33 52 11 Rev.pdf

PDF 20 KB Posted

Attached to
Amendment 0010 -Use the applicable Small Business Forms attached Federal contract opportunity
Solicitation number
n44255
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document contains a technical specification for a prefabricated utility enclosure and related federal contract opportunity.

The technical specification defines requirements for a metal utility enclosure to serve a fueling receiving facility where fuel tanker trucks unload diesel fuel to underground storage tanks. It provides details on structural design loads, submittal requirements, materials, doors, framing, panels, insulation, heating and ventilation systems. The related federal contract opportunity is to construct a berthing pier, tessel, vessel maintenance facility and fuel distribution system to support a Maritime Force Protection Unit's operations mission at the Bangor Naval Base. The solicitation is issued by the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files for this federal contract opportunity

Other files attached to Amendment 0010 -Use the applicable Small Business Forms attached, newest first.
File Type Posted
VMF Site 1 from Sturgeon St.jpg JPG image
KB Spit 1 - Pier Location.jpg JPG image
MW101 Rev 1.pdf PDF
EW111 Rev 2.pdf PDF
EB131 Rev 1.pdf PDF
22 13 29 Rev.pdf PDF
08 41 13 Rev.pdf PDF
EW404 Rev 3.pdf PDF
Attachment K.docx DOCX document
01 32 17.00 20 Rev.pdf PDF
106 Rev 1.pdf PDF
MW412 Rev 1.pdf PDF
EW613 Rev 2.pdf PDF
SW521 Rev 2.pdf PDF
MW613 Rev 1.pdf PDF
MW611 Rev 1.pdf PDF
MW112 Rev 1.pdf PDF
MW601 Rev 1.pdf PDF
Amendment 0007.pdf PDF
Revised_Sections 00100 and 00800.pdf PDF
P907 TPS Geotech Report_0006.pdf PDF
P907 TPS UST Site Assess Report_0006.pdf PDF
PPIs Continued.pdf PDF
1100 kW Generator Photo_0006.pdf PDF
PPI AMEND 0006.pdf PDF
Amendment 0005.pdf PDF
EW404 Rev 1.pdf PDF
EW602 Rev 1.pdf PDF
EW611 Rev 1.pdf PDF
AB104 Rev1.pdf PDF
SW526 Rev 1.pdf PDF
CS102 Rev 1.pdf PDF
EW141 Rev 1.pdf PDF
CS103 Rev 1.pdf PDF
EW124 Rev 1.pdf PDF
P-876 AS-Built_E130.pdf PDF
AB603 Rev 1.pdf PDF
01 32 17.00 20.pdf PDF
AB111 Rev 1.pdf PDF
Amendment 0004.pdf PDF
SF30 Continuation .pdf PDF
SF30 Continuation rev.pdf PDF
Amendment 003.pdf PDF
Amendment 0002 SF30.pdf PDF
Amend_1_Page_2.pdf PDF
P907 Project Location.pdf PDF
SF30 Amendment 0001.pdf PDF
RFP Attachment K_EXAMPLE Overhead Forms.xlsx XLSX spreadsheet
Attachment J.pdf PDF
RFP P-907 Pier and Maintence Facility.pdf PDF
Show all 50

Amendment 0010 -Use the applicable Small Business Forms attached has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bangor P-907 TPP Pier 217069

SECTION 33 52 11

FUELING FACILITY UTILITY ENCLOSURE

04/19

PART 1 GENERAL

1.1 SUMMARY

This section defines the requirements for a pre-fabricated metal utility enclosure that serves the fueling receiving facility where fuel tanker trucks unload diesel fuel marine (DFM) to underground fuel storage tanks UST-1 and UST-2.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A167 (2011) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code

INTERNATIONAL CODE COUNCIL (ICC)

ICC IBC (2015) International Building Code

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;

TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;

TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;

TIA 17-11; TIA 17-12; TIA 17-13; TIA

17-14; TIA 17-15; TIA 17-16; TIA 17-17 )

National Electrical Code

1.3 RELATED REQUIREMENTS

Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS and Section 26 08 00 APPARATUS INSPECTION AND TESTING apply to this section, with the additions and modifications specified herein.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SECTION 33 52 11 Rev 1 Page 1 August 5, 2019

SD-02 Shop Drawings

Utility Enclosure Drawings; G

Utility Enclosure Design Drawings, Calculations, and Specifications;

G

SD-03 Product Data

Utility Enclosure; G

SD-05 Design Data

Seismic Design; G

1.5 QUALITY ASSURANCE

1.5.1 Utility Enclosure Drawings

Prior to fabrication, submit shop drawings for the utility enclosure.

Submit utility enclosure design drawings, calculations, and specifications stamped by professional engineers registered in the State of Washington.

a. Submit seismic design and calculations sealed and signed by a registered structural engineer.

b. Floor plans, elevations, and details showing architectural and structural components including roof panels, wall panels, man doors, gables, eave trim, gutters, downspouts, girders, columns, purlins, girts, steel bracing, column base plates, anchors, hardware, insulation, and weather sealing. Include penetration sealing details.

Include finish details. Include template for anchor bolt installation.

c. Floor plans, elevations, and details showing mechanical components including ventilators, louvers, fans, heaters, thermostats, and controllers.

d. Floor plans, elevations, and details showing electrical components including lighting, switches, and receptacles.

1.5.2 Utility Enclosure Product Data

Prior to fabrication, submit manufacturer's product data for the utility enclosure.

a. Architectural and structural components including but not limited to wall panels, man doors, gables, eave trim, gutters, downspouts, girders, columns, purlins, girts, steel bracing, column base plates, anchors, and hardware. Include drawings showing floor joists and primary foundation support locations coordinated with the final structural floor slab details for supporting the enclosure.

b. Sealants and flashings.

c. Finishes.

d. Ventilators.

e. Louvers and dampers.

