Amendment 05.pdf

PDF 161 KB Posted

Attached to
N40085-20-R-0044 Repair LP Area Runway + ILS Installation
Solicitation number
N40085-20-R-0044
Issued by

About this file

This amendment modifies a solicitation for a design-build-bid project at Naval Station Norfolk to repair a runway and install instrument landing system equipment. The amendment provides responses to 15 pre-proposal inquiries, clarifying aspects of the work such as the depth of existing pavement, use of stainless steel or ceramic-coated bolts for fixtures, and protection of lights during milling and paving operations. A design revision attached adds notes on pavement sections, manhole adjustments, and bolt specifications. The related federal contract opportunity is a full and open competition solicitation by the Navy to repair a limited-use area runway and support instrument landing system installation through demolition, site preparation, construction, pavement and signage work. The period of performance is June through December 2020.

View the file

Other files

Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

DESIGN-BID-BUILD; REPAIR LP AREA RUNWAY + ILS INSTALLATION, NAVAL STATION NORFOLK, VA

The purpose of this Amendment is to address Pre-Proposal Inquiries 1-15, and to provide Design Revision 1. The proposal date is NOT extended.

POC: Quin Conerly-Anderson; quin.conerly-anderso@navy.mil; 757-341-0089

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Apr-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008520R0044

X 9B. DATED (SEE ITEM 11)

12-Mar-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Apr-2020

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008520R0044

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 05

The purpose of this Amendment is to provide the following:

1. Responses to PPI 1-15

PPI

Date

Submitted

Reference

Question Responses PROJECT Page

Section Paragraph

1 03/24/20 ILS

INSTALLATION

SUPPORT

DWG

ES108

Indicates new TW lights installed in existing PCC at north area delta TW.

Are we to remove only the concrete required for installation of ductbank per detail C1, dwg ES501 or are we required to remove the whole square inside the joints?

Yes. Refer to civil drawing sheets CD101 and CD102 for removal of concrete pavement to install new TW lights.

2 03/24/20 ILS

INSTALLATION

SUPPORT

DWG

ES108

Regarding trench for TW lights-Will a detail be provided as to how the trench is to be repaired (dowels, rebar, ect..)? If I have overlooked this detail, please provide drawing # detail is located.

Refer to civil drawing sheets CS101, CS102 and C-501 (Detail D2 and C4) for how trench to be repair and details.

3 03/24/20 ILS

INSTALLATION

SUPPORT

DWG

ES108

What is the depth of the PCC at the north area delta taxiway?

See Design Revision 01, which adds a note describing assume pavement section of 11" PCC over 11" cracked and seated concrete in the north area delta taxiway.

4 03/24/20 ILS

INSTALLATION

SUPPORT

DWG

ES101

Is the work associated with the demo of TW lights and circuit to be included in Clin

0001AC?

Yes. Work associated with of TW lights and circuits to be included in Clin 0001AC.

5 03/24/20 ILS

INSTALLATION

SUPPORT

DWG

ES108

Is the work associated with the new TW lights and ductbank to be included in Clin

0001AC?

Yes. Work associated with TW lights and ductbank to be included in Clin 0001AC.

6 03/24/20 REPAIR LP

AREA

RUNWAY 10-28

DWG

CD100-

CS103

Is the work associated with the RW centerline lights to be applied to Clin 0001AA or Clin 0001AG? Please clarify.

Yes. Work associated with RW centerline lights to be applied to CLIN

0001AA.

7 03/24/20 REPAIR LP

AREA

RUNWAY 10-28

DWG

CD100

Demo Keynote #8- Are we to remove and reset the manhole (EMH-4) to grade or are we to cut the top and set at proper grade? If we are to remove/reset, can you provide the size of this manhole?

See Design Revision 01, which revises Demo Keynote #8 to clarify top of manhole will be cut to meet proposed elevation and to provide assumed dimensions. New Work Keynote #17 is revised to ensure finished grade is flush with lowered structure cover.

