This document is a section of a solicitation for FY22 Site Fire Suppression Improvements at NSA Mechanicsburg, PA, prepared by Fisher Engineering on 11/14/23. The document details specific requirements for project superintendent qualifications and responsibilities, including a minimum of 10 years construction experience with at least 5 years as a superintendent on similar complex projects. Key requirements include fluent English communication skills, mandatory on-site presence throughout the project, attendance at meetings like Red Zone and partnering sessions, and adherence to safety compliance standards. The Contracting Officer retains the right to remove the superintendent for non-compliance and can issue stop-work orders if project management is unsatisfactory. A preconstruction meeting must be coordinated within 35 calendar days after contract award to discuss administrative requirements and develop mutual understanding of contract expectations.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY22 SITE FIRE SUPPRESSION IMPROVEMENTS (FINAL SUBMISSION) 1654727
NSA MECHANICSBURG, PA FISHER ENGINEERING (11/14/23)
during the entire period of performance under this contract. Provide other insurance coverage as required by State of Pennsylvania law.
1.6 SUPERVISION
1.6.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
The Superintendent may not serve as the Quality Control (QC) Manager or the Site Safety and Health Officer (SSHO).
1.6.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.6.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION MEETING
Immediately after award and prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including
SECTION 01 30 00 Page 2