Upgrade Restrooms DLA Multiple Bldgs.
Solicitation number
N400857179549
Issued by

About this file

This is Amendment 0007 to a solicitation for upgrading restrooms in multiple DLA buildings at MCAS Cherry Point, NC. The amendment provides responses to 22 pre-award RFIs and includes revised specifications for several sections including Total Building Commissioning, Paints and Coatings, Fire Protection Systems, Plumbing, and Fire Alarm Systems.

Key details include: proposal due date remains January 8, 2025 at 12:00 PM local time; fire alarm/mass notification and sprinkler systems are not required in temporary bathroom trailers; QFPE roughin inspection is only required for new rooms 150A, 150B, and 150C in Building 150; fire alarm system testing is only required on modified circuits; and revisions were made to multiple drawing sheets including floor plans, interior elevations, and plumbing details. The amendment also clarifies that temporary trailer submittals will be evaluated for overall compliance with drawings and specifications, with minor deviations potentially being acceptable. Several specification sections were updated including new requirements for concrete sealer products and commissioning procedures.

View the file

Other files

File Type Posted
Amendment 0008 7179548.pdf PDF
Amendment 0006 7179548.pdf PDF
Amendment 0005 7179548.pdf PDF
Amendment 0004 7179548.pdf PDF
Amendment 0003 7179548.pdf PDF
Amendment 0002 7179548.pdf PDF
Amendment 0001 7179548.pdf PDF
RFP 7179548.pdf PDF
7179548 DrawingsAsOne SIGNED.pdf PDF
7179548 SpecsAsOne SIGNED.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVFAC

SPECIFICATION

7179548 Upgrade Restrooms DLA Multiple Bldgs.

MCAS Cherry Point, NC

AMENDMENT #0007

IMPORTANT

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of the proposal.

If your proposal has been submitted prior to the receipt of this amendment, acknowledgement should be made by telegram, which should state whether the price contained in your proposal is to remain unchanged, is to be decreased by an amount, or is to be increased by an amount. The acknowledgement must be received prior to proposal opening time.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0007 12/30/2024 7179548

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code

CG MCAS Cherry Point

FACILITIES, ROICC

B-87, 748 Roosevelt Blvd.

PSC BOX 8006

CHERRY POINT, NC 28533

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION

Upgrade Restrooms DLA Multiple Bldgs.

9B. DATED (SEE ITEM 11)

AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL 10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return original to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

7179548 Upgrade Restrooms DLA Multiple Bldgs., Marine Corps Air Station Cherry Point, NC

Amendment 0007 is being issued to answer pre-award RFI’s.

The deadline to submit pre-award RFI’s has passed. No further RFI’s will be accepted.

The proposal due date of 08 January 2025 at 12:00 PM local time REMAINS unchanged.

See Attached.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

Amendment 0007 7179548 Upgrade Restrooms DLA Multiple Bldgs.

RFI Responses:

1. Could the government please provide the details for the hardware sets that are indicated on the door schedule that are to appear in 08710? There are no Specifications available for hardware.

Response:

See revised specification 08 71 00 for hardware sets. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

2. The specs say the CxC is hired by the Government. Commissioning Provider (CxC) ‐ The entity hired by the Government, who leads, plans, and coordinates the Commissioning Team. The terms Commissioning Provider, Commissioning Firm, Lead Commissioning Specialist, Commissioning Specialist, and Commissioning Authority (CA or CxA) when used by sustainable Third‐Party Certification (TPC) programs, are interchangeable. Please verify that all commissioning costs are excluded from this contract.

See revised spec section 01 91 00.15 20 dated 20 DEC 2024. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

3. Bid documents don’t appear to require fire alarm, mass notification, or fire sprinkler systems in the temporary bathroom trailers. Please confirm whether Contractor is responsible for design or construction of fire protection systems in temporary trailers.

Response: Fire alarm, mass notification and sprinklers are not required in the temporary bathroom trailers. See revised NAVFAC Drawing No. 12882187 dated 23 DEC 2024. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

4. Bid documents include spec 07 84 00 “Firestopping”, but drawings don’t appear to identify new or existing fire‐rated construction. Please clarify whether project includes firestopping, and if so, how should the Contractor identify the rating and extent of existing fire‐rated construction.

Response: Project is not anticipated to include firestopping. This specification section has been included in the event that situations requiring it outlined in other specification sections are encountered per direction from the NAVFAC FPE. Submit proposals in accordance with RFP,

5. Division 21 and 28 specs say QFPE must perform “in‐progress construction surveillance prior to installation of ceilings (rough‐in inspection).” In areas where work includes new ceilings, design drawings depict scope as limited to adding/relocating sprinklers and installing several fire alarm notification appliances throughout the entire project. There will be little for the QFPE to see before ceiling installation, and each site visit will inflate project cost. Please confirm whether QFPE must perform construction surveillance before ceiling installation.

