AMENDMENT_0001_N4008523R2887_B603.pdf

PDF 426 KB Posted

Attached to
RENOVATE LAB BUILDING FACILITY, BLDG 603 NAS OCEANA
Solicitation number
N4008523R2887
Issued by

About this file

This document contains an amendment to a solicitation for the renovation of a laboratory building facility at Naval Air Station Oceana in Virginia Beach, Virginia. The Navy is seeking proposals to renovate Building 603, including replacing exterior cladding, windows, roofing, and mechanical systems. The solicitation number is N4008523R2887. The receipt of proposals deadline remains November 10, 2023 at 2:00 PM EST. The amendment provides responses to eight contractor questions, clarifies technical specifications around insulation installation, vapor barriers, and panel finishes, and replaces language in the special maintenance warranty agreement attachment.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

J

PAGE OF PAGES

1 4

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

25 Oct-2023

4. REQUISITION/PURCHASE REQ. NO.

ACQR6004886

5. P ROJECT NO.(If applicable)

6. ISSUED BY CODE N40085 7. ADMINISTERED BY (If other than item 6) CODE

NAVFACSYSCOM MID-ATLANTIC

D OCEANA

FACILITIES ENGINEERING & ACQ DIV

953 HORNET DR SUITE 213

VIRGINIA BEACH VA 23460-2190

See Item 6

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION

NO. N40085-23-R-2887

X 9B. DATED (SEE ITEM

11) 27-Sept-2023

10A. MOD. OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue ofthis amendment you desire to change an offer already submitted, such change may be made by telegramor letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES T HE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. T HIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO T HE AUT HORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORT ANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SOLICITATION N40085-23-R-2887, RENOVATE LAB BUILDING FACILITY, BLDG 603, NAS OCEANA, VIRGINIA BEACH, VA

The purpose of this amendment is to answer Pre-Proposal Inquiries (PPI's) and to add technical changes.

The Receipt of Proposal due date remains unchanged at 10 November 2023 at 2:00PM EDT.

SEE CONTINUATION PAGE.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

TEL: EMAIL:

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

25 October-2023

EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

30-105-04 ST ANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N40085-23-R-2887 0001 Page

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

SOLICITATION N40085-23-R-2887, RENOVATE LAB BUILDING

FACILITY, BLGD 603, NAS OCEANA,VIRGINIA BEACH, VIRGINIA

PRE-PROPOSAL INQUIRIES

PPI#1

QUESTION: We have downloaded the project documents and the design drawings are missing. Please provide.

RESPONSE: Drawings are posted on SAM

PPI#2

QUESTION: The General Requirements states that "Attachments" includes Attachment B Wage Determination VA20230167 Dated 01/13/2023. This wage determination is not included in the RFP documents. Please provide.

RESPONSE: Wage Determination VA20230167 01/13/2023 is posted on SAM

PPI#3

QUESTION: The General Requirements states that "Attachments" includes Attachment A Scope of Work. The Attachment A Scope of Work is not included in the RFP documents. Please provide.

RESPONSE: The SOW is located in the Specifications Volume 1- General Requirements

PPI#4

QUESTION: Spec section 08 51 13, Aluminum windows, 1.8.5.1 states that this is North-Central climate zone 4 with a U-value of 0.36. This is incorrect, as this project is located within South-Central climate zone 3. International Energy Climate Code (IECC) and ASHRAE, table C402.4 states that U-value requirement for zone 3 is .060 for operable fenestration and 0.46 for fixed fenestration. Please provide clarification.

RESPONSE: Use fenestration performance values from ASHRAE 90.1-2016 for climate zone 3A (per

ASHRAE 169).

PPI#5

QUESTION: Please clarify panel profile for metal wall panels, soffit panels, and perforated panels RESPONSE: 07 42 13 1.3 calls for 'panel profiles to match length, height, and depth profile as terracotta panels. Refer to 07 42 29 TERRACOTTA RAIN SCREEN for full product description'. 07 42 29 2.2 specifies terracotta panels to have a length of 60 inches, height of 15.75 inches, and thickness of 1.18 inches. 07 42 13 2.2.2.5 specifies metal panels to match approved terracotta panel finish while 07 42 29 2.1.6 specifies terracotta panels are to 'closely match Federal Standard 2778 from manufacturer's standard color. Once final selection of terracota panels has been approved metal panels are to be finished to match that of the terracotta. Refer also to Exterior Finish Legend for exterior cladding on A-201. Soffits and ceilings where shown in the drawings are to comply with 09 54 23, refer to 2.1.1 Metal Panel Units for profile and finish. 05 72 00 refers to the mechanical screen assembly; see 2.2.5 2.2.6 for requirements.

