ELIN - Recurring Base Year
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT N4008526Q0003 |
| EXHIBIT A |
| Line Item 0001 Recurring Work - Base Year |
| PROVIDE PRICES FOR BASE SUPPORT EQUIPMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C |
| ELINs A001 |
| ELIN/Sub ELIN | Description | Quanity | Unit of Issue | Unit Price | Total Price |
| A001 | | | | | |
| A001AA | 1000 KW, 450V, 3 phase, ungrounded trailer mounted generator Tier 4, Diesel (5 ea) | 12 | MO | | |
| TOTAL RECURRING WORK BASE YEAR | | | | |
ELIN - Non-Recurring Base Year
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT #N4008526Q0003 |
| EXHIBIT A |
| Line Item 0002 Non-Recurring Work - Base Year | | | | | | |
| PROVIDE PRICES FOR BSVE - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C | | | | | | |
| ELINs A700 through A709 | | | | | | |
| ELIN | Product Name | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| A700 | 500 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| A701 | 500 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| A702 | 500 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
| A703 | 1000 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| A704 | 1000 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| A705 | 1000 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
TOTAL NON-RECURRING WORK BASE YEAR
ELIN - Recurring - OPT YR 1
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT N4008526Q0003 |
| EXHIBIT A |
| Line Item 0001 Recurring Work - Base Year |
| PROVIDE PRICES FOR BASE SUPPORT EQUIPMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C |
| ELINs B001 |
| ELIN/Sub ELIN | Description | Quanity | Unit of Issue | Unit Price | Total Price |
| B001 | | | | | |
| B001AA | 1000 KW, 450V, 3 phase, ungrounded trailer mounted generator Tier 4, Diesel (5 ea) | 12 | MO | | |
| TOTAL RECURRING WORK BASE YEAR | | | | |
ELIN - Non-Recurring OPT YR 1
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT #N4008526Q0003 |
| EXHIBIT A |
| Line Item 0002 Non-Recurring Work - Base Year | | | | | | |
| PROVIDE PRICES FOR BSVE - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C | | | | | | |
| ELINs B700 through B709 | | | | | | |
| ELIN | Product Name | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| B700 | 500 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| B701 | 500 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| B702 | 500 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
| B703 | 1000 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| B704 | 1000 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| B705 | 1000 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
TOTAL NON-RECURRING WORK BASE YEAR
ELIN - Recurring - OPT YR 2
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT N4008526Q0003 |
| EXHIBIT A |
| Line Item 0001 Recurring Work - Base Year |
| PROVIDE PRICES FOR BASE SUPPORT EQUIPMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C |
| ELINs C001 |
| ELIN/Sub ELIN | Description | Quanity | Unit of Issue | Unit Price | Total Price |
| C001 | | | | | |
| C001AA | 1000 KW, 450V, 3 phase, ungrounded trailer mounted generator Tier 4, Diesel (5 ea) | 12 | MO | | |
| TOTAL RECURRING WORK BASE YEAR | | | | |
ELIN - Non-Recurring OPT YR 2
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT #N4008526Q0003 |
| EXHIBIT A |
| Line Item 0002 Non-Recurring Work - Base Year | | | | | | |
| PROVIDE PRICES FOR BSVE - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C | | | | | | |
| ELINs C700 through C709 | | | | | | |
| ELIN | Product Name | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| C700 | 500 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| C701 | 500 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| C702 | 500 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
| C703 | 1000 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| C704 | 1000 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| C705 | 1000 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
TOTAL NON-RECURRING WORK BASE YEAR
ELIN - Recurring - OPT YR 3
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT N4008526Q0003 |
| EXHIBIT A |
| Line Item 0001 Recurring Work - Base Year |
| PROVIDE PRICES FOR BASE SUPPORT EQUIPMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C |
| ELINs D001 |
| ELIN/Sub ELIN | Description | Quanity | Unit of Issue | Unit Price | Total Price |
| D001 | | | | | |
| D001AA | 1000 KW, 450V, 3 phase, ungrounded trailer mounted generator Tier 4, Diesel (5 ea) | 12 | MO | | |
| TOTAL RECURRING WORK BASE YEAR | | | | |
ELIN - Non-Recurring OPT YR 3
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT #N4008526Q0003 |
| EXHIBIT A |
| Line Item 0002 Non-Recurring Work - Base Year | | | | | | |
| PROVIDE PRICES FOR BSVE - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C | | | | | | |
| ELINs D700 through D709 | | | | | | |
| ELIN | Product Name | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| D700 | 500 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| D701 | 500 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| D702 | 500 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
| D703 | 1000 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| D704 | 1000 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| D705 | 1000 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
TOTAL NON-RECURRING WORK BASE YEAR
ELIN - Recurring - OPT YR 4
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT N4008526Q0003 |
| EXHIBIT A |
| Line Item 0001 Recurring Work - Base Year |
| PROVIDE PRICES FOR BASE SUPPORT EQUIPMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C |
| ELINs E001 |
| ELIN/Sub ELIN | Description | Quanity | Unit of Issue | Unit Price | Total Price |
| E001 | | | | | |
| E001AA | 1000 KW, 450V, 3 phase, ungrounded trailer mounted generator Tier 4, Diesel (5 ea) | 12 | MO | | |
| TOTAL RECURRING WORK BASE YEAR | | | | |
ELIN - Non-Recurring OPT YR 4
| ATTACHMENT II |
| EXHIBIT LINE ITEM NUMBERS |
| SOLICITATION/CONTRACT #N4008526Q0003 |
| EXHIBIT A |
| Line Item 0002 Non-Recurring Work - Base Year | | | | | | |
| PROVIDE PRICES FOR BSVE - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C | | | | | | |
| ELINs E700 through E709 | | | | | | |
| ELIN | Product Name | Description Extended | Estimated Quantity | Unit of Issue | Unit Price | Extended Price |
| E700 | 500 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| E701 | 500 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| E702 | 500 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
| E703 | 1000 KW Generator | WEEKLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 2 | EA |
| E704 | 1000 KW Generator | MONTHLY RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 1 | EA |
| E705 | 1000 KW Generator | YEAR (12 month) RENTAL The contractor is responsible for the supply, delivery, and pick-up for each piece of equipment. The rental equipment will be delivered to the Government's requestor no later than 48 hours after contractor receives order. | 0 | EA |
TOTAL NON-RECURRING WORK BASE YEAR