1502000 – Facility Investment
SECTION F: DELIVERIES OR PERFORMANCE
DELIVERABLES
Annex/ Spec Item Form Attachment Number
| Deliverable Title |
| Date (s) of Submission |
| Distribution |
| Frequency |
| Original/ Copies |
| Number of Copies (including original) |
1502000/ 2.2.1
| N/A |
| Certification and Licenses |
| Within 15 days after award or as requested by the KO |
| KO |
| 1 |
| Once for initial submittal, then as requested |
1502000/
| N/A |
| Monthly Critical Equipment Availability Report |
| First work day of each month |
| KO |
| 2 |
| Monthly |
1502000/ 3.1
| N/A |
| Critical Spare Parts List |
| Within 15 days prior to contract start and as requested by the KO |
| KO |
| 2 |
| Once for initial submittal, then as requested |
1502000/ 3.1
| N/A |
| Service Order Summary Report |
| First work day of each week |
| KO |
| 2 |
| Weekly |
1502000/ 3.1
| N/A |
| Completed Service Orders updated in USMCMax |
| As specified |
| KO |
| 2 |
| As specified |
1502000/ 3.2
| N/A |
| Preventive Maintenance Program Plan |
| 30 calendar days after contract award |
| KO |
| 2 |
| Annually |
1502000/ 3.2
| N/A |
| Critical Spare Parts List |
| Within 15 days prior to contract start and as requested by the KO |
| KO |
| 2 |
| Once for initial submittal, then as requested |
1502000/ 3.2
| N/A |
| Monthly PM Work Schedule |
| Five work days prior to the beginning of each month |
| KO |
| 1 |
| Monthly |
1502000/ 3.2.1
| N/A |
| Schedule for changing Paint Booth and Make-Up Filters |
| At contract start and the first work day of each option period |
| KO |
| 2 |
| Annually |
1502000/ 3.2.5
| N/A |
| Dynamometer Calibration Program |
| At contract start and the first work day of each option period |
| KO |
| 2 |
| Annually |
1502000/ 3.2.6
| N/A |
| Hydraulic Test Bench Calibration Program |
| At contract start and the first work day of each option period |
| KO |
| 2 |
| Annually |
1502000/ 3.3
| Inspection, Testing, and Certification Program Plan |
| 30 calendar days after contract award |
| KO |
| 2 |
| Annually |
1502000/ 3.3
| N/A |
| Inspection, Testing, and Certification Program Summary Report |
| First work day of each month |
| KO |
| 2 |
| Monthly |
1502000/ 3.3
| N/A |
| Inspection, Testing and Certification Schedule and Equipment Certifications |
| First work day of each month |
| KO |
| 2 |
| Monthly |
1502000/ 3.3.1
| N/A |
| Certification of Load Test and Condition Inspection Form |
| First work day of each month |
| KO |
| 2 |
| Monthly |
1502000/ 3.3.3
| N/A |
| Calibration Program |
| At contract start and the first work day of each option period |
| KO |
| 2 |
| Annually |