Response: Rough‐in inspection prior to ceiling installation by the QFPE must only be performed for new rooms 150‐A, 150‐B, and 150‐C in Building 150. See Revised division 21 and 28 specification sections dated 17 DEC 2024. Submit proposals in accordance with RFP,

6. Division 28 specs require fire alarm and fire alarm/mass notification system testing including audibility/intelligibility tests, loop resistance tests, tests of “each initiating device and notification appliance”, functional tests, primary/secondary power tests, circuit spare capacity tests, and voltage drop tests. Project scope generally includes minor adjustments to existing fire alarm circuits; testing/remediating existing system‐wide conditions would be more expensive. Please clarify required extent of fire alarm and fire alarm/mass notification system testing.

Response: System testing is only required on modified circuits. As noted in specification sections, contractor is to test the existing system and identify any deficiencies. Deficiencies identified before commencing work are not the responsibility of the contactor to remediate.

See revised Division 28 specification sections dated 17 DEC 2024. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

7. RFP (“Proposal Requirements” file) paragraph 1.2 refers to CLINs 0002, 0003, 0004, 0005, 0006, and 0007. The price proposal sheet doesn’t refer to CLINs 0006 and 0007. Please advise.

See Amendment 0004. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

8. The submittal and review time for the Health & Safety Plan, coordination with existing tenants, and front‐end coordination requirements for this project make the contract completion time of 380 days unachievable. Would the government consider extending the contract duration by 99 additional days?

See Amendment 0002. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

9. Could the government provide an interior signage schedule including design and materials of the required signage?

Response:

See Signage Note #3, B4/A‐603. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

10. CLIN’s do not include additional time if awarded with this contract. Is 380 days for all CLIN’s specified in the RFP? If so, more time is required to complete the project due to the additional coordination and requirements.

See Amendment 0002. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

11. The specifications call for surveillance and lighting at all construction locations. Could the government elaborate on these requirements?

Response:

Insufficient information to identify the source and context of the comment within the specifications. Submit proposals in accordance with RFP, Specifications, Drawings and all

12. Please clarify the number of temporary modular restroom buildings you’re requesting and the sizes for each building. It seemed confusing on Plan CS 502 that Type A is a 12’x34’ Male/ Female restroom trailer and then there is an 8’X12’ single stall men temp toilet structure with an ADA ramp and step‐ Please clarify drawings on this page and what is being requested as the requirement?

Sheet CS502 indicates temporary head facilities Types “A” and “B”, including requisite sizes; site layout drawing sheets CS101 through CS103 indicate locations of each type. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

13. Will aluminum engineered ADA deck, ramps and steps be acceptable or will you accept pressure treated wood decks, ramps, and steps?

Response:

No material requirements nor restrictions are provided. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

14. Will you accept used trailers, or must they be Brand new?

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

15. Will you accept minor design deviations from the drawings for the floorplans of the temporary restroom trailers?

Response:

Temporary trailer submittal will be evaluated for overall compliance with drawings and specifications; minor deviations from floor plans may be acceptable. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

16. Division 21 and 28 specs say QFPE must attend separate “Pre‐Government” and

“Government Final” testing. Each QFPE site visit will inflate project cost; considering the limited Fire Protection scope, is it necessary for the QFPE to attend “Pre‐Government” testing in person? Regular communication between QFPE and Contractor, in addition to

QFPE review of photographs and test reports, could be a cost‐effective alternative to physical attendance for minimal fire protection system testing?

Response: QFPE attendance is not required at the Government Final testing, only prefinal testing per the specifications. Submit proposals in accordance with RFP, Specifications, Drawings and all

17. On drawing P‐108 (C1), it shows a Backflow Preventer in the Janitor Room but the Fixture

Schedule on P‐501 doesn’t have it listed. Could this please be added to the Fixture Schedule?

Response: See previous response in Amendment. Submit proposals in accordance with RFP,

18. Is there a specification for floor sealer? Floor at 145‐A is peeling in several spots how should this floor be treated?

Response:

See 02 41 00 for floor prep. See revised section 09 90 00 dated 20 DEC 2024 for added sealer product, paragraph 3.11.1.1. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

19. Drawing A‐101 Restroom at B145: Area outside of restroom is shaded in grey to indicate slab removal but there is no demolition keynote #1 in the area. Can we confirm if the slab outside of the restroom is coming out?

See revised drawing sheet 12882155 23 DEC 2024. Submit proposals in accordance with RFP,

20. Looking at drawing P‐109 details C1 & C3 it shows 1ea P‐14 plumbing fixtures. A P‐14 fixture is not listed in the Plumbing Fixture Schedule. Is this a mis tagged item, or will there be a P‐ 14 fixture required?

See revised Fixture Schedule on NAVFAC Drawing No. 12882213 with revision date of December 10, 2024. Submit proposals in accordance with RFP, Specifications, Drawings and all

21. If the P‐14 Plumbing fixture is required, may we get this fixture added to the plumbing fixture schedule and plumbing specifications?

Response:

See revised Fixture Schedule on NAVFAC Drawing No. 12882213 with revision date of December 10, 2024. Also, please see updated paragraph that reflects the specification for the double‐bowl service sink. Submit proposals in accordance with RFP, Specifications, Drawings and all

22. Drawing P‐110 Detail C1 Partial; Construction Plan, Bldg. 159‐water shows a water line entering room 159‐L Women, the size of the water line (Domestic Cold Water) is not shown.

