AMENDMENT 0001.pdf
PDF 418 KB Posted
- Solicitation number
- N4008525R2684
About this file
This document is a federal contract amendment (Standard Form 30) for a Multiple Award Construction Contract (MACC) Indefinite Delivery/Indefinite Quantity (IDIQ) solicitation for general construction services in the Pennsylvania area. The amendment (Number 0001) extends the proposal due date from September 5, 2025, to September 12, 2025, by 1400 EDT, and modifies the contract's financial parameters, increasing the Government Obligation to Order Maximum from $249,000,000 to $498,000,000 and the Allowed Per Order Maximum from $5,000,000 to $249,000,000.
The solicitation is a competitive 8(a) procurement for design-build and design-bid-build construction projects, with an anticipated project cost range between $500,000 and $5,000,000. The amendment includes responses to pre-proposal inquiries, clarifications on past performance requirements, design experience submission guidelines, and wage determination information for Cumberland County, Pennsylvania. The contract will be administered by NAVFACSYSCOM (Naval Facilities Systems Command) Mid-Atlantic, with a 480-calendar-day period of performance, including 15 days for bonds and insurance.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
Created On:
22 Aug 2025, 15:05 PM Greenwich Mean Time
J 1 2
0001 22 Aug 2025 See Continuation Sheet 1850246 N40085
NAVFACSYSCOM MID-ATLANTIC
9324 VIRGINIA AVENUE, NORFOLK VA 23511-0395
NORFOLK, VA 23511-0395
UNITED STATES
BRITTANY CRISTELLI, Email: brittany.n.cristelli.civ@us.navy.mil Telephone:
757-341-1978
SCD: PAS:
N4008525R2684
22 Jul 2025
See Section G - Contract Administration Data
See Schedule
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Block 14 (Description of Amendment/Modification): SOLICITATION NO. N4008525R2684 DESIGN-BUILD / DESIGN-BID-BUILD, INDEFINITE DELIVERY/INDEFINITE QUANTITY MULTIPLE AWARD CONSTRUCTION CONTRACT FOR GENERAL CONSTRUCTION
SERVICES IN THE PUBLIC WORKS DEPARTMENT PENNSYLVANIA AREA OF RESPONSIBILITY
The proposal due date has been extended to 12 September 2025 NLT 1400 EDT.
See Continuation Page(s).
Section 00 00 00 - Procurement and Contracting Requirements
The following changes have been made:
INFORMATION FROM TO
Response Due Date 05 Sep 2025 12 Sep 2025
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
The following changes to Limits have been made:
INFORMATION FROM TO CHANGED BY
Government Obligation to Order Maximum USD 249,000,000.00 USD +249,000,000.00 Allowed Per Order Maximum USD 5,000,000.00 USD 249,000,000.00 USD +244,000,000.00 Contractor Obligation to Deliver Minimum USD 5,000.00 USD +5,000.00
N4008525R26840001
The purpose of this amendment is to provide the following:
1. Extend the proposal due date from 05 September to 12 September 2025 NLT 1400 EDT.
2. Site Visit Sign-In Log
3. Responses to Pre Proposal Inquiries (PPI’s)
4. Revised Section 01 11 00 Summary of Work (Attachment provided)
PRE-PROPOSAL INQUIRY RESPONSES:
Question # Reference
Question Government Response Page Section Paragraph
1 15 Factor 4 1
Are Offeror's allowed to use previously completed PPQs in lieu of obtaining new ones?
Per the RFP, “the Offeror should provide completed
PPQs in the proposal.
Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs.
However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.”
2 15 Factor 3
RFP states Offeror shall include all completed CPARS evaluations
(interim and final) for a project.
Some projects have multiple rounds of interim CPARS, please confirm ALL interims should be provided.
Correct.
Are there any font size/type limitations?
No required font size or type.
Arial or Times New Roman size 10 or 12 preferred.
Seed
Project
Please confirm the seed project is pricing only and no technical narrative is required.
Seed project is price only.
