N40085-19-R-9243 0003.pdf
PDF 199 KB Posted
- Solicitation number
- N4008519R9243
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N40085-19-R-9243 0005.pdf | ||
| ELINS J-0200000-17 Revised.xlsx | XLSX spreadsheet | |
| 1502000 C Revised.docx | DOCX document | |
| N40085-19-R-9243 0004.pdf | ||
| J-0200000-17-ELINs Revised.xlsx | XLSX spreadsheet | |
| N40085-19-R-9243 Site visit List of Attendees.pdf | ||
| N40085-19-R-9243 0002.pdf | ||
| N40085-19-R-9243- 0001.pdf | ||
| SECNAV_ 5512_1.pdf | ||
| J- 1501000.pdf | ||
| J-0200000-17-ELINs.xlsx | XLSX spreadsheet | |
| J-1502000.pdf | ||
| J- 0200000.pdf | ||
| N40085-19-R-9243 RFP.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
REGIONAL MAINTENANCE OF EMERGENCY GENERATORS AND HVAC EQUIPMENT
This Amendment is issued to incorporate a revised Section M - Factor 3 - Safety and the Site Visit List of Attendees.
All other terms and conditions remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Jan-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9243
X 9B. DATED (SEE ITEM 11)
20-Dec-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Jan-2020
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9243
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 03
Section M
The following have been added by full text:
BASIS FOR AWARD
M.1 BASIS FOR AWARD
a. The Government will select the lowest-price technically acceptable offer at a reasonable cost to the Government.
M.2 EVALUATION FACTORS
1. The solicitation requires the evaluation of price and the following non-price factors:
Factor 1 – Technical Approach/Management Factor 2 – Corporate Experience Factor 3 – Safety Factor 4 – Past Performance
Offerors must be evaluated as technically ACCEPTABLE under factors 1, 2, 3 and 4 in order to be considered technically acceptable overall.
NOTE: The distinction between corporate experience and past performance is corporate experience pertains to the types of work and volume of work completed by a contractor that are comparable to the types of work covered by this requirement, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.
In order to permit efficient competition, the Navy will utilize the following methodology: Proposals will initially be screened for price and placed in order of price (lowest priced to highest price). The Navy will then evaluate the technical factors of the lowest priced proposal. The Navy will make award to the lowest priced technically acceptable proposal. However, if the lowest priced proposal is not found to be technically acceptable, the Navy, at its sole discretion, reserves the right to increase the number of proposals it will review, until the Navy identifies a technically acceptable proposal. Accordingly, under this methodology, the non-price factors of some proposals may not be evaluated by the Navy. If discussions are deemed necessary by the Contracting Officer, all proposals will be evaluated (both technical and price) for the purpose of establishing a competitive range.
1. An overall non-price factors rating must be at least “ACCEPTABLE” in order to be eligible for award. An “UNACCEPTABLE” rating in any factor results in the overall non-price factors proposal rating of “UNACCEPTABLE” unless corrected through discussions. An overall non-price factors rating of “UNACCEPTABLE” makes a proposal ineligible for award.
b. Technical proposals will be evaluated to ensure the offeror understands the requirements of the solicitation in accordance with the following descriptions of each evaluation factor
(1) Factor 1, Technical Approach/Management:
(i) Solicitation Submittal Requirements: The offeror shall submit a narrative response that clearly demonstrates its understanding of and approach to accomplishing the complexity and magnitude of service requirements set forth in the performance objectives and standards of the Performance Work Statement. Each of the topics below must be included in the narrative and tabbed in the technical proposal and discussed separately.
a. Phase-In Transition Plan. Describe what you will do to “start-up” for performance of this contract. The phase in transition period is 30 days as per F.2 of the RFP. Include a schedule of key events; personnel actions, identification of key personnel and their responsibilities.
b. Workforce Management.
(1) Describe the lines of management authority, supervision, span of control and accountability, including the relationship between overall management (corporate and on-site), administration, and subcontractors.
(2) Demonstrate your ability to provide and maintain a qualified workforce.
(3) Demonstrate your ability to manage different workforces and competing priorities at various sites.
