REVISED-Solit-Pricing Breakdown-Submarine_Preservation.xlsx

XLSX spreadsheet 456 KB Posted

Attached to
USS Toledo (SSN-769) Submarine Preservation and Maintenance
Solicitation number
N4215821RS004
Issued by

About this file

This solicitation requests proposals for submarine preservation services to support the Los Angeles-class submarine USS Toledo (SSN-769). The scope of work includes typical preservation and maintenance availability services to be performed at Norfolk Naval Shipyard in Portsmouth, Virginia from May 2021 through September 2022. Responses are due by February 15, 2021 and proposals shall remain valid for 180 days. The solicitation will be awarded using lowest price technically acceptable procedures following full and open competition in accordance with FAR Part 6. Only qualified sources capable of providing the services identified in the performance work statement should respond. The NAICS code is 336611 and the small business size standard is 1,250 employees.

View the file

Other files

File Type Posted
Questions RFP.docx DOCX document
N4215821RS0040008.pdf PDF
156-11-003.pdf PDF
New RFQ Questions..docx DOCX document
156-11-006.pdf PDF
156-11-005.pdf PDF
156-11-004.pdf PDF
Updated ESPECs.pdf PDF
N4215821RS004U0007.pdf PDF
N4215821RS004U0006.pdf PDF
N4215821RS0040005.pdf PDF
N4215821RZ0040004.pdf PDF
Answers to Questions from Offerors..pdf PDF
Submarine Preservation Questions-Answers.docx DOCX document
N4215821RS0040003..pdf PDF
Attachment 8-Solic-Pricing Breakdown-Submarine_Preservation.xlsx XLSX spreadsheet
N4215821RS0040003.pdf PDF
ESPEC 176-11-002.pdf PDF
N4215821RS0040001.pdf PDF
N4215821RS0040002.pdf PDF
N4215821RS004 RFP.pdf PDF
CDRL- USS TOLEDO PRESERVATION.pdf PDF
Attachment 6.docx DOCX document
Attachment 1.pdf PDF
ESPECs for USS Toledo.pdf PDF
Attachment 7.docx DOCX document
Attachment 9.docx DOCX document
Attachment 8.xlsx XLSX spreadsheet
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Proposal

REQUEST FOR PRICE PROPOSALN42158
VESSEL:USS Toledo (SSN-769)
LOCATION:NNSY, PORTSMOUTH, VA
CONTRACTOR:
CLINDESCRIPTIONPERIOD OF
PERFORMANCEMILESTONE DATESPRICE

0001 - Base Period Prepare for and accomplish submarine preservation for the USS Toledo (SSN-769), SSP: 502-21 (EXCLUDING spec items identified as option items). NON-OPTION ITEM Includes PRE-PLANNING in accordance with spec item 042-05-001.

Considering NAVSEA Standard Items, contractor’s price shall include the latest revision at time of solicitation.

For planning purposes, the Contractor shall consider all FEDERAL holidays and NNSY holiday routines.5/1/2021 - 4/30/2022* See Milestone Dates on the following tab$ - 0
0002 - Option Period 1Prepare for and accomplish submarine preservation for the USS Toledo (SSN-769), SSP: 502-21 (EXCLUDING spec items identified as option items). NON-OPTION ITEM Includes PRE-PLANNING in accordance with spec item 042-05-001.

Considering NAVSEA Standard Items, contractor’s price shall include the latest revision at time of solicitation.

For planning purposes, the Contractor shall consider all FEDERAL holidays and NNSY holiday routines.5/1/2022 - 9/30/2022* See Milestone Dates on the following tab$ - 0
Option ELINSPrepare for and accomplish submarine preservation for the USS Toledo (SSN-769). As exercised, the price for the option ELINS will be incorporated into CLINs 0001/0002 as appropriate via modification. The purpose of this line is to summarize the total price for all option ELINS.N/A* See Milestone Dates on the following tab$ - 0
TOTAL PRICE:$ - 0

