N4008525R0070 DESIGN-BUILD (DB), REPAIR CVN BULKHEAD Q8, Naval Station Norfolk, Norfolk, Virginia
Solicitation number
N4008525R0070
Issued by

About this file

This is an Amendment of Solicitation for a Design-Build (DB) Repair project at Naval Station Norfolk, Virginia, specifically for repairing the CVN Bulkhead Q8. Amendment 0005 extends the proposal due date from 11 September 2025 to 17 September 2025 at 2:00pm ET and provides responses to multiple Pre-Proposal Inquiries (PPIs). The project involves complex marine construction work including phased demolition, installation of a new sheet pile bulkhead, soil anchors, fender systems, mooring hardware, and associated site and utility work.

Key changes include clarifying that this is a Design-Build project where the contractor will determine means and methods, addressing questions about material salvage, pile extraction, weep holes, drainage systems, and various technical specifications. The government emphasizes that concept drawings are for information purposes only, and the contractor's price must include design and construction based on current Unified Facilities Criteria (UFC) and the Request for Proposal (RFP) document. The project is divided into multiple phases across different station locations, with Base Bid covering the area between Piers 12 and 14, and additional bid options for areas south and north of these piers.

View the file

Other files

File Type Posted
25R0070 Amendment 0009.pdf PDF
25R0070 Amendment 0007.pdf PDF
25R0070 Amendment 0006.pdf PDF
25R0070 Amendment 0004.pdf PDF
25R0070 Bulkhead Q8 Site Visit Log.pdf PDF
25R0070 Amendment 0003.pdf PDF
25R0070 Amendment 0002.pdf PDF
PROD_Form.docx DOCX document
NAVFAC LID Data Card v3.0.pdf PDF
NAVFAC LID Waiver Form v4.docx DOCX document
HR-SOP.pdf PDF
Utility Connection Permit Application.pdf PDF
25R0070 Amendment 0001.pdf PDF
1513553-SPC-5of5.pdf PDF
1513553-SPC-3of5.pdf PDF
1513553-SPC-1of5.pdf PDF
1513553-SPC-2of5.pdf PDF
1513553-SPC-4of5.pdf PDF
25R0070 General Requirements.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

PAGE OF PAGES

1 19

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

04-SEPT-2025

4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than item 6) CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

See Item 6

8. NAME AND ADDRESS OF CONT RACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.

N40085-25-R-0070

X 9B. DATED (SEE ITEM 11)

08/12/25

10A. MOD. OF CONT RACT /ORDER NO.

10B. DAT ED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENT S OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer x is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15 and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT

TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNT ING AND APPROPRIAT ION DAT A (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICAT IONS OF CONT RACTS/ORDERS.

IT MODIFIES THE CONT RACT /ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONT RACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED TO REFLECT THE ADMINIST RAT IVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORT ANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

N4008525R0070 Design-Build (DB) Repair CVN Bulkhead Q8 at Naval Station Norfolk, Norfolk, Virginia

Contract POC: Catharine Keeling, catharine.a.keeling.civ@us.navy.mil

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONT RACTING OFFICER (Type or print)

TEL: EMAIL:

15B. CONT RACT OR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNIT ED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

EXCEPTION TO SF 30

STANDARD FORM 30 (Rev. 11/16) APPROVED BY OIRM 11-84 Prescribed by GSA

FAR (48 CFR) 53.243

N40085-25-R-0070

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

AMENDMENT 0005

The purpose of this amendment is to incorporate the following:

1. To Extend Proposal Due Date

2. To Include responses to Pre-Proposal Inquiries (PPIs)

1. Extend Proposal Due Date

The proposal due date is extended from 11 September 2025 to 17 September 2025 at 2:00pm ET.

2. Pre-Proposal Inquiries (PPIs) responses below:

Question No.

Question Government Responses

10 Due to the size, scope, and complexity of the subject project, key marine subcontractors and estimators have requested additional time to assess, design, and price the work. Please consider extending the solicitation’s close date by two weeks.

The proposal due date has been extended from 11 September 2025 to 17 September 2025

11 Due the complexity and size of this project and the time necessary to allow our design team and subcontractors to review, scope, and provide pricing, can the proposal due date be pushed to September 26, 2025?

The proposal due date has been extended from 11 September 2025 to 17 September 2025

16 Drawings show to remove and salvage existing fender piles (concrete and composite). Would NAVFAC providing a bid item for replacing composite and concrete fender piles?

No Piles are to be salvaged. See RFP Part 3, 1.0 Project Description, Note 8. Page 310 of RFP (RFP attached).

19 Drawing has a note for potential void to be filled with flowable fill. Would NAVFAC consider a unit price bid item to limit the unknown quantity of flowable fill that could be required to fill these voids?

This will be controlled by the individual contractor's design and would be applicable to all of the CLINS

20 Wage Determination - Will a wage determination for Marine Construction trades be provided?

Including pile drivers, tug captain, mechanics, deckhands, etc.

