Insulated surfaces A4-254-0-E 8 days 12/2/16 12/13/16 288-300 L1-L12 S Hold TANGLE BOXInstall P10 4

137 HED to MRG Installation and Alignment Procedur 4-254-0-E 1 day 1/5/17 1/5/17 260 Hold SYSTEMS O04

138 Installation Alignment and Clutch Operation Verific4-254-0-E 1 day 1/6/17 1/6/17 260 Hold SYSTEMS O04

91 Pull T400 Cable to SWBD and Hookup 4-254-0-E 8 days 2/16/17 2/27/17 288-300 L7-L11 S Hold TANGLE BOXPull T40 E02 4

93 Install Vent AFT 4-254-0-E 2 days 2/28/17 3/1/17 288-300 L7-L11 S Hold TANGLE BOXInstall T04 2

139 HED-EPS Electrical Installation Verification 4-254-0-E 10 days 2/28/17 3/13/17 254-300 Hold SYSTEMS E02

134 Perform Volumetric Balancing of New and Disturbed Ventilation

4-254-0-E 10 days 3/2/17 3/15/17 254-300 Hold SYSTEMS T04 2

140 HED-EPS Signal Verification (Hardware) 4-254-0-E 5 days 3/14/17 3/20/17 254-300 Hold SYSTEMS E02

141 HED-EPS Initial Light-Off, FODMS, & Vital Power 4-254-0-E 2 days 3/21/17 3/22/17 Hold SYSTEMS E02

135 HED COMPLETION 0 days 3/31/17 3/31/17 Hold 0 3/31

S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Deadline