Amendment0009_24R2711.pdf
PDF 76 KB Posted
- Attached to
- Replace Sanitary Sewer Lines at Pier 12 and 14
- Solicitation number
- N4008524R2711
About this file
This document is Amendment 0009 to Solicitation N40085-24-R-2711 for the replacement of sanitary sewer lines at Piers 12 and 14. The amendment extends the proposal due date to August 30, 2024 and updates the time for completion, with the base bid for Pier 12 and design work for both piers to be completed within 600 days of contract award, and the option to construct Pier 14 within 420 days after completion of the Pier 12 work. The amendment also provides for one-on-one scope meetings with offerors to gather feedback, which may result in further amendments, design revisions, or proposal deadline extensions. The solicitation is restricted to MACC holders under the Navy's Indefinite Delivery, Indefinite Quantity (IDIQ) Multiple Award Construction Contract for utility mechanical construction in the Hampton Roads, Virginia area.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0009 08/23/2024
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
NAVFACSY SCOM MID-ATLANTIC
PWD NORFOLK
9324 VIRGINIA AVENUE
NORFOLK, VA 23511-3624
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
N40085-24-R-2711
9B. DATED (SEE ITEM 11)
07/10/24
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N40085-24-R-2711 REPLACE SANITARY SEWER LINES AT PIER 12 AND 14
The purpose of this amendment is to provide the following:
1. Update the General Requirements to extend the proposal due date, time for completion, and update the Bid Schedule/Supplementary Instructions to Offerors.
2. Provide for one-on-one Scope Meetings.
Contract POC: Ashlee Beggs, ashlee.r.beggs.civ@us.navy.mil,Tel: 757-341-0564 and Kathryn Arnold kathryn.l.arnold3.civ@us.navy.mil,Tel 757-341-0554
SEE CONTINUATION PAGE(s)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA mailto:ashlee.r.beggs.civ@us.navy.mil mailto:kathryn.l.arnold3.civ@us.navy.mil
N40085-24-R-2711
Amendment 0009
SF 30 BLOCK 14 CONTINUATION PAGE
1. Update General Requirements IAW the following:
a. Proposal Due Date: Proposal due date is extended to 30 August 2024 at 1400 EDT (Due date highlighted in blue in General Requirements, attached separately).
b. Time for Completion: As described in the updated General Requirements; time for completion is amended as follows:
CLIN 0001 Base Bid – Pier 12 and ALL DESIGN both Piers: The Base Bid shall include all design for
Piers 12 and 14 and construction of Pier 12, complete, within 600 days of contract award.
CLIN 0002 Option 1 – Pier 14: Option 1 shall include construction of Pier 14, complete, within 420 days after completion of Pier 12/Base Bid work.
c. Bid Schedule/Supplementary Instructions to Offerors: See Attachment G, REV 2
2. One-on-one Scope Meetings:
Due to the receipt of feedback from multiple offerors on the scope of this project, we will be offering one-on-one meetings (in person or on Teams) with each MACC holder, if desired, to hear feedback. This feedback may or may not result in an Amendment, possible design revisions, and/or an extension to receipt of proposals.
If your firm would like to schedule a scope feedback session, please notify Ashlee Beggs, ashlee.r.beggs.civ@us.navy.mil and Kathryn Arnold kathryn.l.arnold3.civ@us.navy.mil, by email immediately, but no later than Monday, August 26, 2024 at 1400 hrs.
Once you have notified our team, we will schedule the session to be held no later than Wednesday, August 28, 2024.
(End of Summary Changes) mailto:ashlee.r.beggs.civ@us.navy.mil mailto:kathryn.l.arnold3.civ@us.navy.mil
File details come from the government source that posted it. Updated .