PPI#6

QUESTION: Please clarify color of metal wall panels, soffit panels, and perforated panels; specs call to match terracotta while drawings call clear anodized and white.

RESPONSE: 07 42 13 1.3 calls for 'panel profiles to match length, height, and depth profile as terracotta panels. Refer to 07 42 29 TERRACOTTA RAIN SCREEN for full product description'. 07 42 29 2.2 specifies terracotta panels to have a length of 60 inches, height of 15.75 inches, and thickness of 1.18 inches. 07 42 13 2.2.2.5 specifies metal panels to match approved terracotta panel finish while 07 42 29 2.1.6 specifies terracotta panels are to 'closely match Federal Standard 2778 from manufacturer's standard color. Once final selection of terracota panels has been approved metal panels are to be finished to match that of the terracotta. Refer also to Exterior Finish Legend for exterior cladding on A-201. Soffits and ceilings where shown in the drawings are to comply with 09 54 23, refer to 2.1.1 Metal Panel Units for profile and finish. 05 72 00 refers to the mechanical screen assembly; see 2.2.5 2.2.6 for requirements.

PPI#7

QUESTION: Drawings call for roof insulation to be adhered and fastened, please clarify.

RESPONSE: Install total tickness of insulation with mechanical fasteners per 07 22 00 3.3.1. with total assembly meeting the specified wind uplift criteria and otherwise approved attachment by the roof membrane manufacturer. Reference to adhesion will be removed from details.

PPI#8

QUESTION: Please clarify the vapor barrier/retarder. Drawings only show it in one roof type, specs mention 2 ply and setting vapor retarder in asphalt on insulation. Please advise.

RESPONSE: Of the three roof types, Roof Type 1 is the only assembly over conditioned spaces. No vapor barrier desired or required in other roof types. Remove the base sheet under insulation that is shown mechanically fastened to deck. The type vapor barrier shall be amended to become a fiber glass-reinforced, polyethylene surfaced, self-adhering SBS vapor barrier applied directly to deck surface.

TECHNICAL CHANGES

1) Revision to specification section 07 52 00 ATTACHMENT – SPECIAL MAINTENANCE:

a. DELETE in its entirety:

Part 6 – SPECIAL MAINTENANCE WARRANTY AGREEMENT

b. REPLACE with the following:

Attached Part 6 – SPECIAL MAINTENANCE WARRANTY AGREEMENT.

2) Sheet A-501 Detail A3

a. DELETE note in its entirety:

The note “FASTENED BASE SHEET” should be removed from detail.

b. REPLACE note “2” with the following:

POLYISO RIGID INSULATION, ADHERED AND FASTENED, MIN R-10” should be revised to read “2” POLYISO RIGID INSULATION, FASTENED, MIN R-10”

3) Sheet A-501 Detail A4

a. DELETE note in its entirety:

The note “FASTENED BASE SHEET” should be removed from detail.

b. REPLACE note “2” with the following:

0001 Page 3 of 4

POLYISO RIGID INSULATION, ADHERED AND FASTENED, MIN R-10” should be revised to read “2” POLYISO RIGID INSULATION, FASTENED, MIN R-10”

4) Specification Section 07 22 00

a. REPLACE 2.3.1.1 with the following:

“Fiber Glass-Reinforced, Polyethylene Surfaced, Self-Adhering SBS Vapor Barrier Provide in accordance with ASTM D 5147, having a thickness not less than 47 mil (1.2mm).”

b. ADD to 1.1 References:

ASTM D5147/D5147M-14 Standard Test Methods for Sampling and Testing Modified Bituminous Sheet Material

c. REMOVE 2.3.1.2 in its entirety.

d. REPLACE 3.2 with the following:

“Install vapor barrier in direct contact with roof deck surface. Unless otherwise specified, vapor barrier to consist of fiber glass-reinforced, polyethylene surfaced, self-adhering modified bitumen.

Stagger end laps and overlap side laps by a minimum of 3.” End laps should have a minimum of 6” overlap. At end laps on steel decks, a 6 x 39.5” metal plate should be installed to support the lap between the deck ribs. Remove release liner at an angle to expose adhesive surface. Roll membrane after installation with a minimum 75 lb. roller. The entire surface should be rolled, side and end laps to be rolled with a hand roller as well to ensure full contact.”

e. REMOVE 3.2.1 in its entirety.

0001 Page 4 of 4