These categories are specialized and there is not a wage decision applicable. Please bid per RFP.

21 Wage Determination - Will a wage determination for Divers and Tenders be provided?

These categories are specialized and there is not a wage decision applicable. Please bid per RFP.

32 For basis of bid, please provide a detail or dimensions of the various concrete foundations to be demolished.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

33 For basis of bid, please provide a quantity of flowable fill that is to be used to fill potential voids beneath the relieving platform, or provide a bid item for this activity.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

34 There is a call out in drawing area B1, "Demo abandoned utilities coordinate with contracting officer, see CD502 for photographs." Please clarify whether this refers photograph #4 on CD- 501, and that the telecom conduit and cable is only to be demolished between roughly STA 6+18 (utility pedestal location) to STA 6+02 (extent of excavation).

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

35 Please identify what type of equipment is shown in this photo (CD-502), as well as what is required to remove and reinstall the equipment.

Also please define the stationing in order to determine which phase this work is to be completed.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

36 Please identify what type of equipment is shown in this photo (CD-502) and clarify whether it is to be protected in place or removed and reinstalled.

Also please define the stationing in order to determine which phase this work is to be completed.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

37 Please provide the length of communication cable and conduit that is to be removed and reinstalled as depicted in this photo (CD-502). Also please define the stationing in order to determine which phase this work is to be completed.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

38 Please provide the length of communication cable and conduit that is to be removed and reinstalled as depicted in this photo (CD-502). Also please define the stationing in order to determine which phase this work is to be completed.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

39 Please identify what type of equipment is shown in this photo, and clarify whether it is to be protected in place or removed and reinstalled.

Also please define the stationing in order to determine which phase this work is to be completed.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

40 There is a call out in drawing area D3, "Contractor to provide temporary support to keep the hoist structure in place…" Please provide more detail on the hoist structures for contractor to be able to determine support requirements.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

41 Please provide the type and dimensions of the piping and length of piping to be demolished for basis of bid.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

46 Note 3 states "Attach equipment with epoxy anchors to match existing size and pattern."

Please provide the quantity and anchor bolt dimensions required for each piece of equipment that is to be reinstalled.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

53 Please provide a bid item for Marine Mammal Watch downtime.

This will be controlled by the individual contractor's design and would be applicable to all of the CLINS

54 Please provide a bid item for FAA downtime. This will be controlled by the individual contractor's design and would be applicable to all of the CLINS

58 Note 1 states to cut off top 1' of reinstalled inverted composite fender pile. As pile manufacturer recommends the use of a vibratory hammer for install, this will result in the top 3' - 5' of the pile being damaged. Please revise the cut-off length from 1' to 5'.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

59 We understand the Government’s intent is to maintain the current bid date to support an award by the end of the FYE calendar year. However, given the scale and complexity of the (Design Build) Q-8 Bulkhead Repair — which includes phased demolition, installation of a new sheet pile bulkhead, soil anchors, fender systems, mooring hardware, and associated site and utility work— the current proposal preparation period does not allow sufficient time to develop a complete and competitive bid package. Our concern is that the compressed schedule limits the ability of offerors to fully evaluate the technical requirements, coordinate subcontractor and supplier pricing, and develop accurate cost and risk assessments.

Extending the bid date would help ensure the Government receives comprehensive proposals that reflect the true scope and magnitude of the work. Accordingly, we respectfully request an extension of the bid due date by [3 weeks] to allow adequate time for thorough proposal development. We appreciate your consideration and remain committed to submitting a responsive proposal in line with the Government’s objectives.

The proposal due date has been extended from 11 September 2025 to 17 September 2025

67 In the base bid of the Waterfront MACC award, contract clause 52.225-11 states “*To be completed per Task Order.”.

Please provide the contract clause applicable to this solicitation.

Specifically, for this solicitation, are all steel construction materials required to be produced in the United States? or will steel construction materials be allowed from designated countries listed in the clause under the WTO GPA, FTA, least developed countries, and Caribbean Basin countries?

FAR 52.225-11 is required to this task order. Please follow instructions within the clause.

71 CD-103 notes to transition excavation at approximately STA 23+90; however, CD-301 shows typical excavation up to STA 24+30.

Please confirm that excavation is to transition to a lesser area starting STA 23+90 as to retain and protect the buildings to the north, which in turn means that probing underneath the relieving platform ceases at STA 23+90.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

73 Utility Note 1 states that all storm drain pipes less than 12" diameter shall be ductile iron, but storm drain pipe in drawing area D4 on C-110 calls for 10" dia. RCP. Please confirm that this pipe is meant to be ductile iron.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

74 There is an underground electrical line in this drawing area, only with a note (Note 9) to retain and protect the electrical handhole and adjust to finished grade. Please provide further detail on this electrical line, such as depth and ductbank detail, as well as if the line is to be protected in place or demolished and replaced.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

76 Section 1.5.3 states the Concrete QC specialist's "area of Responsibility" is concrete repairs.

Please confirm that no QC specialist is required as there is no concrete repairs on this project.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

77 Please confirm this spec states for the KTR will pay for all utilities at the governments prevailing rates and is in agreement with the General Requirements.

