N4008524R2535 Amend 03.pdf
PDF 186 KB Posted
- Solicitation number
- N4008524R2535
About this file
This document is an amendment to Solicitation N4008524R2535 for a Maintenance & Repair Multiple Award Construction Contract (MACC) issued by the Department of the Navy Naval Facilities Engineering Command.
The amendment provides responses to several RFI questions, including information about the FAPIIS certification, file size limitations, project details (270-day duration, $880/day liquidated damages, $250,000-$500,000 estimated cost range), and past performance requirements (CPARS or PPQ). It clarifies that the correct Construction Experience Project Data Sheet form to use is Attachment C. The anticipated start date for the seed task order is 15 days from contract award with a 270-day duration. A site visit attendance roster has also been provided.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFIC T ON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO.
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLIC TION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 3
AMENDMENT NO. 0003 4/15/24
5. PROJECT NO. (If applicble) 20-0005
N40085
NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1005 Michael Road Camp Lejeune, NC 28547-2521
See Item 6
✘ N40085-24-R-2535
3/27/24
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
22-0005, Building AS2818 Head Repairs Amendment 0003 - RFI responses
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
See Continuation Page(s) Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
N40085-24-R-2535 Amendment 0003
CONTINUATION SHEET
1. Question: Page 8 of Solicitation paragraph 4.5 (vi) FAPIIS Certification. What information are we supposed to provide in our proposal for this section?
Answer: The instructions provided in FAR 52.209-7(d) specify that required information be posted through the Offeror’s active registration in the System for Award Management (https://sam.gov). A copy of the FAPIIS response page from SAM can be provided as part of the Offeror’s proposal.
2. Question: Can the file size be increased higher than 1.9MB for our electronic proposals? Due to all the documentation the government is asking for.
Answer: No this is a system constraint of the PIEE Solicitation Module.
3. Question: Can the number of days to perform the Seed Project, the dollar amount of liquidated damages and the estimated cost range for the project be provided by Amendment?
Answer: Days for completion is 270 days. Liquidated damages are $880 per calendar day. The estimated project range is $250,000 to $500,000.
4. Question: Section 00 21 00 – Instructions, Factor 4 – Past Performance requires submission of a CPARS evaluation or a completed PPQ to be submitted with the proposal response. If a CPARS evaluation is not available, will NAVFAC accept previously completed PPQs if completed copies are submitted with our response (not incorporated by reference)? The submission of existing completed PPQs will relieve the burden on our references to complete separate PPQs for each procurement.
Answer: Yes.
5. Question: Section 00 21 00 – Instructions, Factor 1 – Corporate Experience states, “The attached Construction Experience Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project information.” However, the Attachment C file provided references “Attachment 5” at the top of the document. Please confirm this is the correct form to use for Factor 1.
Answer: Attachment C is the correct file. Disregard the typo referencing “Attachment 5” at the top of the document.
6. Question: What is the anticipated start date and project duration or end date for seed task order?
N40085-24-R-2535 Amendment 0003
Answer: The anticipated start date is 15 days from award of a contract. Project duration is 270 days.
7. The site visit attendance roster has been provided.
8. All other terms and conditions remain unchanged.
File details come from the government source that posted it. Updated .