This document summarizes responses to pre-proposal inquiries (PPIs) for solicitation number N4008523R2887 to renovate the lab building facility at building 603 at NAS Oceana in Virginia Beach, Virginia. The Navy seeks to award a firm-fixed price contract to supply and install a new 100kW diesel generator, 400A automatic transfer switch, and perform building renovations. Key requirements include supplying the generator, ATS, and associated control equipment; installing all equipment; performing on-site testing including load bank testing; and providing training. The contractor must complete all work within 540 calendar days of the notice to proceed. The receipt of proposals remains due by November 10, 2023 at 2:00PM EST and the contractor is required to meet Buy American and seismic restraint standards.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

J

PAGE OF PAGES

1 5

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

27 Oct-2023

4. REQUISITION/PURCHASE REQ. NO.

ACQR6004886

5. P ROJECT NO.(If applicable)

6. ISSUED BY CODE N40085 7. ADMINISTERED BY (If other than item 6) CODE

NAVFACSYSCOM MID-ATLANTIC

D OCEANA

FACILITIES ENGINEERING & ACQ DIV

953 HORNET DR SUITE 213

VIRGINIA BEACH VA 23460-2190

See Item 6

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION

NO. N40085-23-R-2887

X 9B. DATED (SEE ITEM

11) 27-Sept-2023

10A. MOD. OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue ofthis amendment you desire to change an offer already submitted, such change may be made by telegramor letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES T HE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. T HIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO T HE AUT HORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORT ANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SOLICITATION N40085-23-R-2887, RENOVATE LAB BUILDING FACILITY, BLDG 603, NAS OCEANA, VIRGINIA BEACH, VA

The purpose of this amendment is to answer Pre-Proposal Inquiries (PPI's) and to add technical changes.

The Receipt of Proposal due date remains unchanged at 10 November 2023 at 2:00PM EDT.

SEE CONTINUATION PAGE.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

TEL: EMAIL:

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

27 October-2023

EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

30-105-04 ST ANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N40085-23-R-2887

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

SOLICITATION N40085-23-R-2887, RENOVATE LAB BUILDING

FACILITY, BLGD 603, NAS OCEANA,VIRGINIA BEACH, VIRGINIA

PRE-PROPOSAL INQUIRIES

PPI#9

QUESTION: 26 32 15 Advise if seismic is required.

RESPONSE: Seismic restraints is not required per UFGS 01 45 35

PPI#10

QUESTION: 26 32 15 Advise if Buy American is required.

RESPONSE: Yes, Buy American is required

PPI#11

QUESTION: 26 32 15 Is there a project schedule for completion.

RESPONSE: Dates were provided in the solicitation. Complete the entire work ready for use not later than 540 calendar days after notice to proceed. The following schedule will be adjusted per the award date:

Phase Description Scheduled Start Day Completion Date

Non-Permanent

Trailers 10/2/23 12/31/23

1 Lab 12/31/23 5/9/24

2 Building 5/9/24

3/25/25

PPI#12

QUESTION: 26 32 15 (2.1.6 )- States corrosion resistant enclosure which technically painted steel is corrosion resistant. Is painted steel acceptable or is aluminum enclosure required? There is also an enclosure section 2.20.1 for the enclosure which states steel.

RESPONSE: Please conform to enclosure requirements as stated in section 2.20.1 in Specification 26 32 15.00.

PPI#13

QUESTION: 26 32 15 (2.19 )- Generator Control Panel is digital via LED Screen (there are no dial type gauges in production). Confirm this is acceptable.

RESPONSE: Digital is acceptable.

PPI#14

QUESTION: 26 32 15 (2.27) - References extensive factory testing including High Pot Tests, Insulation Resistance testing, Winding Resistance testing, etc. Is all of this required for this small of a machine or would a standard 0.8PF Test with Report from the factory suffice since there is also on-site testing being performed. Please advise.

RESPONSE: Please conform to requirements as stated in the specification section.

PPI#15

QUESTION: 26 32 15 Throughout the specs there are multiple requests for 6 sets of "X" in 3-ring binders, and 3 sets of "Y" in 3 ring binders etc. Is all of this required, or would electronic versions of the needs suffice?

RESPONSE: Provide as required by the specifications

PPI#16

QUESTION: 26 32 15 (3.4 )- Onsite Inspection and Tests - List items like oil and fuel piping flushes, cable insulation integrity testing, ground resistance testing, Dynamometer Testing, Regulator range Testing, tank draining testing etc etc which is the bottom of page 40 thru 61. For the 100kW generator only, is the industry standard NFPA110 Resistive Loadbank Test acceptable? Testing as it's currently listed will multiple days and cost thousands of additional dollars to perform.

RESPONSE: Please conform to requirements as stated in the specification section.