Yes

79 This states that "For bidding purposes, Contractor shall assume 5 percent of Prestressed Fender Pile and 5 percent the Composite fender piles may be damaged / broken during extraction. The contractors shall account for this occurrence in their bids for the complete extraction of any portions of these damaged piles and any portions which may have broken off the main section of piling." Please confirm that if contractor exceeds 5%, this will be considered a changed condition.

Any abandoned in place piles would need to be outside the area of new work and would need to be broken / cutoff at a minimum at the mudline. So a lot with be determined with the Contractor's design and means and methods for Construction.

80 Please confirm the KTR can utilize ASTM A767 Class II galvanizing or A1094 galvanizing prior to fabrication in lieu of A706 hot dipped galvanizing after fabrication.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

84 Please confirm that the KTR is not required to clean any existing storm drain pipe. This paragraph only applies to newly installed pipe, if required.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

86 This paragraph states that probing IS REQUIRED prior to installation of PC fender piling. Please confirm.

This is from the previous design. This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

88 Demolition Keynote states, "Remove, salvage and store exist conc fender pile for reuse." In regards to all salvaged material of the fender system (concrete piles, composite piles, and timber), please confirm that this material that is not reused will become property of the government. In other words, KTR is not responsible for disposal of unused salvaged fender material.

No Piles are to be salvaged. See RFP Part 3, 1.0 Project Description, Note 8. Page 310 of RFP.

90 Please confirm that probing (as defined in Notes 3/4 on CD301 Section A1 Typical Demolition Section at Storm Drain Pipe - STA 0+00 to STA 24+30) for voids and installation of flowable fill only occur at the storm drain outfalls / catch basin locations.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

91 Outfall #54 & Outfall #55 call for new 16" dia.

ductile iron pipe, but Utility Note 2 on C-002 states all storm drain pipes 12" diameter and greater shall be circular reinforced concrete.

Please confirm these are to be 16" ductile iron.

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

92 Outfalls #45 & #51 call for new 12" dia. ductile iron pipe, but Utility Note 2 on C-002 states all storm drain pipes 12" diameter and greater shall be circular reinforced concrete. Please confirm these are to be 12" ductile iron.

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

93 Due to design-build requirements and coordination, we request a 2 week bid extension.

The proposal due date has been extended from 11 September 2025 to 17 September 2025

94 Section states, "Excavatable flowable fill must be used to fill abandoned pipes and backfill demolished utility vaults as indicated."

No abandoned pipes or utility vaults have been identified on the drawings, please confirm that this is not a requirement.

This is a Design-Build project. Because of this, means and methods for construction are to be determined by the Contractor's design and are at the Contractor's discretion.

95 Please confirm the use of thread locker is only for the fasteners themselves, not filling the counterbored hole in the UHMW (i.e the counterbores are left unfilled).

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

96 This specs states to allow new pavement surfaces to cure for a period of not less than 30 days before application of pavement marking paint.

This greatly affects schedule with regards to quadrant completion for turnover to mobilize to the next quadrant. Please confirm that thermoplastic striping can be utlitized in lieu of pavement marking paint and if allowed, this curing period would not apply.

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

97 During the site visit and many RFI responses, the proposer is directed to find answers in Part 3.

Part 3 has not been provided, which impacts the offeror’s ability to provide a timely quote. Please provide Part 3 ASAP and extend the PPI question due date to allow for additional time to review the Part 3 requirements.

A summary of the project is provided in Part 3, 1.0 Project Description. Pages 309 -311 of RFP. (RFP attached)

98 Are there any Buy America/Buy American requirements on this project?

Yes, FAR 52.225-11 is required for this project.

99 Please provide a description of the breakdown of the CLIN’s.

See Bid Schedule and RFP

100 On drawing S506, are the rubber “D” fender systems to be 8”x8” as labeled in detail A3 (scales to 12”x12”) or 12”x12” as shown in detail B5?

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

101 On drawing S505, are the UHMW pile fenders to be 13’6”L for high piles & 10’6”L for low piles as shown in detail C2 or 14’6”L for high piles & 12’0”L for low piles as scaled out on detail A1?

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

102 1. Is class 2 galvanized rebar (galvanized after fabrication) acceptable in lieu of class 1 galvanized rebar (galvanized prior to fabrication)? – Asked by a vendor

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

103 On drawing S002 detail C1, are all post installed anchors & rebar to be installed to the greater of 12d or 12” minimum? The drawings do not depict 12” minimum embedment for all of the post installed anchor

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

104 On drawing S510, is the life ring stand to receive a galvanized finish? Also, in detail A1 they reference HSS 6x0.375 tubing, but reference 6” standard pipe in detail C1. Please confirm the correct material for the life ring stand.