5 11 & 12 Factor 1 2, page 12
Please confirm that Designers' projects need only the Design portion of the project to be 100% complete within the past 5 years.
Per the RFP, projects submitted for the DOR shall have been completed within the past five (5) years of the date of issuance of this RFP.
This includes the construction.
For Design-Build project, the design portion of the contract shall have been completed within the past five (5) years of the date of issuance of the
RFP.
6 10 Price Attach E
Attachment E and the Basis of
Evaluation for Price states pricing for only the Seed Project. How will the government evaluate
Design pricing, since the Seed
Project does not require design?
No design pricing is being evaluated.
7 01 35 26 1.7.1.1.1
Spec states that SSHO may perform duties of the Site
Superintendent while Spec 01 30
00, 1.6.1 confirms that the Site
PENDING RESPONSE
Superintendent cannot perform duties of neither SSHO nor QC
Manager. Please clarify.
8 21 13 13
Please confirm that Qualified Fire
Protection Engineer is not required for quality control for this project.
PENDING RESPONSE
9 02 82 00
Please elaborate on the abatement scope of work. There are no
Hazmat Survey or Hazmat
Drawings provided.
PENDING RESPONSE
10 02 82 00
Does the contractor need to provide Hazmat Survey? If yes, please confirm that all fundings of hazmat materials will be treated as a change order.
PENDING RESPONSE
11 03 30 00
Please elaborate on concrete work since no scope noted on the drawings.
PENDING RESPONSE
12 10 & 11 Factor 1, (i) Size
Upon reviewing Solicitation
Section 1.3, General Overview of the Contract, it is noted that the estimated construction cost for projects under the MACC is anticipated to range between
$500,000 and $5,000,000.
(i) However, Evaluation factors for award Factor 1, Corporate experience states Offerors shall submit a minimum of three (3) up to a maximum of five (5) relevant construction projects with a final construction cost of $500,000 or greater. At least one (1) project must have a final construction cost of $5,000,000 or greater.
(ii) Design experience for a project with a final construction cost of
$500,000 or greater. At least one
(1) project must have a final construction cost of $5,000,000 or greater.
Even though the solicitation ranges from $500,000 to $5,000,000, we respectfully seek clarification on the reason behind requiring
Offerors to demonstrate experience with projects exceeding $5M.
Propose per RFP.
If we are bidding as a JV, can the bank reference letter be provided for both JV partners in lieu of the
JV?
Yes
For submission of other work.
provide a list of offer’s other work presently under contract; should we submit current work being performed by the JV if we are bidding as a JV only or work currently performed by the JV and both JV partners individually?
Per the RFP, for Factor 1 for construction experience, submittal requirements, “projects submitted for the
Offeror shall be completed within the past five years of the date of issuance of this
RFP.” For design experience, “projects submitted for the
DOR shall have been completed within the past five
(5) years of the date of issuance of this RFP.
Submitted projects that were not completed within this timeframe will be considered
Not Relevant. For design-build projects, the design portion of the contract shall have been completed within the past five (5) years of the date of issuance of this RFP.
The design completion date shall be clearly stated on the
Construction & Design
Project Data sheet. The project will be considered Not
Relevant if the design completion date is not clearly provided.”
If bidding as a newly formed JV, can the JV partners submit 5 years of DART and TCR rates in lieu of the JV has the JV was formed less than 5 years ago?
Per the RFP, “For a partnership or joint venture, the Offeror shall submit separate DART rates and TCR for the specified five (5) CY for each contractor who is part of the partnership/joint venture; however, only one safety narrative is required.”
Are EMR rates required to be submitted? If yes for how many years? If Yes, can EMR rates be submitted for the JV partners in lieu of the JV as it’s a newly formed JV?
No. Propose per RFP.
Do we have to submit resumes for the personnel to be listed as part of the management plan?
No. Propose per RFP.
Will the government provide CAD drawings to prepare shop drawing?
