ATTACHMENT M - Design Revision 2-Cover Sheet.pdf

PDF 120 KB Posted

Attached to
DESIGN-BID-BUILD, LAG-105 REPLACE H SUBSTATION, NAVAL STATION NORFOLK, NORFOLK, VIRGINIA
Solicitation number
N4008524R2743
Issued by

About this file

This document is a Design Revision related to a federal contract opportunity for the Replace H Substation project at Naval Station Norfolk. The Design Revision was made in response to PPIs (Potential Problem Issues) and includes revisions to the FAR 52.211-10 clause to change the completion timeline to 750 calendar days.

The related federal contract opportunity is a solicitation for a Design-Bid-Build project to Replace the H Substation at Naval Station Norfolk. The solicitation is only open to 8(a) contractors under an Indefinite Delivery/Indefinite Quantity (IDIQ), Firm Fixed Price, Multiple Award Construction Contract. The contracting agency is the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PWD Norfolk, Facilities Engineering and Acquisition Division Form Version 2023.11.07 Page 1 of 1

Design Revision 2 eProjects Work Order Number: 1745518

Construction Contract Number:

Building: LAG-105

Project Title: Replace H Substation

Date: 31 July 2024

Design Revision Purpose

1. Response to PPIs.

PIF Revisions

FAR 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) -

ALTERNATE I (APR 1984)

https://www.acquisition.gov/far/52.211-10

Change paragraph (3) to read as follows:

“Complete the entire work ready for use not later than 750 calendar days after notice to proceed.

File details come from the government source that posted it. Updated .