ID Alteration Number
Task No Title JCN Component Summary
Dur Provider Start Finish Location System Hot Work
ScaffoWork AS AF % Work Compl
1 USS SAMPSON (DDG102) SHIPALT 288K 40 d Mon 7/23/18
Thu 9/6/18
Yes No 320 h NA NA 0%
2 Key Event - Start of Availability 0 d Mon 7/16/18
Mon 7/16/18
No No 0 h NA NA 0%
3 PREPARATIONS 6 d Mon 7/23/18
Sat 7/28/18
No No 60 h NA NA 0%
4 SA
00288K
1S RMMCO Check-in 1 d NSWC Mon 7/23/18
Mon 7/23/18
No No 10 h NA NA 0%
5 SA
00288K
2S Submit WAFS 1 d AIT Tue 7/24/18
Tue 7/24/18
No No 10 h NA NA 0%
6 SA
00288K
3S Onload Material & Tooling 4 d AIT Wed 7/25/18
Sat 7/28/18
No No 40 h NA NA 0%
7 DRAWING 8749069A 6 d AIT Mon 7/30/18
Sat 8/4/18 4-410-1-A, 4-418-1-L
No No 110 h NA NA 0%
8 HAZMINCEN (4-410-1-A) 5 d AIT Mon 7/30/18
Fri 8/3/18 4-410-1-A No No 90 h NA NA 0%
9 REMOVALS/RE-LOCATIONS 2 d AIT Mon 7/30/18
Tue 7/31/18
4-410-1-A No No 30 h NA NA 0%
10 SA
00288K
1U Coil Cable and Cable Tags Power Cable 1 d AIT Mon 7/30/18
Mon 7/30/18
4-410-1-A LC No No 10 h NA NA 0%
11 SA
00288K
2U Remove Cable Hangers Cable Hangers 1 d AIT Tue 7/31/18
Tue 7/31/18
4-410-1-A LC Yes No 10 h NA NA 0%
12 SA
00288K
3U Remove Cable and Cable Tags Power Cable 1 d AIT Tue 7/31/18
Tue 7/31/18
4-410-1-A LC No No 10 h NA NA 0%
13 INSTALLATIONS 3 d AIT Wed 8/1/18
Fri 8/3/18 4-410-1-A No No 60 h NA NA 0%
14 SA
00288K
1R Install Latern Lantern 1 d AIT Wed 8/1/18
Wed 8/1/18
4-410-1-A LC Yes No 10 h NA NA 0%
15 SA
00288K
2R Install Desk Light Desk Light 1 d AIT Wed 8/1/18
Wed 8/1/18
4-410-1-A LC Yes No 10 h NA NA 0%
16 SA
00288K
3R Install Junction Boxes Junction Boxes 1 d AIT Thu 8/2/18
Thu 8/2/18
4-410-1-A LC No No 10 h NA NA 0%
17 SA
00288K
4R Install Heat Detectors Heat Detectors 1 d AIT Thu 8/2/18
Thu 8/2/18
4-410-1-A VEN Yes No 10 h NA NA 0%
18 SA
00288K
5R Perform Cable Terminations / Connectorizations Power Cable Connections
1 d AIT Fri 8/3/18 Fri 8/3/18 4-410-1-A LC No No 10 h NA NA 0%
19 SA
00288K
6R Install Label Plates Label Plates 1 d AIT Fri 8/3/18 Fri 8/3/18 4-410-1-A LC No No 10 h NA NA 0%
20 PASSAGE (4-418-1-L) 1 d AIT Sat 8/4/18 Sat 8/4/18 4-418-1-L No No 20 h NA NA 0%
21 REMOVALS/RE-LOCATIONS 1 d AIT Sat 8/4/18 Sat 8/4/18 4-418-1-L No No 10 h NA NA 0%
22 SA
00288K
4U Remove Cable and Cable Tags Power Cable 1 d AIT Sat 8/4/18 Sat 8/4/18 4-418-1-L LC No No 10 h NA NA 0%
23 INSTALLATION 1 d AIT Sat 8/4/18 Sat 8/4/18 4-418-1-L No No 10 h NA NA 0%
24 SA
00288K
7R Install Wire and Cable Tags Power Cables 1 d AIT Sat 8/4/18 Sat 8/4/18 4-418-1-L LC No No 10 h NA NA 0%
DDG-102 SA 288K HAZMINCEN POA&M.mpp Page 1 of 4 AIT 9090.310 SERIES
ID Alteration Number
Task No Title JCN Component Summary
Dur Provider Start Finish Location System Hot Work
ScaffoWork AS AF % Work Compl
25 DRAWING 8749070A 7 d AIT Mon 8/6/18
Mon 8/13/18
4-410-1-A No No 80 h NA NA 0%
26 HAZMINCEN (4-410-1-A) 7 d AIT Mon 8/6/18
Mon 8/13/18
4-410-1-A No No 80 h NA NA 0%
27 REMOVALS/RE-LOCATIONS 1 d AIT Mon 8/6/18
Mon 8/6/18
4-410-1-A No No 20 h NA NA 0%
28 SA
00288K
5U Ripout and Scrap Locker and Foundation Outfitting 1 d AIT Mon 8/6/18