&"-,Bold"&20USS TOLEDO SSN-769 Submarine Preservation

Milestones

*MILESTONE DATES FOR: Prepare for and accomplish submarine preservation for the USS TOLEDO (SSN 769), SSP: 501-14 (excluding spec items identified below as option items) (NON-OPTION ITEM)
Milestone dates are the expected date that the ESPEC Items will be ready for contractor work and are subject to change with the USS Toledo Project Schedule
E-SPEC NO.TITLEMILESTONE DATES
042-05-001GENERAL REQUIREMENTS FOR WORK ON SUBMARINES FOR NORFOLK NAVAL SHIPYARD DEPOT LEVEL AVAILABILITIES5/15/2021-9/30/2022
042-11-001GENERAL OCCUPATIONAL SAFETY, HEALTH, AND ENVIROMENT REQUIREMENTS FOR WORK WITHIN NORFOLK NAVAL SHIPYARD5/15/2021-9/30/2022
042-22-001GENERAL REQUIREMENTS FOR WORK WITHIN NORFOLK NAVAL SHIPYARD5/15/2021-9/30/2022
042-26-001SECURITY REQUIREMENTS FOR WORK WITHIN NORFOLK NAVAL SHIPYARD5/15/2021-9/30/2022
042-27-001ACCOUNTABILITY OF MANHOUR AND MATERIAL RESERVATION5/15/2021-9/30/2022
042-28-001SPECIAL REQUIREMENTS FOR NON-SUBSAFE WORK ON SUBMARINES5/15/2021-9/30/2022
042-88-001PAINTING REQUIREMENTS FOR SUBMARINES WITHIN NORFOLK NAVAL SHIPYARD5/15/2021-10/30/2022
042-89-001GENERAL RADIOLOGICAL REQUIREMENTS FOR NUCLEAR POWERED SUBMARINES AT NORFOLK NAVAL SHIPYARD5/15/2021-10/30/2022
111-11-003FAIRWATER, SSPC-SP 6 BLAST (INTERIOR)08/10/2021-9/15/2021
111-11-001FAIRWATER, SSPC-SP 6 BLAST (EXTERIOR)08/10/2021-9/15/2021
111-11-004PRESERVE FAIRWATER (INTERIOR) BLAST AND PAINT2/10/2022-3/20/2022
111-11-002PRESERVE FAIRWATER (EXTERIOR) BLAST AND PAINT2/10/2022-3/20/2022
131-11-001EXTERNAL HULL (TOTAL PRESERVATION)8/15/21 – 1/22/22
131-11-002SPECIAL HULL TREATMENT (SHT) REMOVE5/15/21- 5/15/22
131-11-003SPECIAL HULL TREATMENT (SHT) INSTALL8/15/22- 9/30/22
132-11-004VLS BATHTUB SSPC-SP 6 BLAST7/10/2021-8/14/2021
132-11-001RETRACTABLE BOW PLANE RECESS, SSPC-SP 6 BLAST8/10/2021-9/15/2021
132-11-008NON-PRESSURE HULL RECESSES - SSPC-SP 6 BLAST6/10/2021-7/20/2021
132-11-007PRESERVE NON-PRESSURE HULL RECESSES (TOUCH-UP)(Option Item)5/10/2022-6/30/2022
132-11-005PRESERVE VLS BATHTUB (BLAST/PAINT)12/10/2021-1/20/2022
132-11-002RETRACTABLE BOW PLANE RECESS, PRESERVE11/10/2021-12/18/2021
132-11-009PRESERVE NON-PRESSURE HULL RECESSES (BLAST/PAINT)11/10/2021-12/18/2021
156-11-002/004MAIN BALLAST TANK (MBT) LEAD BALLAST INSTALLATION FOR REBALLST(002 OPTION ITEM)1/15/22 – 3/30/22
156-11-006LEAD BALLAST REMOVE AUX #2 FOR REBALLAST (OPTION ITEM)1/15/22 – 2/15/22
156-11-005SEA TRIAL LEAD BALLAST INSTALLATION ( AUX 1 and AUX 2 )1/15/22 – 2/15/22
156-11-001/003MAIN BALLAST TANK (MBT) LEAD BALLAST REMOVAL FOR REBALLST (001 OPTION ITEM)8/15/21 – 10/15/21
176-01-001CLEAN SANITARY TANKS 1, 2, & 36/1/21 – 8/1/21
176-11-001MBT 1A, SSPC-SP 6 BLAST9/15/21 – 10/15/21
176-11-002MBT 1B, SSPC-SP 6 BLAST9/15/21 – 10/15/21
176-11-003MBT 2A, SSPC-SP 6 BLAST9/15/21 – 10/15/21
176-11-004MBT 2B, SSPC-SP 6 BLAST9/15/21 – 10/15/21
176-11-005MBT 3A, SSPC-SP 6 BLAST10/15/21 – 11/15/21
176-11-006MBT 3B, SSPC-SP 6 BLAST10/15/21 – 11/15/21
176-11-060MBT 4A, SSPC-SP 6 BLAST9/15/21 - 10-15-21
176-11-061MBT 4B, SSPC-SP 6 BLAST9/15/21 - 10-15-21
176-11-062MBT 5A, SSPC-SP 6 BLAST10/15/21 – 11/15/21
176-11-063MBT 5B, SSPC-SP 6 BLAST10/15/21 – 11/15/21
176-11-008PRESERVE MBT 1A, BLAST AND PAINT12/15/21 – 1/15/22