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

105 Specification section 02 41 00 paragraph 3.1.2 says to assume that 5% of prestressed fender piles and 5% of composite fender piles will be broken during extraction. There are details/specs for the prestressed concrete fender piles, but there are no specifications for new composite fender piles in the drawings or specification section 35 59 13.14

20. Please provide the material specifications/details for new composite fender piles. Will the contractor be required to dispose of any damaged/broken/unused fender piles or will the Government dispose of them?

To be determined by Contractor's design and UFC requirements. No piles are to be salvaged and Contractor will be responsible for disposal.

106 1. Specification Section 35 59 35, Paragraph

2.2.1.1 requires ductile iron cleats per ASTM A536, Grade 65-45-12, class 1. Can you please ask if cast steel cleats per ASTM A27 Grade 65- 35 would be acceptable as long as the cleats meet the rated capacities listed on drawing S- 001? Below is a small list of Navy projects we have completed with cast steel cleats or bollards per ASTM A27 Grade 65-35.1. Port Damage Repair Trainer - Naval Base Ventura - Ventura, CA.

2. V47 Breakwater Pier - Naval Station Norfolk - Norfolk, VA.

3. LC Piers 20-35, Replace Mooring Cleats - Joint Expeditionary Base Little Creek Fort Story - Virginia Beach, VA.

4. P-044 & P-1006 Waterfront Improvements - Joint Base Harbor-Hickman - Honolulu, HI.

5. Wharf Bravo Structural Repairs - Naval Station Guantanamo - Cuba

6. Berth 42, Replace Double Bitt Bollards - Naval Station Norfolk - Norfolk, V

Because this is Design Build, this will be determined by the Contractor's design and UFC requirements.

107 Specification section 01 11 00 paragraph 1.2.1 states “installation of prestressed concrete fender system (existing fender piles installed in groups of three as "low" piles centered on cleat locations)” Specification section 02 41 00 paragraph 3.1.2 states “For bidding purposes, Contractor shall assume 5 percent of Prestressed Fender Pile and 5 percent the Composite fender piles may be damaged / broken during extraction. The contractors shall account for this occurrence in their bids for the complete extraction of any portions of these damaged piles and any portions which may have broken off the main section of piling.” The NAVFAC drawing & review comments dated 3/10/2025 that were included as part of addendum 002 state in items 14, 16, 17, 43, & 61 state that the “RFP requires demo of all existing piles and providing new piles.”. Is the intent to reuse existing concrete piles at new “low” fender pile locations (accounting for 5% as new piles for breakage/damage during extraction), provide new concrete piles for the “high” fender pile locations, and reuse existing polymetric fender piles (accounting for 5” as new piles for breakage/damage during extraction)? Please confirm that there is no warranty for reused piles

Because this is a Design Build, this will be determined by the Contractor's design and UFC requirements.

108 The NAVFAC drawing & review comments dated 3/10/2025 that were included as part of addendum 002 state in items 48 & 50 state that no turbidity curtain is required, but section 31 62

22.21 temporary turbidity curtain has been included in the RFP. Please confirm that no turbidity curtain or turbidity testing is required

Turbidity Curtain is not required.

109 Specification section 03 31 29 paragraph 1.2.f references “mass concrete”, but doesn’t have any other specifications in this section. Please confirm the requirements are for mass concrete that are to be included in the scope of work.

Because this is a Design Build, this will be determined by the Contractor's design and UFC requirements.

110 For items 1G, 1H, 2F, 2G, 3F, & 3G on the pricing schedule, what are the disposal requirements and what classification of disposal facility for these contaminated materials?

Disposal requirements per the TPH level denoted in each line item.

111 Specification section 01 45 00.10 20 paragraph 1.5.3: can the underwater QC specialist be part of a 3rd party diving contractor that is performing the work if inspections are documented with photos & video?

The inspector needs to be different than the group that is performing the repairs.

112 On drawing S505 details A3 & A4, are the L6x6x1/2, PL ½”, and L9x4x5/8 steel sections on the pile connection to be galvanized or stainless steel?

Because this is a Design Build, this will be determined by the Contractor's design and UFC requirements.

113 Does the drainage system require hydrostatic testing? Specification section 33 40 00 paragraph

2.6 hydrostatic test on water tight joints doesn’t have any text underneath of it.

Drainage systems require hydrostatic testing.

114 Specification Section 35 59 35, Paragraph 2.2.1.1 requires ductile iron cleats per ASTM A536, Grade 65-45-12, class 1. Would cast steel cleats per ASTM A27 Grade 65-35 would be acceptable as long as the cleats meet the rated capacities listed on drawing S-001? The Navy routinely allows the use of cast steel cleats or bollards per ASTM A27 Grade 65-35.

Because this is a Design Build, this will be determined by the Contractor's design and UFC requirements.

115 On drawing S505 details A3 & A4, are the L6x6x1/2, PL ½”, and L9x4x5/8 steel sections on the pile connection to be galvanized or stainless steel?

Because this is a Design Build, this will be determined by the Contractor's design and UFC requirements.

116 Does the drainage system require hydrostatic testing? Specification section 33 40 00 paragraph

2.6 hydrostatic test on water tight joints doesn’t have any text underneath of it.