Detail A1 (B159 Riser‐Water) on drawing P‐703 does not show this branch of pipe which connects to the existing water line. What size pipe is this incoming water line?

See revised Detail C1 on NAVFAC Drawing No. 12882209 with revision date of December 10, 2024. Also, we revised Detail A1 on NAVFAC Drawing No. 12882216 with revision date of December 10, 2024. These drawings show delineation point for cold water as well as the assumed size for where it connects. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

Subj: AMENDMENT TO WO 7179548, Upgrade Restrooms DLA Dist Multiple Buildings, MCAS CHERRY POINT NC

CONTINUATION SHEET

PROJECT TABLE OF CONTENTS

SECTION 01 91 00.15 20, TOTAL BUILDING COMMISSIONING is deleted and 01 91

00.15 20, TOTAL BUILDING COMMISSIONING, dated 20 DEC 2024, as shown in the footer, is added to the Project Table of Contents and accompanies this Amendment.

SECTION 09 90 00, PAINTS AND COATINGS is deleted and 09 90 00, PAINTS AND COATINGS, dated 20 DEC 2024, as shown in the footer, is added to the Project Table of Contents and accompanies this Amendment.

SECTION 21 13 13, WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION is deleted and 21 13 13, WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION, dated 17 DEC 2024, as shown in the footer, is added to the Project Table of Contents and accompanies this Amendment.

SECTION 22 00 00, PLUMBING is deleted and 22 00 00, PLUMBING, dated 17 DEC 2024, as shown in the footer, is added to the Project Table of Contents and accompanies this Amendment.

SECTION 28 31 60, INTERIOR FIRE ALARM SYSTEM, NON-ADDRESSABLE is deleted and 28 31 60, INTERIOR FIRE ALARM SYSTEM, NON-ADDRESSABLE dated 17 DEC 2024, as shown in the footer, is added to the Project Table of Contents and accompanies this Amendment.

SECTION 28 31 70, INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE is deleted and 28 31 70, INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE dated 17 DEC 2024, as shown in the footer, is added to the Project Table of Contents and accompanies this Amendment.

SECTION 28 31 76, INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,

ADDRESSABLE is deleted and 28 31 70, INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM, ADDRESSABLE dated 17 DEC 2024, as shown in the footer, is added to the Project Table of Contents and accompanies this Amendment.

SUBMITTAL REGISTER is deleted and SUBMITTAL REGISTER dated 23 DEC 2024, as shown in the footer, is added to the Project Table of Contents and accompanies this Amendment.

DOCUMENT 00 01 15

1.2 CONTRACT DRAWINGS

The following drawings are revised as of 10 DEC 2024:

NAVFAC DWG NO. TITLE

12882155 A-101 PARTIAL FLOOR PLANS: B145 & B146

12882157 A-103 PARTIAL FLOOR PLANS: B147

12882174 A-405 INTERIOR ELEVATIONS

12882175 A-406 INTERIOR ELEVATIONS

12882176 A-407 INTERIOR ELEVATIONS

12882177 A-408 INTERIOR ELEVATIONS

12882178 A-409 INTERIOR ELEVATIONS

12882179 A-410 INTERIOR ELEVATIONS

12882180 A-411 INTERIOR ELEVATIONS

12882181 A-412 INTERIOR ELEVATIONS

Subj: AMENDMENT TO WO 7179548, Upgrade Restrooms DLA Dist Multiple Buildings, MCAS CHERRY POINT NC

12882182 A-413 INTERIOR ELEVATIONS

12882209 P-110 PARTIAL FLOOR PLANS: B159 – PLUMBING

12882213 P-501 PLUMBING RISERS

12882216 P-703 PLUMBING RISERS

These drawings accompany this Amendment.

The following drawings are revised as of 17 DEC 2024:

NAVFAC DWG NO. TITLE

12882187 F-001 FIRE PROTECTION LEGEND, NOTES & DETAILS

This drawing accompanies this Amendment.

Upgrade Restrooms, DLA Distribution, Multiple Buildings WO# 7179548 MCAS Cherry Point, NC 5 March 2023

SECTION 01 91 00.15 20

TOTAL BUILDING COMMISSIONING

02/21, CHG 1: 05/21

PART 1 GENERAL

Total Building Commissioning (TBCx) is a systematic, quality-focused process for enhancing the delivery of a project that focuses on verifying and documenting that all of the commissioned systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the project requirements. The purpose is to reduce the cost and performance risks associated with delivering facilities projects, and to increase value to owners, occupants, and users.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 202 (2018) Commissioning Process for Buildings and Systems

ASSOCIATED AIR BALANCE COUNCIL (AABC)

ACG Commissioning Guideline (2005) Commissioning Guideline

NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)

NEBB Commissioning Standard (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

ANSI/SMACNA 014 (2013) HVAC Systems Commissioning Manual, 2nd Edition

1.2 DEFINITIONS

Commissioning Process (Cx) - a quality-focused process for enhancing the delivery of a project. Refer to ASHRAE 202 for a comprehensive description of the commissioning process.