PPI#17

QUESTION: 26 32 15 (3.4.1.3) - States the Contractor shall supply all equipment needed for on-site testing. Please clarify whether the generator manufacturer shall provide the load bank equipment for testing.

RESPONSE: This is a contractor means and methods. It is the contractors discression where they procure the load bank for testing.

PPI#18

QUESTION: 26 32 15 (3.10) - Advise if more than one 2-hours onsite training session is needed (i.e. 3 sessions at site for 2-hours each).

RESPONSE: Provide the training hours as stated in Specification 26 32 15 section 3.10.

PPI#19

QUESTION: Specs have sections that define a need (Installation, site testing for two examples) in multiple areas of the specs. For example, Installation is mentioned in 3.2, 3.3 and 3.11 too, On-site testing is mentioned in 3.4 and 3.7 and then a final testing section 3.12 as well. Many of the needs in these sections are redundant. Are we to base our pricing on all sections we see in the specs?

RESPONSE: Please conform to requirements as stated in the specification section.

PPI#20

QUESTION: 26 36 23 Advise if Bypass/Isolation is required. Not mentioned on one-line E-601 however there are several areas in the specs that mention Bypass/Isolation.

RESPONSE: During the design phase, we sent an RFI asking NAVFAC if Bypass/Isolation Switch was required. NAVFAC confirmed that it was not a requirement.

PPI#21

QUESTION: 26 36 23 Advise on the required ATS size needed (not listed on one-line E-601).

RESPONSE: The ATS size is 400Amps.

PPI#22

QUESTION: 26 36 23 Confirm the required ATS enclosure type is NEMA1.

RESPONSE: A NEMA 250, Type 1 enclosure is required per section 2.2.a in Specification 26 36 23.

PPI#23

QUESTION: 07 42 29 (2.2.9.a –e) (A501 Details B3 & B4 ) The specifications call for a clip and sub-girt support system yet the details show what amounts to a thermally broken system at the horizontal member. Is there a thermal member (Knight Wall, SMART-ci, Cascadia Clip, Nvelope etc.) being used here or can we provide our standard horizontal sub-girt/adjustment angle with thermal isolator?

RESPONSE: The rain-screen assembly is to be provided as a complete system as prescribed by selected manufacturer. Completed system to achieve both manufacturer's and installer's warranty as specified in 07 42 29 1.7. Components within the rain screen assembly to meet the performance and warranty criteria established within the specification. Alternate assemblies are acceptable if all other performance criteria are met.

PPI#24

QUESTION: 7 42 29 (2.2.3.b) (A521 Detail D2) The specifications call for silicone gaskets at the vertical carriers. Would a pvc spacer be acceptable? We have found with our various external façade systems that the EPDM gasket is significantly stronger and less prone to tearing than a silicone gasket of the same shape. EPDM can be blended to have a wide range of shore hardness and with the designed shape aid deflection recovery. When inserting a terracotta tile the gaskets can roll but the EPDM designed gasket is less likely to tear from the tile retaining aluminium clips. The aluminium clip with EPDM gasket is hidden from the external elements and will have a long-term performance life similar to silicone.

RESPONSE: The rain-screen assembly is to be provided as a complete system as prescribed by selected manufacturer. Completed system to achieve both manufacturer's and installer's warranty as specified in 07 42 29 1.7. Components within the rain screen assembly to meet the performance and warranty criteria established within the specification. The use of EPDM gasket as an alternate is acceptable if all other criteria are met.

TECHNICAL CHANGES

1) Specification Section 26 32 15

a. REMOVE 2.19 in its entirety.

b. REPLACE 2.19 with the following:

“Provide panel as specified in paragraph PANELS and provide controls, gauges, meters, and displays to include:

A. Frequency meters, digital or dial type, with a range of 90 to 110 percent of rated frequency. Do not use vibrating-reed type meters . One must monitor generator output frequency ("Generator Frequency Meter") and the other must monitor the frequency of the parallel source ("Bus Frequency Meter").

B. Voltmeters, ac, digital or dial type, 3-phase, with 4-position selector switch for the generator output ("Generator Volt Meter") and for the parallel power source ("Bus volt meter").

C. Automatic synchronizer.

D. Manual synchronizing controls.

E. Indicating lights for supplementary indication of synchronization.

F. Synchroscope.

G. Wattmeter, indicating.”

2) Specification Section 26 36 23

a. REMOVE 2.1.b in its entirety.

b. REPLACE 2.1.b with the following:

“Amperage: 400 amps ac. Provide an ATS with a continuous load current rating of the switch rating.”

3) Sheet E-601 Detail A2 Single-Line Diagram

a. REPLACE ATS-1 description with the following:

“SERVICE ENTRANCE (SE)

RATED, 4-POLE, 400A