176-11-009PRESERVE MBT 1B, BLAST AND PAINT12/15/21 – 1/15/22
176-11-010PRESERVE MBT 2A, BLAST AND PAINT12/15/21 – 1/15/22
176-11-011PRESERVE MBT 2B, BLAST AND PAINT12/15/21 – 1/15/22
176-11-012PRESERVE MBT 3A, BLAST AND PAINT1/15/22 – 2/15/22
176-11-013PRESERVE MBT 3B, BLAST AND PAINT1/15/22 – 2/15/22
176-11-064PRESERVE MBT 4A, BLAST AND PAINT1/15/22 – 2/15/22
176-11-065PRESERVE MBT 4B, BLAST AND PAINT1/15/22 – 2/15/22
176-11-066PRESERVE MBT 5A, BLAST AND PAINT2/15/22 - 3/15/22
176-11-067PRESERVE MBT 5B, BLAST AND PAINT2/15/22 – 3/15/22
176-11-068AFT MAIN BALLAST TANK LEAD REMOVAL (OPTION ITEM)9/15/21 -10/15/21
176-11-041POTABLE WATER TANKS 1 AND 2; SSPC-SP 6 BLAST7/15/21 – 8/15/21
176-11-042POTABLE WATER TANKS 1 AND 2; PRESERVE (BLAST AND PAINT)12/1/21 – 1/10/22
176-11-029FORWARD BILGE COLLECTING TANK; SSPC-SP 6 BLAST8/15/21 – 9/15/21
176-11-030FORWARD BILGE COLLECTING TANK; preserve (BLAST AND PAINT)11/15/21 – 12/15/21
176-11-039Battery Compartment; blast (SSPC-SP 6)7/15/21-8/15/2021
176-11-040Battery Compartment; preserve (SSPC-SP 10 Blast and Paint)12/1/2021-1/10/2022
176-11-023TORPEDO IMPULSE TANK 1 & 2; SSPC-SP 6 BLAST8/1/21 – 9/1/21
176-11-024TORPEDO IMPULSE TANK 1 & 2; preserve (BLAST AND PAINT)11/1/21 – 12/1/21
176-11-031SEA WATER EXPANSION TANK; SSPC-SP 6 BLAST10/1/21 – 11/1/21
176-11-032SEA WATER EXPANSION TANK; PRESERVE (BLAST AND PAINT)12/1/21 – 1/1/22
176-11-036ALT AUX TANK (TOUCH UP)10/1/21 – 11/1/21
176-11-033ALT FWD TRIM (TOUCH UP)12/15/21 – 1/15/22
176-11-027FWD TRIM TANK; SSPC-SP 6 BLAST8/1/21 – 9/1/21
176-11-028FWD TRIM TANK; preserve (BLAST AND PAINT)11/1/21 – 12/15/21
176-11-021WRT TANK #1 & #2; SSPC-SP 6 BLAST8/15/21 – 9/15/21
176-11-022WRT TANK #1 & #2; preserve (BLAST AND PAINT)11/15/21 – 12/15/21
176-11-017AUXILARY TANK #1 & #2; SSPC-SP 6 BLAST9/15/21 – 10/15/21
176-11-019AUXILARY TANK #1 & #2; PRESERVE (BLAST AND PAINT)12/15/21 – 1/15/22
176-11-018AUXILARY TANK #3 & #4; SSPC-SP 6 BLAST10/1/21 – 11/1/21
176-11-020AUXILARY TANK #3 & #4; PRESERVE (BLAST AND PAINT)12/15/21 – 1/15/22
176-11-025SAN TANK 1, 2 & 3; SSPC-SP 6 BLAST7/1/21 – 9/1/21
176-11-026SAN TANK 1, 2 & 3; preserve (BLAST AND PAINT)9/1/21 – 11/1/21
176-11-014BOW TANK/ BOW SONAR TANK AND SPHERE, SSPC-SP 6 BLAST10/10/2021-2/18/2022
176-11-015PRESERVE BOW TANK/ BOW SONAR TANK AND SPHERE, BLAST & PAINT12/10/2021–1/15/2022
132-11-003Retractable Bow Plane (RBP) Recess blast (SSPC-SP 6) (OPTION ITEM)INVOKE BY 11/15/2021
132-11-006Vertical Launch System (VLS) Bathtub Recess, Surface Preparation blast (SSPC-SP 6) (OPTION ITEM)INVOKE BY 9/14/2021
176-11-007Forward Main Ballast Tank (MBT), Surface Preparation SSPC-SP 6 OPTION ITEMINVOKE BY 12/15/2021
176-11-016Sonar Bow Tank and Sonar Dome Access Trunk, Surface Preparation SSPC-SP 6 OPTION ITEMINVOKE BY 3/18/2022
176-11-034Alternate Forward Trim Tank; blast (SSPC-SP 6) (OPTION ITEM)INVOKE BY 10/15/2021
176-11-035Alternate Forward Trim Tank; preserve (SSPC-SP 10 Blast and Paint) (OPTION ITEM)INVOKE BY 1/15/2022
176-11-037Alternate Auxiliary Tank; blast (SSPC-SP 6) (OPTION ITEM)INVOKE BY 11/15/2021
176-11-038Alternate Auxiliary Tank; preserve (SSPC-SP 10 Blast and Paint) (OPTION ITEM)INVOKE BY 2/15/2022
991-11-001Scaffolding; provide5/15/2021-9/30/2022
997-11-001Ship's Docking Report, Inspection and Services; provide3/1/23