(4) Describe the work to be performed as the prime contractor as well as the work to be performed by each subcontractor proposed. The work to be self-performed, subcontractors to be utilized and their roles shall be clearly identified. If the prime will self-perform 100% of the work, it shall be clearly stated. Additionally, Offeror must meet the requirements of FAR 52.219-14, Limitation on Subcontracting and submit AttachmentJ-0200000-20 (Contractor’
Self-Performance Certification and Notification of Subcontracting), as part of this Factor.
c. Quality Management. Provide a two-page summary (single-sided pages) of your “Quality Management System” i.e. the Quality Processes (Practices, Resources and Activities) and minimum controls that will be used to ensure full compliance with all performance objectives and standards as described in Section C Annex 0200000 Management and Administration. Include the methodology to be implemented to accomplish the performance requirements and detail how the proposed approach will effectively achieve each performance objective and standard.
(ii) Basis of Evaluation: The Technical Approach/Management factor shall be evaluated based upon the following criteria:
a. The proposal demonstrates an acceptable understanding of the performance objectives and standards.
b. The proposal demonstrates a thorough plan for having equipment and personnel in place to commence work on the contract start date.
c. The proposal provides a feasible technical approach with the capability to, at least, meet solicitation performance objectives and standards.
(2) Factor 2, Corporate Experience:
(i) Solicitation Submittal Requirements: The Offeror shall submit the following information:
Submit a minimum of one (1) and a maximum of five (5) relevant projects, where the offeror served as the Prime Contractor that are similar in size, scope, and complexity to the work requirements specified in the solicitation.
For projects submitted, experience of proposed subcontractors will not be considered. Likewise, the Offeror’s experience as a subcontractor will not be considered.
Size, scope, and complexity are further defined as follows:
Size: A maintenance service contract with a yearly value of at least $900K or greater for recurring services. Indefinite Quantity/Indefinite Delivery values for non-recurring work will not be considered similar in size.
Scope: Demonstrate the ability to provide maintenance and repair services of Auxiliary Generators, Generator Fuel System, Transfer Switch, Integrated maintenance Program (IMP), HVAC and Refrigeration Systems, HVAC Water Testing and Treatment Services, Temperature Controls Systems, Auxiliary Generators and Power Distribution Equipment, compressed Air Systems, Direct Digital Controls, Electrical, Uninterruptible Power Systems (UPS) and Tanks. Routine Service Orders, Emergency Service Orders, and Preventive Maintenance and other services that may be typical of a generator maintenance contract.
Complexity: Demonstrate the ability to respond simultaneously to service calls (routine, urgent, and emergency) and maintenance requirements for repair, alteration, and minor construction at various locations and buildings throughout the installation and supporting annexes. Demonstrate the ability to manage competing priorities in order to support customer demands.
The attached Corporate Experience Form (J-0200000-18) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page (or two (2) single-sided pages).
Projects submitted for the Offeror shall be ongoing and /or completed within the past five (5) years of the date of issuance of the solicitation; dates beyond one year shall be clearly defined as multi-year contracts or base contracts with options years. If the project has option periods, state which option period is in progress, if applicable.
For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP as it relates to size, scope, and complexity.
If the Offeror is a Joint Venture (JV), relevant project experience shall be submitted for projects completed by the Joint Venture entity. If the Joint Venture itself does not have the required experience, projects shall be submitted for each Joint Venture partner. For a JV, the offeror shall provide the signed U.S. Small Business Administration (SBA)- approved Joint Venture Agreement or an SBA-approved Mentor-Protégé Agreement as part of this Factor. Failure to submit an SBA-approved Agreement will result in the relationship being considered as Prime/Subcontractor, and the prime contractor will not be found acceptable on the basis of the subcontractor’s experience only. Offerors are still limited to a total of five (5) projects combined.
If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF33), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract. The meaningful involvement shall be described in detail.
The assessment of the offeror’s relevant experience will be used as a means of evaluating the capability of the offeror to successfully meet the requirements of the RFP. As noted above, to be deemed acceptable under this factor, the offeror must submit at least one (1) relevant project, where the offeror served as the prime contractor (similar size, scope and complexity as the current requirement). The prime contractor will not be found acceptable on the basis of its subcontractor’s experience. Likewise, the Offeror’s experience as a subcontractor will not be considered.
(ii) Basis of Evaluation:
The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing relevant projects as defined in the solicitation submittal requirements. The assessment of the Offeror’s relevant experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. The Government will only review five projects. Any projects submitted in excess of the five (5) for Experience will not be considered.
(3) Factor 3, Safety:
(i) Solicitation Submittal Requirements: The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each contractor who is part of the partnership or joint venture; however, only one safety narrative is required. EMR, DART and TRC Rates shall not be submitted for subcontractors.)
