SF30 24-0408.pdf
PDF 254 KB Posted
- Attached to
- Multiple Building Flooring Repairs
- Solicitation number
- N4008525R9019
About this file
This document is an Amendment of Solicitation (Standard Form 30) for a multiple building flooring repairs project at Camp Lejeune, North Carolina. The solicitation number is N40085-24-R-9019, issued by NAVFAC Mid-Atlantic Resident Officer in Charge of Construction, with a project number 24-0408. The amendment (Amendment 0003) addresses two key clarifications for potential contractors: 1) contractors are responsible for moving all furnishings during floor replacement, and 2) for AS4109 Room 242, wood base should be replaced with vinyl cove base only if it will fully cover the wall, otherwise the same dimension and color wood base should be reinstalled. The time and date for receipt of proposals remains 1400 on 08 September 2025, and the amendment applies to flooring repairs for buildings AS4019, G920, and 9710.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1
1. CONTRACT ID CODE
I
PAG
OF PAGES
I 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DA TE 4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicble)
AMENDMENT NO. 0003 08/20/25 24-0408
6. ISSUED BY CODE N40085 7. ADMINISTERED BY (If other than Item 6) CODE I
NAVFAC Mid-Atlantic See Item 6 Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICIATION NO.
" N40085-25-R-9019
9B. DATED (SEE ITEM 11)
08/07/25
10A. MODIFICATION OF CONTRACT/ORDER NO.
1 OB. DA TED (SEE ITEM 11 )
CODE I FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[!] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers D is extended, [!] is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning 1 copies of the amendment; (bl By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor D is not, D is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
24-0408 MULTIPLE BUILDING FLOORING REPAIRS AS4019, G920 & 9710
Amendment 0003, Revised Answer Request for Information.
The time and date for receipt of proposals remains 1400, 08 September 2025.
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 1 OA, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
NSN 7540-01-152-8070
Previous edition unusable
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of Contracting Officer)
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
N40085-24-R-9019 Amendment 0003
CONTINUATION SHEET
Revised
1. Question
Will the Government move and reinstall furnishings in the rooms where floors are to be replaced?
Answer: Contractors are responsible for moving all furnishings.
2. Question
AS4109 Room 242 has wood base, are we to remove the wood and install vinyl cove base?
Answer: If vinyl cove base will cover the wall where wood base is removed yes replace with vinyl. If not replace it with same dimension and color wood base.