This document appears to be a Statement of Work (SOW) for a carpet replacement project at Camp Lejeune, North Carolina. The scope involves removing and replacing carpet in specified areas of Buildings AS 4109, G920, and G710 on the Air Station, including associated baseboard replacement.

The project requires the contractor to conduct work with minimal disruption to the facility's ongoing operations, with the responsibility of moving furniture and room objects. The contractor may consolidate leadership roles, allowing one qualified person to serve simultaneously as Superintendent, Quality Control Manager, and Safety & Health Officer, as defined in the project specifications. The work must be performed with careful consideration of the facility's continuous operational needs.

View the file

Other files

File Type Posted
SF30 24-0408.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Resilient Flooring SPEC.pdf PDF
24M018CN Multiple Building Flooring Repairs SOW.pdf PDF
RFP 240408.pdf PDF
Combined DIV 01 SPECS.pdf PDF
Building AS4109 ACM Report.pdf PDF
09 65 00 LVT Spec.pdf PDF
Building G920 ACM Repaort.pdf PDF
Building G710 ACM Repaort.pdf PDF
Revised Contractor_Environmental_Guide.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT DESCRIPTION

This scope of work is to be accomplished at Buildings AS 4109, G920 and G710 on the Air Station at Camp Lejeune, North Carolina. The contractor shall remove carpet in specified areas and replace along with any baseboard for those said areas.

SPECIAL SCHEDULING

The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity. The furniture and other objects in the room are to be moved by the contractor.

SUPERVISION

One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.