Because this is a Design Build, this will be determined by the Contractor's design and UFC requirements.

117 The NAVFAC drawing & review comments dated 3/10/2025 that were included as part of addendum 002 state in items 23 & 26 state that all ladders are to be demolished & provide new.

Drawing SD501 note 2 says to salvage the ladders for reuse. Please clarify if the existing ladders are to be salvaged/reused or if all new ladders are to be provided.

No Piles are to be salvaged. See RFP Part 3, 1.0 Project Description, Note 9. Page 310 of RFP (RFP attached).

118 This sections states, "Drawings showing locations of … material storage areas ... and stockpiles of excess soil." No material storage areas or stockpile areas are shown on the drawings, please specify where these areas are located in proximity to the job site, as well as there approximate acreage.

Reference to Concept Spec which has been replaced by RFP Spec.

119 Please confirm that location of stockpiles of excess soil will be on naval base property, i.e.

hauling trucks will not need to re-enter truck inspection hauling soil from project site to stockpile area.

Reference to Concept Spec which has been replaced by RFP Spec.

120 Drawings depict and note seven separate locations of a "bulkhead extension" under Pier 11, Boat Ramp, Pier 12, and Pier 14. There are no details or cross sections indicating what is required in these extension areas. There isn't a scope define in PART 3 Chapter 1 Please provide technical requirements for this extension, if it is required. Further details.

There are no requirements for these areas. Drawing just denoted how far the bulkheads extend past the area of work for general knowledge

121 A3 on drawing SD503 shows a 30" concrete saltwater intake pipe. Should the contractor assume this pipe is currently plugged, abandoned, and filled? This is assumed because no penetration detail was given on the new structural drawings.

For Basis of Bids, Contractor shall assume that 130 Linear Feet of 30" Diameter Concrete Pipe shall be filled with flowable fill and abandoned in place.

122 Regarding the response to PPI #89, it is understood that the final design, provided post award, will be in accordance with the current UFCs. As the proposal is based upon the current conceptual design (since a final design will be developed post award and is currently unavailable) please confirm that if a change to the conceptual design, as provided in the RFP, is required to meet the current UFCs post award, that the change will be a compensable to the contractor as it is currently unknown.

Incorrect. The concept drawings are provided for information and to give a general scope of work of the project. This is a Design-Build project. Contractor's price will include the design and the construction based upon the current UFC's and the RFP document. Changes from the Concept Drawings and Specs will not be grounds for additional compensation.

124 At the site visit a Navy employee indicated that "section 3" was very important. Can more specifics be provided as to where this is in the documents?

A summary of the project is provided in Part 3, 1.0 Project Description. Pages 309-311 of RFP.

125 The documents provided are not typical design-build bridging documents. No design requirements are specified. Will the scope of design work be made available?

See RFP. A summary of the project is provided in Part 3, 1.0 Project Description. Pages 309-311 of RFP.

126 Has the government secured any permits for this work?

LOA, ESA and EFH Concurrence, and MMPA have been supplied in Part 6 - Electronic Attachments. ACOE Permit and VMRC Permit will be provided prior to construction beginning. Contractor will be required to submit and obtain approvals from VDEQ for Erosion and Sediments Control Plans and Stormwater Permits based upon their Contractor's design.

127 Were permits secured for the work proposed in the "2017_Q_8_Concept_DWGS" file?

No, they were not.

128 Will the contractor be responsible for any permits or any renewal of existing permits?

Requirements for Annual Reporting as part of the LOA.

129 Are the firms responsible for preparation of the "2017_Q_8_Concept_DWGS" and the "1513553_SPC_1of5" files to be excluded (prohibited) from working for the contractor as the designer?

No, they are not prohibited from completing the design.

130 Is it an acceptable approach to use the "2017_Q_8_Concept_DWGS" and the "1513553_SPC_1of5" as contract documents and use the contractor's design team for Special Inspections, Submittal Review and to provide design modifications that may be required due to changed site conditions or errors/omissions in the "2017_Q_8_Concept_DWGS" and the "1513553_SPC_1of5"?

No, an updated design (via A/E firm) will need to be submitted to the Government before construction can begin.

131 These drawings appear to be "for construction" and provide detailed requirements that appear to coincide with the "Description of the work" paragraph of the General Requirements file. Is there anything in the construction scope of the solicitation that is not included in the "2017_Q_8_Concept_DWGS" ?

See RFP. A summary of the project is provided in Part 3, 1.0 Project Description. Pages 309-311 of RFP.

132 These drawings appear to be "for construction" and provide detailed requirements that appear to coincide with the "Description of the work" paragraph of the General Requirements file. Is there anything in the "2017_Q_8_Concept_DWGS" that is not included in the construction scope of the solicitation?

See RFP. A summary of the project is provided in Part 3, 1.0 Project Description. Pages 309-311 of RFP.

133 Will our survey crews be allowed to use tripod based LiDAR equipment in the area of work?

Some of this equipment takes panoramic pictures that supplement the point cloud. Would the picture taking phase need to be omitted from the process?