Commissioning Provider (CxC) - The entity who leads, plans, and coordinates the Commissioning Team. The terms Commissioning Provider, Commissioning Firm, Lead Commissioning Specialist, Commissioning Specialist, and Commissioning Authority (CA or CxA) when used by sustainable Third Party Certification (TPC) programs, are interchangeable.

Commissioning Authority – The Government retains the authority for oversight and assurance of the entire commissioning process, and final approval of all commissioning deliverables.

SECTION 01 91 00.15 20 Page 1

REVISED 20 DEC 2024

1.3 COMMUNICATION WITH THE GOVERNMENT

The Lead Commissioning Specialist (CxC) must submit all plans, schedules, reports, and documentation directly to the Contracting Officer's Representative concurrent with submission to theManager.

The Lead Commissioning Specialist must have direct communication with the Contracting Officer's Representative regarding all elements of the commissioning process; however, the Government has no direct contract authority with the Lead Commissioning Specialist.

1.4 SYSTEMS TO BE COMMISSIONED

Coordinate commissioning and quality control activities for the following systems, equipment, and associated controls. System-specific requirements are located in the associated specification Sections. Commission the following systems, equipment, and associated controls in accordance with this section and the inspection, testing, and quality control requirements of their respective sections:

Heating, ventilating, air-conditioning, and refrigeration systems (mechanical and passive) and associated controls

Lighting systems: automatic and manual daylighting controls, occupancy sensing devices, automatic shut-off controls, time switching, and other lighting control devices, and dimming systems

Domestic hot-water systems and controls

1.5 COMMISSIONING TEAM

The Commissioning team will include, but is not limited to the following team members.

Ensure all Construction Activities for systems to be commissioned are coordinated with the appropriate commissioning team members.

a. Lead Commissioning Specialist (CxC)

b. Quality Control Manager (QCM)

c. Sub-Contractor Representatives for each trade responsible for construction/installation of systems to be commissioned

d. Construction Manager (CM)

e. Designer of Record (DOR)

f. Technical Commissioning Specialists for each system to be commissioned

g. TAB Representative

h. Equipment manufacturer representatives

SECTION 01 91 00.15 20 Page 2

i. Government Contracting Officer

j. Government Representatives

l. Installation Maintenance Representative

m. Facility End User n.

1.6 PROJECT SCHEDULE

Include the following tasks in the project schedule required by Section.

Ensure sufficient time is scheduled to complete each item. The order of items listed below is not intended to imply a specified sequence:

a. Submission and approval of the Commissioning Firm Qualifications

c. Submission and approval of the Design Review Report

d. Submission and approval of the Interim and Final Construction Phase Commissioning Plans

e. Commissioning Kickoff Coordination Meeting

f. Regular Commissioning Coordination Meetings

g. Installation of permanent utilities (gas, water, electric)

j. Manufacturer's Equipment Start-Up for each of the systems to be commissioned

k. Submission and approval of the Completed Pre-Functional Checklists

l. Submission and approval of Certificate of Readiness for each system to be commissioned

m. Functional Performance Testing for each system to be commissioned

n. Integrated Systems Tests

o. Post-test deficiency correction for each system to be commissioned

p. Re-Testing

r. Training for each of the systems to be commissioned

s. Submission and approval of the Initial and Final Commissioning Reports

t. Seasonal Testing

v. Warranty Phase Site Visit

w. Updated Commissioning report

1.7 PHASING

This project includes multiple phases andbuildings. Commissioning activities for each project phase and building must be scheduled

SECTION 01 91 00.15 20 Page 3 separately and must correspond to each completion milestone in the master schedule.

1.8 SUBMITTALS

Government approval is required for all submittals for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-06 Test Reports

Interim Construction Phase Commissioning Plan; G

Final Construction Phase Commissioning Plan; G; S

Initial Commissioning Report; G

Issues Log; G

Completed Pre-Functional Checklists; G

SD-07 Certificates

Commissioning Firm; G

Certificate Of Readiness; G

SD-11 Closeout Submittals

Final Commissioning Report; G

Updated Final Commissioning Report; G

1.9 COMMISSIONING FIRM

Employ the services of a Commissioning Firm and all Commissioning Specialists required to perform work for this project. The Commissioning Firm must be a first-tier subcontractor that is financially and corporately independent from contractor and all other subcontractors and the Designer of Record.

a. Submit the Commissioning Firm's and Commissioning Specialists' qualifications, including the name of the firm and each CxC and each certification, no later than 30 calendar days after Notice to Proceed.

b. If, for any reason, a specialist loses a certification during this period, immediately notify the Contracting Officer and submit another Commissioning Specialist for approval. Validate all work performed for this project by the CxC who lost a certification by an approved successor.

1.9.1 Commissioning Specialists (CxC)

Assign Lead Commissioning Specialist and other appropriate Commissioning Specialists for the systems to be commissioned.

1.9.1.1 Lead Commissioning Specialist (CxC)

Lead Commissioning Specialist (CxC) coordinates all aspects of the

SECTION 01 91 00.15 20 Page 4 commissioning process. Duties include leading and overseeing the commissioning work, and acting as the primary point of contact for the commissioning work. CxC may serve as a systems Specialist if all requirements for both designations are met. CxC must have a minimum of five years of commissioning experience, including two projects of similar size and complexity to this project.

