26R9047 Amend 0001.pdf
PDF 244 KB Posted
- Solicitation number
- N40085-26-R-9047
About this file
This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) for solicitation N40085-26-R-9047, issued by NAVPAC Mid-Atlantic on July 7, 2026. The contract pertains to Buildings HP51, HP55, and HP57 Paint and Flooring Repairs at Camp Lejeune, North Carolina. Amendment 0001 provides answers to contractor questions and uploads floor plan attachments.
The primary modification addresses a contractor request for additional time to complete the four-building project. The original contract allowed 540 days for completion; however, recognizing scheduling constraints and the requirement that buildings remain occupied during work, the government has extended the requirement completion date to 750 days. The time and date for receipt of proposals remains unchanged. Contractors must acknowledge receipt of this amendment in their proposal submissions, as failure to do so may constitute grounds for proposal rejection. All other terms and conditions of the referenced contract remain in full force and effect. Floor plan attachments have been provided to support project execution.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
N40085-25-R-9047 Amendment 0001
CONTINUATION SHEET
1. QUESTION: We are only given 540 days to complete this project of 4 buildings. We are requesting the government consider giving additional time to this contract, especially with the scheduling requirements and the buildings remaining occupied. We are requesting a minimum of 750 days be allowed to complete all of these buildings?
ANSWER: Requirement completion date will be extended for 750 days.
2. Floor plan attachments have been uploaded.
3. All other terms and conditions remain unchanged.
| Sample Amendment SF30 |
| Untitled |
| Untitled |
Sample SF30 Continuation Sheet
| IDCode: |
| Page: 1 |
| Pages: 2 |
| AmendNo: AMENDMENT NO. 0001 |
| EffDate: 7/7/26 |
| ReqNo: |
| ProjNo: 21-0423 |
| IssCode: N40085 |
| IssuedBy: NAVFAC Mid-Atlantic |
Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521
| AdmCode: |
| AdminBy: See Item 6 |
| ContName: |
| ContStrt: |
| ContCnty: |
| ContSt: |
| ContZIP: |
| Code: |
| FacCode: |
| SolChgYs: Yes |
| SolChgNo: Off |
| SolAmdNo: N40085-26-R-9047 |
| AmendDate: 6/29/26 |
| ModNo: |
| ModDate: |
| NoCopies: 1 |
| Amended: Yes |
| OffrExt: Off |
| OffrNoEx: No |
| ApprData: |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: 21-0423, Buildings HP51, HP55, HP57 Paint and Flooring Repairs |
Amendment 0001, Answer Requests for information, add floor plans attachments
The time and date for receipt of proposals remains unchanged.
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
See Continuation Page(s)
| SignName: |
| SignTitl: |
| ContDate: |
| CoName: |
| CoTitle: |
| CODate: |
File details come from the government source that posted it. Updated .