Yes, as long as no pictures are taken of the ships in port.

134 Is the contractor's designer required to prepare an additional specification manual, a replacement specification manual or will this one suffice for the work?

To be replaced as dictated by the RFP.

135 Is this section part of the contract documents or is it for reference or is it conceptual?

Reference and conceptual

136 In the event that our designers need to modify or replace this engineering effort will the project design analysis, calculations, review comments and responses, BIM models, permit applications and similar documentation be made available by the Navy?

All information that the Government has for the 2017 Concept Project as been provided as part of the Part 6 - Electronic Files.

137 Is preparation of DD1391 included in the scope of work?

No, 1391 has already been prepared

138 Are any additional hazardous material survey or identification efforts to be included in the scope of work?

No additional hazardous waste testing is required.

139 Probing: What length of probe is to be advanced beyond the landside face of the relieving platform, ie how far must the probe be inserted?

Given the excavation limits shown, three feet appears maximum. Please confirm or advise.

Because this is a Design Build, this will be determined by the Contractor's design and UFC requirements.

140 What quantity of flowable fill is to be included in the contract for filling voids below the relieving platform?

To be determined by Contractor's design.

141 Other than cathodic protection is there any electrical work included in the scope of construction

See RFP. A summary of the project is provided in Part 3, 1.0 Project Description. Pages 309-311 of RFP.

142 This appendix B has some borings and some test results. Will you provide the geotechnical reports for referenced projects including "2017Q8Concepts", 1981 Boat Ramp, 2002 Q8Repairs and the Appendix A design projects?

All Geotechincal information has been provided in Part 6 - Electronic Files.

143 These drawings are covered with comment bubbles that make them illegible. Will clean copies be provided?

This is best viewed via PDF.

144 How are these diagrams related to the scope of construction?

See RFP. A summary of the project is provided in Part 3, 1.0 Project Description. Pages 309-311 of RFP.

145 Are there recent hydrographic surveys of the area? Will NAVFAC obtain a hydrographic survey?

Existing depths are shown on the Concept Dwgs. Siltation rates near the bulkhead are extremely low and this data provides the approximate depths. New hydrographic survey of the entire area can be provided to the winning bidder if requested.

146 Geotechnical Data is provided, is there a finial Geotechnical Report?

All Geotechincal information has been provided in Part 6 - Electronic Files.

147 The contract drawings indicate that the soil anchors are to be drilled through the existing timber piles. The contractor assumes the drilled hole will be a minimum of 8 inches in diameter.

A “Class B” timber pile, which is typically required for this type of work, has a minimum required diameter of 14 inches. Drilling an 8-inch hole through a 14-inch pile would significantly compromise the structural integrity of the pile.

Additionally, if the existing piles are not perfectly aligned or if the soil anchor locations do not match up precisely with the center of the piles, there is a substantial risk that the pile could split or fail during drilling. Please clarify the design intent of having the soil anchors pass through the existing timber piles. Also, is there any provision or recommended course of action if an existing pile is damaged or fails as a result of this installation method?

See RFP. A summary of the project is provided in Part 3, 1.0 Project Description. Pages 309-311 of RFP.

148 The original solicitation was issued on 12 August 2025, with a site visit held on 21 August 2025.

The RFP requires Pre-Proposal Inquiries to be submitted by 1 September 2025 (ten [10] calendar days prior to the proposal due date), and the Proposal Due Date is 11 September 2025. This provides only 31 calendar days for contractors to prepare proposals for a project with a potential duration of 1,440 calendar days. The project is design-build, with the option of either “updating” the existing concept drawings or proposing a completely “new” design. Based on the responses already issued on 28 August 2025 (Amendment 004), it is evident there remains significant confusion among all parties. Additionally, the Government issued a 494-page RFP on 28 August 2025 that introduced substantial new requirements, including: electrical systems, telecommunications, and removal, storage, and reinstallation of two (2) 500-gallon fuel tanks.

Given the complexity of the project, the design-build requirements, and the recent addition of significant new scope items, the contractor respectfully requests that the proposal due date be extended by a minimum of six (6) weeks to allow adequate time for review, coordination, and preparation of a complete and responsive proposal.

The proposal due date has been extended from 11 September 2025 to 17 September 2025

149 The Government’s response to questions regarding salvaged/reuse materials appears to indicate that no existing materials are to be salvaged. Please confirm if the contractor should assume that no existing materials are to be salvaged or reused. For example, are items such as 12"x12" timber wales, chocks, and blocking required to be salvaged and reused, or should all such materials be provided new under this contract? Are there any specific materials or items that the Government requires to be salvaged and reused under this contract? If so, please identify which materials are to be salvaged for reuse, and which are to be provided new.

Timber and composite wales and chocks can be salvaged per RFP. See Part 4, Section H60, Paragraph 1.2.2.11 Salvage Material (Page 478 of the RFP).