CxC must be certified in one of the following:

NEBB qualified Systems Commissioning Administrator (SCA)

ACG Certified Commissioning Authority (CxA)

ICB/TABB Certified Commissioning Supervisor

BCA Certified Commissioning Professional (CCP)

AEE Certified Building Commissioning Professional (CBCP)

University of Wisconsin-Madison Qualified Commissioning Process Provider (QCxP)

ASHRAE Building Commissioning Professional (BCxP).

1.9.1.2 Commissioning Specialists

Commissioning Specialists with the following qualifications must perform the technical work associated with each system to be commissioned:

a. Mechanical Commissioning Specialist: The technical work associated with mechanical systems to be commissioned must be performed by a Commissioning Specialist certified by NEBB, ACG, ICB/TABB, AEE, University of Wisconsin-Madison, ASHRAE, or BCA in the commissioning of HVAC systems with five years of experience in the commissioning of HVAC systems.

b. Electrical Commissioning Specialist: The technical work associated with electrical systems to be commissioned must be performed by an engineering technician with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.

1.9.2 Commissioning Standard

Comply with the requirements of the commissioning standard under which the Commissioning Firm and Specialists qualifications are approved. When the firm and specialists are certified by BCA, AEE, ASHRAE, or the University of Wisconsin-Madison, comply with the requirements of one of these acceptable standards: ACG Commissioning Guideline , NEBB Commissioning Standard , ANSI/SMACNA 014 , or ASHRAE 202. Comply with applicable NETA testing standards for electrical systems.

a. Implement all recommendations and suggested practices contained in the Commissioning Standard and electrical test standards.

b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.

c. Where the instrument manufacturer calibration recommendations are more

SECTION 01 91 00.15 20 Page 5 stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.

d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract.

e. The Commissioning Specialists must develop commissioning procedures for any systems or system components not covered in the Commissioning Standard.

f. Use any new requirements, recommendations, and procedures published or adopted by the body responsible for the Commissioning Standard at the time of project award.

g. If there is a conflict between the requirements of the contract documents and the commissioning standard used, the contract documents take precedent.

1.10 ISSUES LOG

The Commissioning Specialist develops and maintain an Issues Log for the systems to be commissioned. The issues log documents and tracks resolution of deficiencies identified during submittal reviews, inspection, and testing. At any point during construction, any commissioning team member finding deficiencies may communicate those deficiencies in writing to the Commissioning Specialist for inclusion into the Issues Log. For each issue, the Issues Log includes, but is not limited to, a unique reference number, description of the issue with contract requirement referenced, location of or equipment name/tags exhibiting the issue, the initials of the individual's name whom reported the issue, the date of first observation, the proposed resolution of the issue and date proposed, the date of any subsequent observations with applicable additional information, and the date of implementation of the final resolution of the issue as confirmed by the Commissioning Specialist and Contracting Officer. Issues must not be deleted from the issues log.

CxC must submit the Issues Log monthly and within three working days from changes to the Issue Log. The CxC is responsible for distributing the Issues Log to the Commissioning Team.

1.11 CERTIFICATE OF READINESS

Prior to scheduling Functional Performance Tests, the Quality Control Manager must issue a Certificate of Readiness for each system, certifying that pre-functional checks have been completed, open issues have been resolved, and the system is ready for Functional Performance Testing. The Certificate of Readiness must include, for each system to be commissioned, equipment and system start-up reports; completed Pre-Functional Checklists; Testing, Adjusting, and Balancing (TAB) Report; Issues Log;

and HVAC Controls Start-Up Reports to the extent applicable to the system. Sign and date the Certificate of Readiness, and include signatures and dates from the CxC; the Quality Control Representative; the Mechanical, Electrical, Controls, and TAB subcontractor representatives.

Submit the Certificate of Readiness for each system 14 calendar days prior to Functional Performance Tests of that system. Do not schedule Functional Performance Tests for a system until the Certificate of Readiness is approved by the Government.

SECTION 01 91 00.15 20 Page 6

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 CONSTRUCTION SUBMITTAL REVIEWS

Coordinate construction submittal document reviews for commissioned systems and assemblies with the CxC. The commissioning submittal review does not replace the designer of record (DoR) or Government submittal review, in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.

The CxC must identify construction submittals to be provided by the contractor for the commissioned systems. The CxC must evaluate construction submittals for compliance with the contract documents.

Include a copy of the submittal document review transmittal and response in the Commissioning Report.

3.2 COMMISSIONING KICKOFF MEETING

Conduct a Commissioning Kickoff Meeting, led by the CxC, after approval of the Commissioning Firm and Commissioning Specialists, and no later than 60 days following construction notice to proceed. Discuss the commissioning process including contract requirements, lines of communication, roles and responsibilities, schedules, documentation requirements, inspection and test procedures, and logistics as specified in this section.

The Quality Control team, Designer of Record, and the Government must attend this meeting. Invite the User and to attend this meeting.

3.3 REGULAR COMMISSIONING COORDINATION MEETINGS

The Quality Control team, Designer of Record, and the Government must attend this meeting. Invite the User and to attend this meeting.