Mon 8/6/18
4-410-1-A DECK Yes No 10 h NA NA 0%
29 SA
00288K
6U Ripout EEBD Safety System 1 d AIT Mon 8/6/18
Mon 8/6/18
4-410-1-A HAB Yes No 10 h NA NA 0%
30 INSTALLATION 6 d AIT Tue 8/7/18
Mon 8/13/18
4-410-1-A No No 60 h NA NA 0%
31 SA
00288K
8R Install Cable Guards Cable Guards 1 d AIT Tue 8/7/18
Tue 8/7/18
4-410-1-A LC No No 10 h NA NA 0%
32 SA
00288K
10R Install Fire Extingisher Fire Safety System 1 d AIT Tue 8/7/18
Tue 8/7/18
4-410-1-A FCS Yes No 10 h NA NA 0%
33 SA
00288K
11R Install Coat/Hat Hook and Foundation Coat/Hat Hook 3 d AIT Tue 8/7/18
Thu 8/9/18
4-410-1-A HAB Yes No 30 h NA NA 0%
34 SA
00288K
12R Install Security Light Stowage and Foundation Safety System 3 d AIT Tue 8/7/18
Thu 8/9/18
4-410-1-A HAB Yes No 0 h NA NA 0%
35 SA
00288K
13R Install Mechanical Protection Safety System 1 d AIT Fri 8/10/18
Fri 8/10/18
4-410-1-A HAB Yes No 0 h NA NA 0%
36 SA
00288K
14R Intall EEBD Safety System 1 d AIT Fri 8/10/18
Fri 8/10/18
4-410-1-A HAB Yes No 0 h NA NA 0%
37 SA
00288K
15R Install Chemical Stowage and Foundation Safety System 3 d AIT Fri 8/10/18
Mon 8/13/18
4-410-1-A HAB Yes No 0 h NA NA 0%
38 SA
00288K
16R Install Label Plates Label Plates 1 d AIT Fri 8/10/18
Fri 8/10/18
4-410-1-A HAB No No 10 h NA NA 0%
39 TESTING 2 d Mon 9/3/18
Tue 9/4/18
No No 50 h NA NA 0%
40 SA
00288K
1T Perform Compartment Completion Air Testing Cable MCT Test 1 d AIT Mon 9/3/18
Mon 9/3/18
4-410-1-A, 4-418-1-L
LC No No 10 h NA NA 0%
41 SA
00288K
2T Perform Operational Check of Overhead, Detail Lighting and Associated Switches
Lighting Test 1 d AIT Mon 9/3/18
Mon 9/3/18
4-410-1-A, 4-418-1-L
LC No No 10 h NA NA 0%
42 SA
00288K
3T Operational Test of Relay Lantern Lighting Test 1 d AIT Mon 9/3/18
Mon 9/3/18
4-410-1-A LC No No 10 h NA NA 0%
43 SA
00288K
4T Operational Test of Ionization Smoke Detectors Fire Safety System 1 d AIT Tue 9/4/18
Tue 9/4/18
4-410-1-A VEN No No 10 h NA NA 0%
44 SA
00288K
5T Operational Test of Heat Detectors Ventilation System 1 d AIT Tue 9/4/18
Tue 9/4/18
4-410-1-A VEN No No 10 h NA NA 0%
45 POST INSTALLATION 2 d Wed 9/5/18
Thu 9/6/18
No No 20 h NA NA 0%
46 SA
00288K
4S Close-Outs WAFs WAF Close out 1 d AIT Wed 9/5/18
Wed 9/5/18
AIT No No 10 h NA NA 0%
47 SA
00288K
5S RMMCO Check-Out RMMCO 1 d AIT Thu 9/6/18
Thu 9/6/18
AIT No No 10 h NA NA 0%
DDG-102 SA 288K HAZMINCEN POA&M.mpp Page 2 of 4 AIT 9090.310 SERIES
Pred Succ
4 6
5 10
6 11
10 12SS
11SS 14
12 15SS
14SS 16
15 17SS
16SS 18
17 19SS
18SS 22
19 24SS
22SS 28
7/16
PREPARATIONS
DRAWING 8749069A
HAZMINCEN (4-410-1-A)
REMOVALS/RE-LOCATIONS
INSTALLATIONS
PASSAGE (4-418-1-L)
REMOVALS/RE-LOCATIONS
INSTALLATION
Jul Aug Sep Qtr 3, 2018 Qtr 4, 2018
DDG-102 SA 288K HAZMINCEN POA&M.mpp Page 3 of 4 AIT 9090.310 SERIES
Pred Succ
24 29SS
28SS 31
29 32SS
31SS 33SS
32SS 34SS
33SS 35
34 36SS
35SS 37SS
36SS 38SS
37SS
41SS
40SS 42SS,43
41SS
41 44SS
43SS 46
44 47
DRAWING 8749070A
HAZMINCEN (4-410-1-A)
REMOVALS/RE-LOCATIONS
INSTALLATION
TESTING
POST INSTALLATION
Jul Aug Sep Qtr 3, 2018 Qtr 4, 2018
DDG-102 SA 288K HAZMINCEN POA&M.mpp Page 4 of 4 AIT 9090.310 SERIES