(1) Experience Modification Rate (EMR): Submit the last three previous complete calendar years’ worth of data. This rate compares company’s annual losses in insurance claims against its policy premiums. The offeror may submit an insurance company-provided equivalent rate if no EMR exists. If the offeror has no EMR or premium, for any year, the offeror must affirmatively state so and an explanation must be provided. Any extenuating circumstances that affect the EMR and negative trends must be addressed as part of the factor submission.
(2) OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate: Submit last three previous complete calendar years’ worth of data. If an offeror cannot submit an OSHA DART, for any year, the offeror shall affirmatively state so and an explanation must be provided. Any extenuating circumstances that affected the OSHA, DART data negatively must be addressed as part of this factor submission.
(3) OSHA Total Recordable Case (TRC) Rate: Submit last three previous complete calendar years’ worth of data. If an offeror cannot submit an OSHA TRC rates for any year, the Offeror must affirmatively state so and an explanation must be provided. Any extenuating circumstances that affected the OSHA TRC rate data negatively must be addressed as part of this factor submission.
(4) Offeror shall submit a separate OSHA 300A form for each of the last three complete calendar years.
(5) Technical Approach for Safety: Describe the plan for safety that will be implemented to evaluate safety performance and vet potential subcontractors as part of the selection process for all levels of subcontractors. The offeror is required to address this whether or not it intends to self-perform the work. The offeror shall submit a narrative that fully describes the safety management system that they will use to oversee the safety compliance and performance of self-performed and subcontractor performed work. The offeror will describe any innovative methods that will be employed to ensure and monitor safe work practices at self-performed and/or all subcontractor levels.
Additionally, the contactor will describe their methodology to execute an effective program that facilitates sound mishap prevention techniques and processes, employee reporting of unsafe conditions, unsafe activities, and near-miss mishaps. The technical approach to safety narrative shall be limited to two pages.
(ii) Basis of Evaluation: The evaluation will collectively consider the following:
- Experience Modification Rate (EMR)
- OSHA Days Away from Work, Restricted Duty, or Job Transfer
(DART)
- Total Recordable Case (TRC) Rates
- Offeror Technical Approach to Safety
- Other sources of information available to the Government
(1) Experience Modification Rate (EMR): Submit the last three previous complete calendar years the offeror will submit EMR. If no EMR exists, the offeror may submit an insurance company-provided equivalent rate explaining why not. If an insurance company-provided equivalent rate is provided, it will be treated the same as an EMR. Any extenuating circumstances that affected the EMR and negative trends should be addressed as part of this selection factor. The board will evaluate the EMR to determine if the offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.
(2) OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate. Submit the last three previous complete calendar years, the offeror must submit their OSHA DART as defined by the U.S.
Department of Labor, Occupational Safety and Health Administration.
If unable to submit OSHA DART, the offeror shall affirmatively state so, and an explanation must be provided. Any extenuating circumstances that affected the OSHA DART rate data and negative trends should be addressed as part of this element. The board will evaluate the OSHA DART Rate to determine if the offeror has demonstrated a history of safe work practices taking into account any upward trends and extenuating circumstances that impact rates.
(3) OSHA Total Recordable Case (TRC) Rate: Submit last three previous complete calendar years’ worth of data. If an offeror cannot submit an OSHA TRC rates for any year, the Offeror must affirmatively state so and an explanation must be provided. Any extenuating circumstances that affected the OSHA TRC rate data negatively must be addressed as part of this factor submission.
(4) Offeror shall submit a separate OSHA 300A form for each of the last three complete calendar years.
(5) Technical Approach to Safety: The offeror will describe their plan to evaluate their safety performance and vet potential subcontractors.
Also, describe any innovative methods that the offeror will employ to ensure and monitor safe work practices at all subcontractor levels. The Safety Narrative shall be limited to two pages. The board will evaluate the narrative to determine the degree to which subcontractor safety performance will be considered in the selection of all levels of subcontractors on the upcoming project. The board will evaluate the narrative to determine the degree to which innovations are being proposed that may enhance safety on this procurement and validate the contractor has addressed methodology to be used in the execution of an effective program that facilitates sound mishap prevention techniques/processes, employee reporting of unsafe conditions, unsafe activities, and near-miss mishaps. Those offerors whose plan demonstrates a commitment to hire subcontractors with a culture of safety and who propose innovative methods to enhance a safe working environment may be given greater weight in the evaluation.