CxC must conduct monthly commissioning coordination meetings when installation of commissioned systems begins. Provide status of commissioned systems, open issues log items, outstanding submittals, and upcoming commissioning activities. Conduct bi-weekly commissioning coordination meetings within 30 days of the scheduled date for functional performance testing.

3.4 CONSTRUCTION PHASE COMMISSIONING PLANS

The Interim Construction Phase Commissioning Plan identifies the commissioning and testing standards and outline the overall commissioning process, the commissioning schedule, the commissioning team members and responsibilities, lines of communication, documentation requirements for the construction phase of the project. Submit the Interim Construction Phase Commissioning Plan 14 calendar days after the Construction Commissioning Coordination Meeting and 14 days prior to the start of construction of the building envelope.

The Final Construction Phase Commissioning Plan includes the information provided in the Interim Construction Phase Commissioning Plan as well as the Pre-Functional Checklists, Integrated Systems Test Checklists, and Functional Performance Test Checklists for each building, for each system required to be commissioned, and for each component for inclusion in the

SECTION 01 91 00.15 20 Page 7

Final Construction Phase Commissioning Plan. Submit the Final Construction Phase Commissioning Plan no later than 90 calendar days prior to the start of Pre-Functional Checks.

3.4.1 Pre-Functional Checklists

The Pre-Functional Checklists must include items for physical inspection or testing that demonstrate that installation and start-up of equipment and systems is complete. Refer to paragraph PRE-FUNCTIONAL CHECKS.

Pre-functional checklists must be tailored to verify the specific installation requirements and details of the construction documents and manufacturer's instructions.

3.4.2 Functional Performance Test Checklists

Functional Performance Test Checklists must include procedures that explain, step-by-step, the actions and expected results that will demonstrate that the system performs in accordance with the contract.

Refer to paragraph FUNCTIONAL PERFORMANCE AND INTEGRATED SYSTEMS TESTS.

Include the following sections and details appropriate to the systems being tested in the Functional Performance Test Checklists:

a. Notable system features including information about controls to facilitate understanding of system operation

b. Conclusions and recommendations. Conclusions must clearly indicate if system does or does not perform in accordance with contract requirements. Recommendation must clearly indicate that the system should or should not be approved by the Government.

c. Test conditions including date, beginning and ending time, and beginning and ending outdoor air conditions

d. Attendees

e. Identification of the equipment involved in the test

f. Control system feature identification

g. Point-to-point observations including demonstrating system flow meters and sensors have been calibrated and are correctly displayed on the Operator work station

h. Actuator operation observations demonstrating actuator responses to commands from the control system

i. As-found condition of the system operation

j. List of test items with step numbers along with the corresponding feature or control operation, intended test procedure, expected system response, and pass/fail indication.

k. Space for comments for each test item.

3.4.3 Integrated Systems Test Checklists

Integrated Systems Test Checklists must include test procedures that explain, step-by-step, the actions and expected results that will demonstrate that the interactive operations between systems performs in

SECTION 01 91 00.15 20 Page 8 accordance with the contract. Refer to paragraph FUNCTIONAL PERFORMANCE AND INTEGRATED SYSTEMS TESTS. Include the following sections in the Integrated Systems Test Checklists:

a. Notable features of the interconnected systems organized by discipline including information to facilitate understanding of system operation

b. Conclusions and recommendations. Conclusions must clearly indicate if the systems do or do not perform in accordance with contract requirements. Recommendation must clearly indicate that the systems should or should not be approved by the Government

c. Test conditions including date and beginning and ending time

d. Identification of the equipment and systems involved in the test

e. List of test items with step numbers along with the corresponding feature or control operation, intended test procedure, expected system response, and pass/fail indication.

f. Space for comments for each test item.

3.5 PRE-FUNCTIONAL CHECKS

Complete one Pre-Functional Checklist for each individual item of equipment or system for each system required to be commissioned including, but not limited to, ductwork, piping, equipment, fixtures (lighting and plumbing), and controls. Indicate commissioning team member inspection and validation of each Pre-Functional Checklist item by initials.

Validation of each Pre-Functional Checklist item by each team member indicates that item conforms to the contract documents and validated design in their area of responsibility. Commissioning Specialist validation of each Pre-Functional Checklist item indicates that each item has been installed correctly and in accordance with contract documents.

Submit the initialed and Completed Pre-Functional Checklists no later than 7 calendar days after completion of inspection of all checklists items for each system. Include manufacturer start-up checklists associated with equipment with the submission of the Pre-Functional Checklists.

3.6 FUNCTIONAL PERFORMANCE AND INTEGRATED SYSTEMS TESTS

Demonstrate that all system components have been installed, that each control device and item of equipment operates, and that the systems operate and perform, including interactive operation between systems, in accordance with contract documents. Provide all materials, services, and labor required to perform the Pre-Functional Checks, Integrated Systems Tests, and Functional Performance Tests.

Commissioning Specialist's duties include leading and documenting all tests for the systems to be commissioned with appropriate sub-contractors performing the Tests. The representatives listed in the paragraph Commissioning Team must attend the tests.

Perform Integrated Systems Tests only after the Functional Performance Tests for each associated system are completed with all deficiencies resolved and after the related Functional Performance Test Checklists have been signed by each commissioning team member.