&"-,Bold"&20USS TOLEDO SSN-769 Submarine Preservation

Spend Plan Forecast - ALL ELINS

Base PeriodOption Period 1
Period Ending5/31/216/30/217/31/218/31/219/30/2110/31/2111/30/2112/31/211/31/222/28/223/31/224/30/225/31/226/30/227/31/228/31/229/30/22
Monthly Forecast$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Cumulative Forecast$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

Total - ALL ELINS

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEMTotal
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

Sub. Pres. Base Year

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEMSummary ELIN Base Year
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

Sub. Pres. Second Year (OPT 1)

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEMSummary ELIN Option Year 1
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

Summary ELIN Options

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEMSummary Options
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

042-05-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM-042-05-001042-05-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

042-11-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM042-11-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

042-22-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM042-22-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

042-26-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM042-26-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

042-27-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM042-27-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

042-28-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM042-28-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

042-88-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM042-88-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

042-89-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM042-89-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

111-11-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM111-11-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

111-11-002 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM111-11-002
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

111-11-003 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM111-11-003
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

111-11-004 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM111-11-004
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

131-11-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM131-11-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

131-11-002 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM131-11-002
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

131-11-003 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM131-11-003
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

132-11-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM132-11-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

132-11-002 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM132-11-002
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

132-11-004 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM132-11-004
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

132-11-005 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM132-11-005
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

132-11-008 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM132-11-008
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

132-11-009 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM132-11-009
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

156-11-003 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM156-11-003
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

156-11-004 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM156-11-004
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

156-11-005 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM156-11-005
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

176-01-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM176-01-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

176-11-001 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM176-11-001
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

176-11-002 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM176-11-002
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

176-11-003 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM176-11-003
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

176-11-004 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM176-11-004
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

176-11-005 ELIN

REQUEST FOR PRICE PROPOSALN42158-21-R-S004NO. PAGES: 1 OF 1
VESSEL: USS Toledo (SSN-769)POP: Base Year 5/1/2021 to 4/30/2022 with 1-6 Month Option Ending September 30, 2022
LOCATION: NNSY, PORTSMOUTH, VACORs:TBD
CONTRACTOR:CLOSING:TBD
ITEM631-11-005
DESCRIPTIONPRIME QTYSUBKR QTYTOTAL QTYUNIT OF ISSUEUNIT PRICETOTAL
Project Manager STHr
Project Engineer STHr
Project Engineer OTHr
Supervisor STHr
Supervisory OTHr
Quality Assurance STHr
Quality Assurance OTHr
Marine Chemist STHr
Marine Chemist OTHr
Competent Person STHr
Competent Person OTHr
Rigger STHr
Rigger OTHr
Carpenter STHr
Carpenter OTHr
Shipfitter STHr
Shipfitter OTHr
Painter/Sandblaster STHr
Painter/Sandblaster OTHr
Burner/Welder STHr
Burner/Welder OTHr
Laborer STHr
Laborer OTHr
Tank Cleaner STHr
Tank Cleaner OTHr
Shipwright STHr
Shipwright OTHr
Firewatch STHr
Firewatch OTHr
MaterialDollars
Material G&A handlingDollars
TravelDollars
Travel G&ADollars
StagingDollars

TOTAL Dollars $0.00

176-11-006 ELIN

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .