N4008524R2743 Amendment 0005.pdf
PDF 477 KB Posted
- Attached to
- DESIGN-BID-BUILD, LAG-105 REPLACE H SUBSTATION, NAVAL STATION NORFOLK, NORFOLK, VIRGINIA
- Solicitation number
- N4008524R2743
About this file
This document is Amendment 0005 to Solicitation N4008524R2743, which is for the Design-Bid-Build replacement of the LAG-105 substation at Naval Station Norfolk in Virginia. The amendment extends the contract completion time from 545 to 750 calendar days and provides responses to pre-proposal inquiries. Key details include:
- The contract completion time is changed from 545 to 750 calendar days.
- Responses are provided to questions on hazardous materials, site access, and contract requirements such as prohibiting the site superintendent from also serving as the SSHO or QC manager.
- The proposal due date is updated from August 5 to August 22, 2024, to accommodate a rescheduled site visit.
- This amendment is applicable to the Multiple Award Construction Contract (MACC) for Facilities Primarily in the Hampton Roads Area for specific contract numbers.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
N40085-24-R-2743
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
AMENDMENT 0005
The purpose of this amendment is to provide the following:
1. Provide the revised General Requirements reflecting revised time for completion. The contract completion days is changed from 545 calendar days to 750 calendar days.
2. Provide the responses to pre-proposal inquires.
LAG-105 Replace H Substation, Naval Station Norfolk, Virginia
Date
Submitted
Question Government
Response
07/02/24 The PPI deadline of 7/08/2024 does not allow for a site visit to take place prior to the deadline. Please consider moving this deadline and the project due date to accommodate the site visit.
The site visit was rescheduled for
7/18/2024. The
PPI deadline was updated to
7/22/2024, with a proposal due date of 05 August 2024.
07/22/24 Will the government consider allowing one person to serve as the site superintendent, SSHO, and QC manager for this project?
Refer to
Amendment 0003, Attachment A
1745518_SPECS -
pg. 84 - 1.7.1.1.1 "
The SSHO may not serve as the
Quality Control
Manager. The
SSHO may not serve as the
Superintendent."
07/22/24 1. 2 Steel drums that were labeled as hazardous waste in the fence at the LAG 105 substation. That creates 2 questions for me. Will we be responsible for the existing drums and are we to assume that any oils encountered will also be hazardous ?
No, the drum is labeled "Non-
Hazardous". The government will remove the drum(s). No, the contractor should not assume that
N40085-24-R-2743 the oils will be hazardous.
07/22/24 Will there be a Div 31 Earthwork spec? No, refer to
Earthwork Notes on sheet C-001;
General Notes on sheets C-101 through C-105 and Civil Details on sheet C-501.
07/31/24 I am getting lead time estimates on the equipment on this job and it is very possible that the lead time will be upwards of 80 weeks. That'll make the contract completion date of 545 days unattainable.
Refer to
ATTACHMENT
M - Design
Revision 2 Cover
Sheet of 31JUL24
| 24R2743 Amendment 0005 |
| 23R2656 Amendment 0001 |
| 23R2656 Amendment 0004 |
| Pages from 23R2541 Amendment 0003-2 |
Amendment 0005 continuation page
| topmostSubform[0]: |
| Page1[0]: |
| AmendmentNo[0]: 0005 |
| Code[0]: N40085 |
| Code[1]: |
| AccountingData[0]: |
| A13[0]: |
| C13[0]: |
| D13[0]: |
| NameandTitleSigner[0]: |
| NameandTitleOfficer[0]: |
| Description[0]: SEE SF 30 BLOCK CONTIUATION PAGE |
| FacilityCode[0]: |
| Code[2]: |
| IssuedBy[0]: NAVFACYSCOM MID-ATLANTIC |
PWD NORFOLK
FACILITIES ENGINEERING & ACQ DIV
9324 VIRGINIA AVENUE
NORFOLK, VA 23511-3095
| NameandAddress[0]: |
| AdministeredBy[0]: |
| ContractIDCode[0]: |
| ReqNumber[0]: |
| AmendmentNo[1]: N4008524R2743 |
| ModificationNo[0]: |
| ProjectNo[0]: |
| Page[0]: 1 |
| Pages[0]: 3 |
| EffectiveDate[0]: 07/31/2024 |
| Dated9B[0]: 06/21/2024 |
| Dated10B[0]: |
| CheckBox9[0]: 1 |
| CheckBox10[0]: Off |
| CheckBox11[0]: 1 |
| CheckBox13A[0]: Off |
| CheckBox13B[0]: Off |
| CheckBox13C[0]: Off |
| CheckBox13D[0]: Off |
| IsNot[0]: Off |
| Is[0]: 1 |
| Extended[0]: Off |
| NotExtended[0]: 1 |
| DateSigned[0]: |
| DateSigned[1]: |
| Copies[0]: 1 |
| CopiesReturned[0]: 1 |
File details come from the government source that posted it. Updated .