150 Please clarify the required composite pile outside diameter for this project. The SD set calls out existing 16" Ø , while the S set calls for new 18" Ø.

Because this is a Design Build, this will be determined by the Contractor's design and UFC requirements.

151 Can the contractor assume that the designated laydown and office trailer area will remain in the same location for the entire duration of the project, regardless of the Phase/Quadrant/Bid Option under construction? Or, will the contractor be required to relocate the laydown and/or office trailer area depending on the phase of work?

See RFP, Spec Section 01 14 00, Paragraph 1.5, part a (Page 19 of the RFP).

152 General Requirements - The current bid schedule does not allow sufficient time to fully evaluate the preliminary concept drawings issued with the solicitation. A four (4) week extension is requested to conduct a detailed review, confirm design feasibility, and develop alternative solutions that may reduce project cost and improve constructability. This additional time will help ensure that bids submitted are accurate, comprehensive, and in the Owner’s best interest.

Additionally, contractors need additional time to ensure that bids are in conformance with the RFP that was provided in Amendment 004 that was issued on 8/28/25.

The proposal due date has been extended from 11 September 2025 to 17 September 2025

153 Concept Drawings - Please confirm that the contractors should use the Design Dredge Elevations shown in the typical bulkhead sections of the drawings for each of the work zones as shown in Concept Drawings S-301-304. If dredge elevations have changed since the concept was developed, please indicate what the new dredge elevations should be.

Existing depths are shown on the Concept Dwgs. Siltation rates near the bulkhead are extremely low and this data provides the approximate depths. New hydrographic survey of the entire area can be provided to the winning bidder if requested.

154 RFP - Should steel pipe piles be needed, can requirements be provided. RFP Part 4 , Section H10, H101001 1.1.9 - Steel Pipe Piles is listed as "not used".

Steel Pipe Piles cannot be used.

155 General - Are the division 01 general requirement specifications included in the “Q8_BULKHEADS_1513553_RFP” document intended to replace the division 01 specifications in the “1513553_SPC_1of5” document and all other specifications in the “1513553_SPC_1of5” document remain unchanged? The “1513553_SPC_1of5” document is still listed part

Specs Sections in RFP do replace the division 01 Specs from the Concept Spec that is provided as a Part 6 - Electronic Files.

6 attachments section of the “Q8_BULKHEADS_1513553_RFP” document.

156 What existing pavement is required to be resurfaced by bituminous overlay as the asphalt/concrete pavement within the work zone are to be demolished/replaced with asphalt/concrete pavement to grades that presumably match the existing pavement grades outside of the work zone?

No resurfacing is expected. New pavements to replace existing demolished pavements.

157 Is this referencing not putting in the new underdrain system detailed in the Civil drawings and instead putting weep holes in the new steel sheet piling? How would this relieve ground water pressures if the void between the existing & new steel sheet pile walls are to be filled with flowable fill?

Weep Holes shall be provided thru Concrete Relieving Platform and/or Concrete Seawall as determined by Contractor's design. Weep Holes will not be provided in the Steel Sheet Piling as stated in the RFP.

158 Will a new pricing schedule be provided as the quantities for the debris removal and timber pile stub removal do not match the current pricing schedule?

Quantities in Price Schedule reflect additional quantities of debris and piles stubs to be removed (for example 1B, 1C, 2A. 2B, 3A, and 3B) if they are encountered above and beyond the quantities reflected in RFP, Part 3, 1.0 Project Description, Note 7. Quantities denoted in Note 7 should be priced within Line Item 1, 2 and 3 respectively.

159 General - Are the stations for the quadrant work limits the same in the amendment 004 RFP section 01 14 00 the same as the original stations for the quadrant work limits that were listed in the original RFP section 01 14 00 as the stations for the quadrant work limits are not listed in the new amendment 004 RFP section 01 14 00?

Base Bid (between Piers 12 and 14) - Phase 1 - Station 5+90 to Station 10+21; Phase 2 - Station 10+21 to Station 14+63) Phases split this area in half. Bid Option 01 (South of Pier

12) - Phase 3 - Station 0+10 to Station 4+63. Bid Option 02 (North of Pier 14) - Phase 4 - Station 15+90 to Station 20+40;

Phase 5 - Station 20+40 to Station 25+00; Phase 6 - Station 25+00 to Station 29+40. Phases split is area in approximately thirds. Stations are depicted in Concept Dwgs.

160 Section states that all fender pile brackets and collars shall be Type 317 or 316L stainless steel.

All fender connecting bolts, anchors, nuts, washers shall be Type 316 stainless steel. Is galvanized steel an acceptable alternative to stainless steel? If so, please confirm that this also applies to RFP Part 4, Section H10, H104001.

Stainless Steel is the requirement.

161 Specification section 01 14 00, 1.1 references height restriction of cranes. What is the maximum tip elevation of a crane?

For Piers 12 and 14 - Maximum Height is 200' above grade.

162 Specification section 01 14 00, 1.4.a references the contractor laydown yard.

What is the:

1. surface area of the lot and existing condition?