SECTION 01 91 00.15 20 Page 9

3.6.1 Test Scheduling and Coordination

Conduct Initial Functional Performance Tests as soon as all contract work is completed, regardless of the season. Develop and implement means of artificial loading to demonstrate, to a reasonable level of confidence, the ability of the HVAC systems to handle peak seasonal loads. Schedule Functional Performance Tests for each system only after the Certificate of Readiness has been approved by the Government for the system. Correct all deficiencies identified through any prior review, inspection, or test activity before the start of Functional Performance Tests.

Functional Performance Tests and Integrated Systems Tests must be performed with the CxC present. Government reserves the right to witness all tests. Coordinate test schedule with Government representatives.

3.6.2 Testing Procedures

Functional performance testing is conducted by simulating conditions at control devices to initiate a control system response. Over-writing control input values through the control system is not allowed unless approved by the Contracting Officer. Do not simulate conditions when damage to the system or building may result.

Follow the Functional Performance Test from the approved Final Construction Phase Commissioning Plan. Perform Functional Performance Tests for each item of equipment and each system required to be commissioned. Verify all sensor calibrations, control responses, safeties, interlocks, operating modes, sequences of operation, capacities, lighting levels, and all other performance requirements comply with contract, regardless of the specific items listed within the checklists provided. In general, testing must progress from equipment or components to subsystems to systems to interlocks and connections between systems.

Commissioning Specialists are responsible for determining the order of components and systems to be tested. Indicate validation of each item of equipment and systems tested by signature of each commissioning team member for each test. The Quality Control Representative, Commissioning Specialists, and Contracting Officer's Representative, if present, must indicate validation after the equipment and systems are free of deficiencies.

3.6.3 Integrated Systems Tests

Follow the Integrated Systems Test Checklists from the approved Final Construction Phase Commissioning Plan. Integrated Systems Tests must be performed for the interactive operation between systems such as HVAC systems, fire protection systems, back-up electrical supply, energy generation systems, and other systems, and verify correct interactive operation, acceptable speed of response, and other contract requirements for both normal and failure modes. Examples of Integrated Systems Tests include the correct operation of HVAC systems during emergency system activation, correct operation of uninterruptible power supplies or energy generators and connected systems, or lighting system operation during power outage or emergency system activation.

3.6.4 Sample Strategy

Perform Functional Performance Tests and Integrated Systems Tests for all systems and equipment to be commissioned using the sample strategy identified herein. Complete a Functional Performance Test Checklist for

SECTION 01 91 00.15 20 Page 10 each item of equipment or system to be tested. For sample sizes less than 100 percent for similar equipment, the Contracting Officer's Representative reserves the right to select the specific equipment or system to be tested during testing. Perform Integrated Systems Tests for all systems and equipment having interactive operation. Complete an Integrated Systems Test Checklist for each item of equipment or system.

Test all central plant equipment, primary air handling units, and process cooling or heating equipment. Test all system-level equipment serving multiple zones. Twenty percent sample testing is allowed for large groups of identical equipment with identical controllers serving single zones such as air terminal units, fan coil units, unitary equipment, lighting zones, and plumbing fixtures.

3.6.4.1 100 Percent Sample Procedures

Systems or equipment for which 100 percent sample size are tested fail if one or more of the test procedures results in discovery of a deficiency and the deficiency cannot be resolved within 5 minutes during the test.

Re-test to the extent necessary to confirm that the deficiencies have been corrected without negatively impacting the performance of the rest of the system.

3.6.4.2 Less than 100 Percent Sample Procedures

Randomly test each sample group of identical equipment. Sample size must be at least three units. If 10 percent of the units in the first sample fail the functional performance tests, test a second sample group, the same size as the first sample group. The second sample must not include any units from the first sample group.

If 10 percent of the units in the second sample fail, test all remaining units. If at any point frequent failures occur, and testing becomes more troubleshooting than verification, the CxC may stop the testing and require the contractor to perform and document a checkout of the remaining units prior to continuing functional testing.

3.6.5 Aborted Tests and Re-Testing

Abort any test if any deficiency prevents successful completion of the test or if any required commissioning team member is not present for the test. Re-test after all deficiencies identified during the original test have been corrected. Contracting Officer may withhold payment equivalent to lost time, re-testing, and aborted tests. These costs may include salary, travel costs, and per diem for Government team members.

3.7 TRAINING PLAN

CxC must review the training plan for training associated with the equipment and systems to be commissioned, checking that each plan has the trainer name, trainer contract information, training schedule and location. Submit review at least 30 days prior to the first training event. Incorporate CxC review comments prior to submitting training plan in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA.

Update and resubmit the training plan based on any corrective action taken.

Document training attendance using training attendance rosters and submit completed attendance rosters no later than 7 calendar days following the

SECTION 01 91 00.15 20 Page 11 completion of training for each system to be commissioned.

3.8 COMMISSIONING REPORT

Submit an Initial Commissioning Report no later than 14 calendar days following commissioning team validates all Functional Performance Tests and Integrated Systems Tests, with the exception of Seasonal Tests.