8 03/24/20 REPAIR LP

AREA

RUNWAY 10-28

DWG C-

265620 2.5 Note 10 states to provide stainless steel bolts and stainless steel 2 piece washers.

Spcification 265620-

2.5 states ceramic fluoroploymer coated bolts and 2 piece locking washers. Are we to use stainless steel bolts or ceramic fluoropolymer coated bolts for fixtures in pavement?

See Design Revision 01, which revises Light Fixture Protection Note #10 to use ceramic-metallic fluoropolymer coated grade 2 bolts for fixtures in pavement.

9 03/24/20 REPAIR LP

AREA

RUNWAY 10-28

DWG

CD101-

Demolition Keynote 11 states: refer to Clin 0001AD Guidance Sign replacement for airfield signage work consisting of airfield sign

See Design Revision 01, which deletes the Clin 0001AD reference from Keynote 11 on Sheets CD101-CD103. Sign work included in the Guidance Sign Replacement drawings removal, replacement ect..

The Bid Form indicates Clin 0001AD is for partial depth repair in concrete. Please clarify what work, if any, is to be quoted for the existing signs and the Clin this work will apply.

will be priced with the Planned Modification:

Airfield Signange Electrical Improvements.

10 03/30/20 We are a NAVAIDS subcontracor and we are interested in bidding this job. Is there a list of Contractors bidding this job?

Please refer to beta.sam.gov for the published Interested Vendors List.

11 03/31/20 4-7 of 50 Is this solcitation a small business set aside?

No. Paragraph 1.1 on Page 4 of 50 in Solicitation states, 'This acquisition is being solicited on an unrestricted basis, with Full and Open Competition.

12 03/31/20 7-8 of 50 Is the prime contractor expected to meet all of the Factor 1 corporate experience solicitation requirements?

Please refer to factor 1 of the Solicitation.

13 03/31/20 REPAIR LP

AREA

RUNWAY 10-28

DWG

CD101

THRU

VOL 2

OF 4

Drawings indicate asphalt removal in the no-taxi area, these areas have signs with foundations in the areas to be demoed.

How are these foundations to be supported considering the removal depth?

The expectation is that the Guidance Sign Replacement work (referenced in Demo Keynote 11) will consist of removing existing signs and associated foundations located in these no-taxi areas. The Guidance Sign Replacement work is listed as a "Planned Modification: Airfield Signage Electrical Improvements" in the Price Proposal Form.

14 03/31/20 REPAIR LP

AREA

RUNWAY 10-28

DWG

CD101 &

VOL 2

OF 4

Drawings indicate milling of the RW shoulders. Used Google Earth to view the shoulders.

The RW edge lights appear to have a 5' x

See Design Revision 01, which revises Airfield Light Fixture Note #2 on Sheet C-001 to allow alternate methods of repaving around existing edge lights. Where

5' patch around the fixture. Are the RW edge lights required to be removed for milling over the fixture base or will the milling operation cease at the patch?

exisitng grades will remain, milling operations may cease at the fixure apron edge or patch.

Where grades will be adjusted, Contractor may select means and methods to protect lights while meeting paving specification requirements.

Please note that Airfield Light Fixture Note #2 on Sheet C-001 applies to edge and approach lights, not runway centerline lights.

15 03/31/20 ILS

INSTALLATION

SUPPORT

DWG

S001

THRU

S104

Vol 1 of 2

Micropile contractors are requesting a Geotechnical Report for the locations the micropiles are to be installed. No report is provided in the bid documents. Will a Geotechnical Report be provided?

No Geotechnical Report will be provided. Typical subsurface profiles based on historical data are provided on Sheet S-001 for use in designing the micropiles. The typical subsurface profiles include but are not limited to Soil Classification, Unit Weight, Depth of Groundwater, and Average N value.

2. Attachement I - 1607816 Design Revision 01

(End of Summary of Changes)