2. location of the lot and is it shared with other contractor?

3.dimensions of the lot to determine fencing?

4.total number of access points?

5.routes in and out of the site? Please provide a site plan with roads allowed for construction access.

6.what utilities are available to connect to if metered separately?

See RFP, Spec Section 01 14 00, Paragraph 1.5, part a (Page 19 of the RFP). This is a laydown area that is undetermined at this time and will be until Construction begins. The area will be within 2 miles of the site which is way overdone as the true area will be as close as we can get it to the Construction Site.

Also the site (size, location, etc) will be determined on the requirements of the winning bidder's design.

163 Specification section 01 14 00, 1.4.b references operations. Please provide a site plan depicting the Limits of Construction for contractor operations/access at each quadrant.

General Limits of Construction are depicted in Concept Drawings and could vary based on Contractor's design.

165 Specification section 01 14 00, 1.6.1.2 references DBIDS badging.

1. What is the cost for an individual badge?

2. How long does it take to receive the badge?

DBIS Badging is required for all Navy Construction projects.

The cost and time to receive badges vary.

166 Specification section 01 14 00, 1.6.2 references working hours but does not define any parameters.

Can the contractor work multiple shifts 7 day per week if required?

Yes

167 Does the estimated number of calendar days as outlined on page 3 of the solicitation include the time for engineered design and owner review?

Yes

168 Concept Drawings - Please confirm the intent of the design is to stop the new bulkhead at Piers 11, 12, 14, and that installation will not go under the piers. If the new bulkhead is to be installed under the piers, what are the restrictions for limiting access to piers?

Correct. New bulkhead will not be installed under the piers.

169 Concept Drawings - What the design intent at the boat ramp location in quadrant #1?

Boat Ramp is to remain. New Bulkheads to end at face of Boat Ramp.

170 Does the estimated number of calendar days as outlined on page 3 of the solicitation include the "Holiday Berthing" required work stoppages? If so, it is requested that the required holiday work stoppage time not be counted against the contractors as that delay time is beyond their control.

Yes. It is already included in the days for construction and it doesn't prevent contractors from doing shore side work.

171 PPI 52 Response does not changes the 2 month holiday berthing schedule. Please confirm that sheet-pile installation, flowable fill behind the sheets, concrete cap construction, and fender pile installation are considered SHORE-SIDE work, if not the contractor will be shut down for 2 months and the schedule is not feasible unless you increase contract duration.

If one is working Shore-Side for these activities, that will be acceptable and not subject to the 2 month holiday berthing schedule.

172 PPI 72 Response states to be determine by KTRs design and means and methods. This is not related to design or means and methods of the contractor, this is an existing system design that must be provided by the owner. Please revise response to give the KTR a basis of bid.

Because this is a Design Build project, this will have to be investigated during design and determined by the Contractor's design

173 PPI response states "No other contracts are CURRENTLY working in these areas". Please confirm for a basis of bid that there will not be any other contracts working in these areas or provide additional defined scope if there will be contracts working in these areas.

There will be no other Contractors working in the area that Contractor is working at that time.

174 This PPI's response is not determined by the KTR's design or means and methods of construction. This is a requirement of the governments documents. Please provide a basis of bid for existing voids under the relieving platform. Please provide a volume of these voids and a length of these voids so the KTR can determine vent holes, flowable fill installation requirements to determine a cost for the basis of bid.

Because this is a Design Build project, this is to be determined by Contractor's design and UFC requirements.

176 The original spec 01 14 00 Section 3.1 stated that the government would obtain all permits within 60 CD after award. This has now been removed from the new spec 01 14 00 Section 3.1. Please confirm that it is still 60 CD after award for the government to obtain permits for the KTR. If not, please provide a time frame.

LOA, ESA and EFH Concurrence, and MMPA have been supplied in Part 6 - Electronic Attachments. ACOE Permit and VMRC Permit will be provided prior to construction beginning. Contractor will be required to submit and obtain approvals from VDEQ for Erosion and Sediments Control Plans and Stormwater Permits based upon their Contractor's design.

177 Please confirm formal partnering is required. The original spec had informal partnering.

Formal Partnering is required per the new Spec

178 Please remove all requirements associated with BIM modeling. BIM is not applicable to this project, as similar with other waterfront projects?

Agreed, BIM Modeling will not be required for this project.

179 Please confirm that the KTR is expected to reuse excavated material as backfill, if it doesn’t come up to compaction we will be paid under the unsatisfactory CLIN or the contaminated CLIN for this material, correct?

Correct. Reuse of excavated material to the maximum extent possible.

180 From amendment 004, are the division 01 general requirement specifications included in the “Q8_BULKHEADS_1513553_RFP” document intended to replace the division 01 specifications in the “1513553_SPC_1of5” document and all other specifications in the “1513553_SPC_1of5” document remain unchanged? The “1513553_SPC_1of5” document is still listed part 6 attachments section of the “Q8_BULKHEADS_1513553_RFP” document

Specs Sections in RFP do replace the division…