PENDING RESPONSE
19 E-001 21 13 13
The specifications require compliance with NFPA 20 for fire pump power, but the drawings leave the feeder source and protective device information blank. Please confirm the intended feeder source and protective device requirements for the fire pump and jockey pump.
E-101, E-102, E-103
26 05 00
The drawings show utility service connections for fire pumps, but do not address whether a secondary/emergency source is required. Please confirm if utility power alone is acceptable or if an alternate source is required for this project.
PENDING RESPONSE
HC001
HC003
21 13 13 2.1
Specifications call for ductile iron pipe for underground fire mains, but the drawings do not clearly indicate pipe material. Please confirm the intended pipe material and joint type for underground fire service piping.
PENDING RESPONSE
FX111–
FX132
21 13 13 3.2
Specifications reference Fire
Department Connections, but the drawings do not clearly identify their locations or tie-in details.
Please confirm the required FDC locations and configurations for each building.
PENDING RESPONSE
LS111–
LS131
21 13 13 1.5
The specifications reference NFPA
13 hazard classifications, but the drawings do not indicate the design criteria for each building. Please confirm the required hazard classification and density/area basis of design.
PENDING RESPONSE
24 FX501 21 05 48
The specifications reference seismic requirements generally, but the drawings do not provide design parameters. Please confirm the seismic bracing and restraint requirements to be applied to the sprinkler piping.
PENDING RESPONSE
P-501, P-601 22 05 23
Plumbing drawings note a 140 PSI supply and PRVs, while the specifications provide general piping requirements. Please confirm whether PRVs are required on the fire suppression systems, and if so, identify the intended pressure setpoints.
PENDING RESPONSE
FA111–
FA131,
FA501
28 31 00
The specifications describe a complete fire alarm system, while the drawings primarily show new devices without clearly indicating if new fire alarm control panels are included. Please confirm whether the scope requires new FACUs or modifications to the existing systems.
PENDING RESPONSE
FA111–
FA131
28 31 00 2.2
The specifications reference NFPA
72, but the drawings do not indicate circuit class, survivability, or notification criteria. Please confirm the required circuit configuration and notification device coverage parameters.
The SF-1442 states “begin within
15 days and complete within 365 days,” while Section 1.3 of the RFP
Supplementary Instructions establishes a 480-calendar-day period of performance (including
15 days for bonds/insurance).
Please confirm the intended contract duration and controlling period of performance.
480 calendar days period of performance (including 15 days for bonds/insurance) is the correct duration for the seed project.
The total building commissioning specification (01 91 00.15 20 – 1.4) lists the systems to be commissioned as “pressure reducing valves and associated piping and accessories”.
Drawing P-601 lists the pressure reducing valves and general note E identifies the maximum water system supply pressure.
Should the pressure reducing valves be functionally tested with and without the fire suppression pumps in operation?
What associated piping and accessories shall receive commissioning oversight?
Which pressure reducing valves have system flow meters, sensors, actuators or are connected to a control system as referenced in the functional performance test section
01 91 00.15 20 – 3.4.2?
Please detail which systems are interconnected with the pressure reducing valves as referenced in the integrated systems test sections
01 91 00.15 20 – 3.4.3 and 01 91
00.15 20 – 3.6.3.
PENDING RESPONSE
30 Please share the Sign In Sheet.
Sign-In Sheet provided with
Amendment 0001.
Please confirm if a single, duly qualified individual may "triple hat" and serve as the project superintendent, QC Manager, and
SSHO.
PENDING RESPONSE
For proposal submission Is PIEE submission is mandatory or email submission is also accepted? Please advise.
Per the RFP, "Only the PIEE solicitation module is authorized for the submission of electronic proposals in response to this solicitation."
"Emailed submissions will not be accepted."
33 11 00 21 16 4
Factor 1, Corporate Experience, Construction Experience: As per the solicitation’s technical proposal requirement, offerors are required to submit at least one past performance project with a value greater than $5 million. However, This is a competitive 8(a) procurement. Propose per
RFP.
according to SBA 8(a) regulations
(13 CFR §124.506), a sole-source award for an 8(a) construction contract is generally limited to $4.5 million.