SECTION 33 52 11 Rev 1 Page 2 August 5, 2019

f. Fans.

g. Heaters.

h. Man doors and hardware.

i. Thermostats.

j. Controllers.

k. Luminaires.

l. Receptacles.

m. Switches.

1.6 DELIVERY, STORAGE, AND HANDLING

Comply with the requirements of Division 01 and the following:

a. Pay for shipping, handling, loading, lifting, rigging, permits, and unloading costs from the point of manufacture to the point of installation, including Contractor's off-site storage facility.

b. Utility enclosure manufacturer shall have representatives to supervise loading, unloading, and storage at each point of loading, unloading, and storage.

c. Coordinate the maximum shipping dimensions and weights of the utility enclosure and systems with the physical characteristics and regulatory restrictions of the roadways from the point of manufacturer to the point of installation. Obtain and pay for all regulatory licenses, escorts, and permits. Coordinate with the Contracting Officer for specific delivery requirements.

d. Provide vibration and impact recorders on each section susceptible to shock and vibration damage. Record counters prior to and after delivery. Submit counters to the Contracting Officer for inspection upon request.

PART 2 PRODUCTS

2.1 PREFABRICATED UTILITY ENCLOSURE

Provide a prefabricated utility enclosure including structural steel framed base, metal enclosure walls, panels, doors, roof, frame, gutters, overhang, structural steel skid and supporting interior power, lighting, heating, and related equipment. enclosure shall be complete, tested, and ready for operation prior to shipment and after installation at the site.

2.1.1 Enclosure

The enclosure shall be a fabricated of ASTM A167 Type 304 or 304L Stainless Steel with interior and exterior surfaces painted with high-performance epoxy coatings per Section 09 96 00 HIGH PERFORMANCE

COATINGS.

SECTION 33 52 11 Rev 1 Page 3 August 5, 2019

2.1.2 Doors

The utility enclosure doors shall be double wall, 16 gauge ASTM A167 Type 316L stainless steel with keyed locking latch hardware. Maximum deflection shall be 0.062 inch across the width and 0.0125 across the height. Personnel doors shall be 84 inches tall. Width shall be as indicated. Provide door louvers as indicated.

2.1.3 Design Load

Design enclosure in accordance with ICC IBC :

a. Roof live load shall be calculated in accordance with the IBC.

b. Roof snow load: 25 psf minimum.

c. Wind loading: Based on 110 mph Basic Wind Speed, Exposure C, Category

IV.

d. Seismic loading: Risk Category IV. Refer to the Structural drawings for design criteria and site information.

2.1.4 Framing

Provide rigid frame type construction, with self-framing vertical walls and standing seam gable roof with maximum panel widths of 16 inches. Roof slope shall be a minimum of 1 to 12. Design framed openings structurally.

2.1.5 Roof, Wall, and Ceiling Panels

a. Exterior panels to be 12 gauge (.105") minimum.

b. Interior panels to be 18 gauge (.048") minimum.

c. Flashing to be 16 gauge (.060") minimum and sealed.

d. Standing seam roof interlocking rib height shall be not less than 2.5 inches and shall be sealed.

e. Insulation in the cores of the roof and wall panels shall be asbestos-free composition and provide insulation values as indicated on drawings.

f. Wall framing must be designed to provide attachment framing and to support wall-mounted electrical panels, equipment, control panels, etc., as indicated on the plans.

2.1.6 Heating and Ventilation

The enclosure Equipment Room shall be provided with heating and ventilation systems having all components necessary to maintain the indoor environmental conditions above 40 degrees F in winter and below 100 degrees F in summer. Use 100 percent outdoor air for cooling. The total design load for the system shall include infiltration, ventilation load and the heat generated by the equipment within the enclosure. The drawings indicate heating and ventilating design components which may be used. All exterior electrical apparatus of the HVAC system shall be tamper proof.

SECTION 33 52 11 Rev 1 Page 4 August 5, 2019

The enclosure Filter Room shall be provided with a heating system and natural ventilation systems having all components necessary to maintain the indoor environmental conditions above 40 degrees F in winter. The drawings indicate heating and and the use of high and low wall louvers for continuous natural ventilation of about 80 CFM, which may be used for heating and ventilation.

Outdoor ambient conditions used in calculations and equipment selection shall be based on the following outdoor design conditions:

a. Cooling Design Dry Bulb Design Temperature: 92 degrees F dry bulb.

b. Heating Design (Median of Extreme Lows): 21 degrees F dry bulb. Indoor design conditions shall be 90 degrees F for freeze protection.

Provide ventilation ducts through walls as indicated. Seal around penetrations. Ductwork shall be constructed, supported, and braced per SMACNA standards. All electrical components must be explosion-proof construction.

PART 3 EXECUTION

3.1 INSTALLATION

Installations shall conform to IEEE C2 , NFPA 70 , and to the requirements specified herein.

3.1.1 Utility Enclosure

Securely mount enclosure on concrete slab on grade as recommended by enclosure manufacturer.

-- End of Section --

SECTION 33 52 11 Rev 1 Page 5 August 5, 2019

33 52 11 - FUELING FACILITY UTILITY ENCLOSURE
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 RELATED REQUIREMENTS
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.5.1 Utility Enclosure Drawings
1.5.2 Utility Enclosure Product Data

1.6 DELIVERY, STORAGE, AND HANDLING

PART 2 PRODUCTS
2.1 PREFABRICATED UTILITY ENCLOSURE
2.1.1 Enclosure
2.1.2 Doors
2.1.3 Design Load
2.1.4 Framing
2.1.5 Roof, Wall, and Ceiling Panels
2.1.6 Heating and Ventilation
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Utility Enclosure