Submit a Final Commissioning Report upon completion of training and trend log reviews. Include the following information in the Final Commissioning Report:

a. An executive summary describing the overall commissioning process, the results of the commissioning process, outstanding deficiencies and recommended resolutions, and seasonal testing that must be scheduled for a later date. Indicate, in the executive summary, whether the systems meet the requirements of the contract documents.

b. A list of deficiencies discovered during the commissioning process and the corrective actions taken in the report.

c. Completed Building Envelope Inspection Checklists, Pre-Functional Checklists, Functional Performance Test Checklists, Integrated Systems Test Checklists, the Final Construction Phase Commissioning Plan, the Issues Log, Training Attendance Rosters, the Design Review Reports, Submittal Review Report, and the approved TAB Report.

3.9 WARRANTY PHASE SITE VISIT

The Lead Commissioning Specialist must visit the building site concurrent with the 9 month warranty inspection to inspect building system equipment and review building operation with the building operating/maintenance staff, and identify any deficiency of the building systems to operate in accordance with the contract documents. The Commissioning Specialist must notify the Contracting Officer of any identified deficiencies and the proposed corrective action. Submit Updated Final Commissioning Report and Systems Manuals, documenting the results of the warranty phase inspection. Include other warranty phase activities, such as Seasonal testing results.

-- End of Section --

SECTION 01 91 00.15 20 Page 12

SECTION 09 90 00

PAINTS AND COATINGS

02/21

PART 1 GENERAL

1.1 RELATED REQUIREMENTS

1.1.1 Painting Included

Where a space or surface is indicated to be painted, include the following unless indicated otherwise.

a. Surfaces behind portable objects and surface mounted articles readily detachable by removal of fasteners, such as screws and bolts.

b. New factory finished surfaces that require identification or color coding and factory finished surfaces that are damaged during performance of the work.

c. Existing coated surfaces that are damaged during performance of the work.

1.1.1.1 Interior Painting

Includes new surfaces and existing coated surfaces of the building and appurtenances as indicated and existing coated surfaces made bare by cleaning operations. Where a space or surface is indicated to be painted, include the following items, unless indicated otherwise.

a. Exposed columns, girders, beams, joists, and metal deck; and

b. Other contiguous surfaces.

1.1.2 Painting Excluded

Do not paint the following unless indicated otherwise.

a. Surfaces concealed and made inaccessible by panelboards, fixed ductwork, machinery, and equipment fixed in place.

b. Surfaces in concealed spaces. Concealed spaces are defined as enclosed spaces above suspended ceilings, furred spaces, attic spaces, crawl spaces, elevator shafts and chases.

c. Steel to be embedded in concrete.

d. Copper, stainless steel, aluminum, anodized aluminum, brass, and lead except existing coated surfaces.

e. Hardware, fittings, and other factory finished items.

1.1.3 Mechanical and Electrical Painting

Includes field coating of interior new surfaces.

a. Where a space or surface is indicated to be painted, include the

SECTION 09 90 00 Page 1 following items unless indicated otherwise.

(1) Exposed piping, conduit, and ductwork;

(2) Supports, hangers, air grilles, and registers;

(3) Miscellaneous metalwork and insulation coverings.

b. Do not paint the following, unless indicated otherwise:

(1) New zinc-coated, aluminum, and copper surfaces under insulation

(2) New aluminum jacket on piping

(3) New interior ferrous piping under insulation.

1.1.3.1 Fire Extinguishing Sprinkler Systems

Clean, pretreat, prime, and paint new fire extinguishing sprinkler systems including valves, piping, conduit, hangers, supports, miscellaneous metalwork, and accessories. Apply coatings to clean, dry surfaces, using clean brushes.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENISTS (ACGIH)

ACGIH 0100 (2017; Suppl 2020) Documentation of the Threshold Limit Values and Biological Exposure Indices

ASTM INTERNATIONAL (ASTM)

ASTM D523 (2014; R 2018) Standard Test Method for Specular Gloss

ASTM D4214 (2007; R 2015) Standard Test Method for Evaluating the Degree of Chalking of Exterior Paint Films

ASTM D4263 (1983; R 2018) Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet Method

ASTM D4444 (2013; R 2018) Standard Test Method for Laboratory Standardization and Calibration of Hand-Held Moisture Meters

ASTM D6386 (2016a) Standard Practice for Preparation of Zinc (Hot-Dip Galvanized) Coated Iron and Steel Product and Hardware Surfaces for Painting

ASTM F1869 (2016a) Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete

SECTION 09 90 00 Page 2

Subfloor Using Anhydrous Calcium Chloride

CENTERS FOR DISEASE CONTROL AND PREVENTION (CDC)

Intelligence Bulletin 65 (2013) Occupational Exposure to Carbon Nanotubes and Nanofibers

MASTER PAINTERS INSTITUTE (MPI)

MPI 4 (2016) Interior/Exterior Latex Block Filler

MPI 9 (2016) Alkyd, Exterior Gloss (MPI Gloss Level 6)

MPI 47 (2016) Alkyd, Interior, Semi-Gloss (MPI Gloss Level 5)

MPI 56 (2012) Varnish, Interior, Polyurethane, Oil Modified, Gloss