Given that this procurement is set aside under the competitive 8(a) program, we respectfully request that the Government consider adjusting the past performance threshold to $4.5 million or greater.
This adjustment would ensure broader participation from qualified 8(a) firms while still maintaining the Government’s intent to evaluate relevant, large-scale project experience.
"Please confirm whether the
Contractor may use available
CPARs for this MACC IDIQ solicitation. Additionally, please confirm whether previously prepared PPQs submitted under other solicitations may be reused, or if new PPQs must be obtained specifically for this solicitation.
Please also note that in some cases, PPQ forms issued by other
Government Agencies may differ in format, appearance, and questions. Kindly confirm whether such PPQs, although not identical to this solicitation’s form, would still be acceptable for submission under this MACC IDIQ."
See response to PPI #1.
Are we going to be able to perform the water shutdowns during the day, or will this be off shift?
PENDING RESPONSE
What's the procedure in the event that the main valves do not hold?
PENDING RESPONSE
37 13 00 21 16 Factor 3
For Joint Venture Offerors, shall the DART and TCR rate be provided for both member entities individually?
See response to PPI#15.
Please provide the sign-in sheet from the site visit.
Sign-in sheet provided with
Amendment 0001.
WAGE DETERMINATION
"General Decision Number: PA20250085 08/08/2025
Superseded General Decision Number: PA20240085
State: Pennsylvania
Construction Type: Building
County: Cumberland County in Pennsylvania.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |. Executive Order 14026 |
|into on or after January 30, | generally applies to the |
|2022, or the contract is | contract. |
|renewed or extended (e.g., an |. The contractor must pay |
|option is exercised) on or | all covered workers at |
|after January 30, 2022: | least $17.75 per hour (or |
| | the applicable wage rate |
| | listed on this wage |
| | determination, if it is |
| | higher) for all hours |
| | spent performing on the |
| | contract in 2025. |
|If the contract was awarded on|. Executive Order 13658 |
|or between January 1, 2015 and| generally applies to the |
|January 29, 2022, and the | contract. |
|contract is not renewed or |. The contractor must pay all|
|extended on or after January | covered workers at least |
|30, 2022: | $13.30 per hour (or the |
| | applicable wage rate listed|
| | on this wage determination,|
| | if it is higher) for all |
| | hours spent performing on |
| | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the
Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/03/2025
1 01/24/2025
2 02/21/2025
3 03/14/2025
4 03/21/2025
5 06/27/2025
6 07/18/2025
7 08/01/2025
8 08/08/2025
ASBE0023-008 07/01/2024
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR - MECHANICAL (Duct, Pipe & Mechanical System
Insulation)......................$ 40.00 29.81
BOIL0013-008 01/01/2025
BOILERMAKER......................$ 55.00 35.48
BRPA0005-062 05/03/2020
BRICKLAYER (Including
Pointing, Caulking, and
Cleaning)........................$ 33.99 16.87
CARP0287-016 06/01/2024
CARPENTER (Drywall Hanging, Metal Stud Installation, Form
Work and Scaffold Building
Only)............................$ 34.34 19.69
CARP0443-003 06/01/2024
MILLWRIGHT.......................$ 43.00 23.44
ELEC0143-010 06/01/2025
ELECTRICIAN (Includes Alarm
Installation, Installation of
Sound and Communication
Systems, HVAC/Temperature
Controls Installation, and
Low Voltage Wiring)..............$ 40.00 27.42
ELEV0059-004 01/01/2025
ELEVATOR MECHANIC................$ 58.70 38.435+a+b
FOOTNOTES:
A. Employer contributes 8% of basic hourly rate for 5 years or more of service as vacation pay credit, and 6% of basic hourly rate for less than 5 years of service.
B. Eight Paid Holidays (provided employee has worked 5 consecutive days before and the working day after the holiday): New Years's Day; Memorial Day; Independence Day;
Labor Day; Veterans' Day; Thanksgiving Day and the Friday after Thanksgiving Day, and Christmas Day.