(6) Other Sources of Information Available to the Government: Other sources for safety may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS) in Enterprise Safety Applications Management System (ESAMS), Contractor Performance Assessment Reporting System (CPARS) and other related databases.
(4) Factor 4, Past Performance:
(i) Solicitation Submittal Requirements: Offerors shall clearly demonstrate a history of successful performance within the past five (5) years of the date of issuance of the solicitation. The offeror shall be the prime contractor on a minimum of one (1) up to a maximum of five (5) relevant contracts of similar size, scope and complexity to the RFP as defined in Factor 2, Corporate Experience. The prime contractor will not be found acceptable on the basis of a subcontractor’s past performance. Additionally, the prime contractor’s experience as a subcontractor will not be considered.
IF A COMPLETED CPARS EVALUATION IS AVAILABLE, IT SHALL BE
SUBMITTED WITH THE PROPOSAL. IF THERE IS NOT A COMPLETED CPARS
EVALUATION, the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 2, Corporate Experience. AN OFFEROR
SHALL NOT SUBMIT A PPQ WHEN A COMPLETED CPARS IS AVAILABLE.
IF A CPARS EVALUATION IS NOT AVAILABLE, ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment C), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Mrs. Jurmin Francis-Ross, via email at jurmin.francis-ross@navy.mil prior to proposal closing date.
Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
Also include performance recognition documents received within the last five (5) from the date of issuance of the solicitation, such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition.
In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/Entity Identifier numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), and any other known sources not provided by the offeror.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
A copy of the blank Past Performance Questionnaire to be used for requesting client references is included as Attachment J-0200000-19.
(ii) Basis of Evaluation: The degree to which past performance evaluations and all other past performance information reviewed by the Government (e.g., PPIRS, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), performance recognition documents, and information obtained from any other source) reflect a trend of satisfactory performance considering:
- A pattern of successful completion of tasks;
- A pattern of deliverables that are timely and of good quality;
- A pattern of cooperativeness and teamwork with the Government at all levels (task managers, contracting officers, auditors, etc.); and
- Recency of tasks performed that are identical to, similar to, or related to the task at hand
(c) Price Proposal:
(1) Solicitation Submittal Requirements: Offerors shall submit one (1) original and one (1) copy of the price proposal, in a separate three ring binder, that shall include the following:
- Signed Solicitation, Offer and Award Forms (SF 33), including Section B (CLINs 0001through 0010), with all amendments acknowledged.
- Exhibits A through E (Attachment J-0200000-17)
- Copy of Representations and Certifications and proof of registration in
System of Award Management (SAM).
- Confirm submission of the most recent Vets 4212 Report.
- Provide name of financial institution, point of contract, telephone number and email address. Provide a signed statement of release giving the reference permission to release the information to the Navy.
- In addition to providing hard copies of the price proposal (original and copy), offerors shall also provide one (1) non-rewritable CD with pricing information. Offerors are advised that in the event of a discrepancy between the original, copy, and CD, the original hard copy will govern.
The price proposal shall be submitted separately but at the same time as the technical proposal. Any non-price information in the price proposal will not be considered. Likewise, any price information in the non-price proposal will not be considered.
(2) Basis of Evaluation: The Government will evaluate price based on the total price. Total price consists of the basic requirements and all option items (see Section B of the solicitation). The Government intends to evaluate all options and has included the provision FAR 52.217-5, Evaluation of Options (JUL 1990) in Section M of the solicitation. In accordance with FAR 52.217-5, Evaluation of Options will not obligate the Government to exercise the option(s). Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
(i) Comparison of proposed prices received in response to the RFP.
(ii) Comparison of proposed prices with the IGCE.
(iii) Comparison of proposed prices with available historical information.
(iv) Comparison of market survey results.
Proposals will be evaluated for completeness and reasonableness as follows:
(1) Completeness. All pricing information required by the solicitation has been provided, all mathematic computations are correct and the pricing application understood, prices are on an “all or none” basis, and failure to submit a price on an item or a number of items may cause this factor and the entire offer to be determined unacceptable.
(2) Reasonableness. Price analysis comparisons indicate the offered price to be fair and reasonable, balanced across option years, and balanced between fixed-price and IDIQ items.
Unreasonable, unbalanced or incomplete pricing may cause a proposal to be determined unacceptable.
(End of Summary of Changes)