ENGI0066-044 07/01/2024
POWER EQUIPMENT OPERATOR
Mechanic....................$ 36.87 21.32
Pump........................$ 32.25 21.32
ENGI0542-032 05/01/2025
POWER EQUIPMENT OPERATOR
Crane.......................$ 47.14 31.58
Hoist (Single Drum), Forklift (under 20 ft., excludes masonry work)......$ 41.88 30.03
Hoist (With Two Towers), Forklift (20 ft and over, excludes masonry work)......$ 44.61 30.83
Oiler.......................$ 39.42 29.30
IRON0404-014 07/01/2024
IRONWORKER, ORNAMENTAL...........$ 37.26 32.63
LABO1180-015 05/01/2017
LABORER
Concrete Worker.............$ 22.86 13.33
Forklift (Masonry Work
Only).......................$ 25.81 13.33
Mason Tender-Brick..........$ 24.31 13.33
PAIN0411-005 05/01/2021
PAINTER: Brush and Roller Only...$ 25.84 16.30
PLUM0520-013 05/01/2023
PIPEFITTER (Includes HVAC
Pipe Installation)...............$ 41.36 29.45
PLUM0520-015 05/01/2023
PLUMBER (Excludes HVAC Unit
Installation)....................$ 41.36 29.45
* SFPA0669-004 04/01/2025
SPRINKLER FITTER (Fire
Sprinklers)......................$ 49.75 28.96
SHEE0019-017 06/01/2025
SHEET METAL WORKER (HVAC Duct
Installation Only)...............$ 45.02 44.09
FOOTNOTE: Paid Holiday: Election Day
* UAVG-PA-0016 01/01/2025
OPERATOR: Bulldozer.............$ 37.85 22.72
SUPA2011-043 08/20/2014
CARPENTER, Excludes Drywall
Hanging and Metal Stud
Installation, Form Work, and
Scaffold Building................$ 25.71 10.62
CEMENT MASON/CONCRETE FINISHER...$ 24.10 15.60
FLOOR LAYER: Carpet Only.........$ 25.71 12.02
GLAZIER..........................$ 25.05 8.58
IRONWORKER, REINFORCING..........$ 27.42 22.45
IRONWORKER, STRUCTURAL...........$ 25.96 21.20
LABORER: Common/General, Including Landscaping............$ 20.16 8.91
LABORER: Mason Tender -
Cement/Concrete..................$ 21.99 8.28
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 36.16 16.15
OPERATOR: Bobcat/Skid
Steer/Skid Loader................$ 26.41 16.58
OPERATOR: Drill.................$ 27.43 16.94
OPERATOR: Gradall...............$ 32.70 18.43
OPERATOR: Grader/Blade..........$ 32.51 17.98
OPERATOR: Hydro Mulch...........$ 26.41 16.58
OPERATOR: Loader................$ 27.05 14.52
OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 30.39 15.05
PAINTER: Spray Only..............$ 27.89 13.53
PLUMBER (HVAC Unit
Installation Only)...............$ 26.67 15.99
ROOFER, Excludes Waterproofing...$ 31.00 22.10
ROOFER: Waterproofing Only.......$ 28.60 18.02
SHEET METAL WORKER, Excludes
HVAC Duct Installation...........$ 28.98 27.03
TILE FINISHER....................$ 20.70 8.51
TILE SETTER......................$ 24.30 11.79
TRUCK DRIVER: Dump Truck........$ 20.86 4.84
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than
""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007
6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007
01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator
U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
Washington, DC 20210.
END OF GENERAL DECISION"
ATTACHMENTS:
1. Amendment 0001 – Site Visit Sign-In Sheet
2. Amendment 0001 – 01 11 00 Para 1.2.1 NSA Fire Protection WON 1654727
(End of Summary of Changes)
| AMENDMENT 0001 EPS |
| Amendment 0001 Text |
File details come from the government source that posted it. Updated .